AI summaryCambridge Joint Development Management Committee approves by 9 to 1 the demolition of six science park buildings and erection of four research and development buildings, retaining Unit 216, subject to conditions and a Section 106 agreement.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to conditions and Section 106 agreement
Money£316m per year GVA estimatedPlus £256m earning potential and 28.89% biodiversity net gain
What happens nextS106 agreement completion and EIA expiryPrior to issuing planning permission, per decision wording
Who it affectsCambridge Science Park, MiltonSite wholly within South Cambridgeshire District, parish of Milton
What was decided
Approve application 24/04575/FUL for the demolition of units 210, 211, 214, 220, 230 and 240 and redevelopment with four Use Class E(g) buildings, retention of Unit 216, basement car and cycle parking, access, landscaping and supporting infrastructure, known as The Fenway. Report P5, 3.1, 1.1
Approval is subject to the planning conditions and informatives in the officer report, with delegated authority to officers for minor amendments and any others considered appropriate, and to the prior completion of a Section 106 Agreement under the Town and Country Planning Act 1990 covering the Heads of Terms in the report. Report 1.6
Officers recommend the buildings deliver approximately 4,650 jobs, an uplift of about 4,150, with offices, lab space, food and beverage, co-working, mobility hub and amenity floorspace across 99,272 sqm GIA. Report 3.9, 14.4, P40, 13.12, 13.20, 13.22, 13.26
Why
Officers found the principle of redevelopment acceptable under South Cambridgeshire Local Plan Policies E/1 and E/9, with efficient reuse of previously developed land and significant weight to economic growth under paragraph 85 of the NPPF, supported by the government Case for Cambridge and the Minister for Housing and Planning's August 2024 open letter. Report 12.5, 12.6, 12.7, 12.8, 12.9
The design is considered high quality, with stepped terraces, articulated facades and landscaped roofscapes, subject to conditions on materials, roof plant, landscaping and phasing. Landscape, townscape and built heritage impacts are acceptable in policies HQ/1, NH/14, SC/9 and under the Planning (Listed Buildings and Conservation Areas) Act 1990. Report 13.39, 16.12, 16.18
The scheme delivers 28.89 percent biodiversity net gain using Natural England's Biodiversity Metric 3.1, with new publicly accessible landscape, lakeside improvements and a wildlife corridor. Health Impact Assessment meets the HIA SPD policy at grade A. Report 7.10, 14.2, 15.3
What happens next
Officers will finalise the Section 106 Agreement covering the Heads of Terms in the report, with delegated authority to negotiate, settle and complete it. Report 1.6
After the EIA site and press notice expiry and the S106 completion, the planning permission can be issued, with delegated authority to officers for minor amendments to conditions and informatives.
The development will be phased, with Buildings A and B first to deliver the underground car park. Conditions will secure materials, roof plant, drainage, landscaping, travel plan, foul water strategy, construction management, employment and skills delivery, and the standard biodiversity net gain condition. Report 13.37, 13.38, 7.8, 7.9, P103
The money
£316m per year Estimated Gross Value Added from the development Report 12.4
£256m Earning potential of new employees Report 12.4
28.89% Biodiversity Net Gain using Natural England's Biodiversity Metric 3.1
Options considered
Chosen: Approve the application subject to conditions and a Section 106 Agreement. Officers considered the scheme compliant with Policies E/1, E/9, HQ/1, NH/14 and SC/9, with acceptable landscape, transport, drainage and heritage impacts, and significant economic and community benefits including around 4,650 jobs. Report 1.6, 12.9, 13.39, 16.18
Rejected: Refuse the application. Not formally presented as an option; officers recommended approval and the committee voted 9 to 1 to approve. Report 1.6
Implications
Legal: A Section 106 Agreement under the Town and Country Planning Act 1990 must be completed before the permission is issued, and the EIA site and press notice must expire, in line with Regulation 26 and 29 of the EIA Regulations 2017. Report 6.6, 6.14
Financial: Estimated £316m per year Gross Value Added to the economy and around 4,650 jobs once operational, with about 375 construction phase jobs and Cambridge Living Wage required of the main contractor. Report 12.4, 14.4, 14.13
Risk: Anglian Water has a holding objection citing insufficient wastewater treatment capacity at the existing Cambridge Water Recycling Centre, with feasibility of options expected to conclude by June 2026. A foul drainage condition is recommended to require a strategic foul water strategy. Report 7.2, 7.3, 7.4, 7.8, 7.9, P103
Equalities: The Disability Panel highlighted external seating options, safe access and movement, inclusive design and Changing Places provision. Health Impact Assessment is assessed as grade A under the HIA SPD. Report 7.26, 7.10
Environment and climate: 28.89 percent biodiversity net gain, landscape-led design with publicly accessible space and lakeside improvements, drainage restricted to 6.9 litres per second, and buildings designed to WELL Building Standard Platinum aspiration. Report 7.14
15 October 2025: Joint Development Management Committee resolves by 9 votes to 1 to approve subject to conditions and S106 Agreement
By June 2026: Anglian Water feasibility review of options to increase wastewater capacity at the existing Cambridge Water Recycling Centre expected to conclude Report 7.3
Plain English for the jargon
Section 106 Agreement: A legal agreement under the Town and Country Planning Act 1990 between a developer and a local planning authority, used to secure planning obligations such as financial contributions or affordable housing.
Environmental Impact Assessment (EIA): A process to assess the likely significant environmental effects of certain projects, required under the Town and Country Planning (Environmental Impact Assessment) Regulations 2017.
Biodiversity Net Gain (BNG): An approach leaving biodiversity in a measurably better state than before a development, calculated using Natural England's Biodiversity Metric.
Use Class E(g): A use class covering offices, research and development, and light industrial processes that can be carried out in a residential area without detriment to amenity.
Gross Internal Area (GIA): The total floor area measured to the internal face of the perimeter walls of a building.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/22/JDMC
Resolved
Resolved (by 9 votes to 1) to approve application 24/04575/FUL subject to: (a) the planning conditions and informatives set out in the officer report to committee with delegated authority to officers to carry through minor amendments to those conditions and informatives (and to include others considered as appropriate and necessary) prior to the issuing of the planning permission, and: (b) the prior completion of a Section 106 Agreement under the Town and Country Planning Act 1990 with delegated authority to officers to negotiate, settle and complete such an Agreement as referenced in the Heads of Terms within this report, including any other planning obligations considered appropriate and necessary to make the development acceptable in planning terms and the expiry of the EIA site and press ... view the full minutes text for item 25/22/JDMC
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Lead Officer: Joint Director of Planning and Economic Development
Ward/parish: Milton
Proposal: Demolition of existing units 210, 211, 214, 220, 230, 240 and redevelopment with Use Class E(g) floorspace (office) (E(g)(i)), research and development (E(g)(ii)) with complementary floorspace (Use Class E (a-g)) along with access, landscaping and supporting infrastructure. Retention of Unit 216.
Applicant: Brockton Everlast
Presenting officer: Mike Huntington
Reason presented to committee: The provision of a non-residential building where the GIA floor space to be created is 1,000m2 or more and the site is more than 1 hectare.
Member site visit date: 13 October 2025
Key issues: 1. Principle of development
2. Amount and design
3. Mitigation – transport, drainage, landscaping, ecology Recommendation: Approve subject to conditions and S106
Report contents
Document section Document heading 1 Executive summary 2 Site description and context 3 The proposal 4 Relevant site history 5 Policy 6 Environmental Impact Regulations 7 Consultations 8 Third party representations 9 Member representations 10 Local groups 11 Assessment 12 Principle of development 13 Masterplan concept, building design, scale and landscaping 14 Community benefits 15 Landscaping, trees and biodiversity 16 Landscape and townscape effects 17 Carbon reduction, sustainable design and potable water use 18 Drainage, flood risk and foul water management 19 Highway safety and transport impacts 20 Cycle and car parking provision 21 Construction and environmental health impacts 22 Third party representation 23 Other matters 24 Planning obligations (S106)
1.1The application proposes the demolition of six buildings and the redevelopment of the site to provide 4 larger buildings, together with the retention of one existing building on the site.
1.2The scheme proposes to remove much of the surface car parking and replace it with underground car parking.
1.3Most of the space between the buildings will become landscaped space, available for both employees and members of the public to use.
1.4The buildings will be designed so that they can be used for general laboratory use and will contain other uses on the ground floor such as food and beverage open to the wider public.
1.5The lake to the south of the site will be improved and made more accessible to members of the public.
1.6Officers recommend that the Joint Development Management Committee APPROVE the application subject to the planning conditions as set out in Section 29 below, with any minor amendments to the conditions as drafted delegated to officers, and the completion of a s106 agreement which includes the Heads of Terms set out in Section 23 below with any minor amendments to the Heads of Terms as set out delegated to officers.
2. Site description and context
2.1The site is wholly within the boundary of South Cambridgeshire District Council and is located to the north of Cambridge within the Cambridge Science Park (CSP), which is in the parish of Milton.
2.2The site is a little over 5 hectares in size. The redline area of the site includes land for the proposed off-plot cycle route improvements to the CSP, site access connections (providing new and also closing existing access points), underground drainage connections, and improvements to the southern lake.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Development Management Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
25/04604/FUL 1 Kings Meadow, CambridgeResolved (by 7 votes to 0, with 2 abstentions) to approve application 25/04604/FUL subject to the planning conditions...
Election of Chair and Vice-ChairResolved by 10 votes to 2 that Councillor Porrer be elected as Chair for the ensuing year. Councillor Porrer took ove...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.