25/02161/FUL Christs College, St Andrews St

Decided Planning 3 papers

AI summaryCambridge Planning Committee grants permission for Christ's College library redevelopment on St Andrews Street, voting 4 to 2 in favour despite heritage concerns.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedBy 4 votes to 2, per officer recommendation
MoneyNot stated
What happens nextSubject to conditionsDelegated authority to officers for minor amendments
Who it affectsChrist's College, Market WardCity centre Cambridge, conservation area

What was decided

The committee resolved to grant planning permission in accordance with the officer recommendation, subject to recommended conditions and the revisions on the amendment sheet.

Officers were given delegated authority to make minor amendments to the conditions as drafted.

Why

The application was referred to committee because it raises complex planning considerations relating to significant heritage assets. Report P7

Officers found the heritage impact neutral overall, with lower end less than substantial harm to the Grade I listed Bodley Library offset by conservation area enhancements. Report 1.11, 6.8, 11.4

No statutory consultees objected to the development subject to conditions. Report 1.14

What happens next

Planning permission will be issued subject to the conditions set out in the officer report and amendment sheet.

S106 contributions will be sought towards public realm improvements at and near Christ's Lane. Report 6.26

Options considered

  • Chosen: Grant planning permission per officer recommendation. Compliant with Local Plan policies, neutral heritage impact overall, public realm benefits Report 11.9

Implications

  • Legal: Section 106 contributions are sought towards public realm improvements at and near Christ's Lane. Report 6.26
  • Equalities: Accessibility of the college is to improve with level access provided throughout Bath Court and the new library. Report 1.13
  • Climate: Sustainability credentials to improve through renewable energy integration and fabric improvements in the replacement building. Report 1.12
  • Risk: Conditions imposed on construction noise, dust, contamination, surface water drainage, and arboricultural protection. Report 6.23, 6.31
  • Other: Lower end less than substantial harm identified to the setting of the Grade I listed Bodley Library. Report 1.11, 6.8

Who and where

  • Christ's College students and staff Report 1.3, 3.2
  • Residents of Christ's Lane apartments Report 2.3, 12.4
  • Pedestrians using Christ's Lane public right of way Report 2.3, 12.12
  • Visitors to the Historic Core conservation area Report 1.2, 1.10

Timeline

  • 13th February 2025: Design Review Panel meeting held Report 1.5
  • 19th May 2025: Member briefing held Report 1.6
  • 28th August 2025: Re-consultation with 15 working days sent following amendments Report 3.7
  • 11th September 2025: Development Control Forum meeting held Report 1.6
  • 27th October 2025: Member site visit conducted Report P8
  • 29th October 2025: Planning Committee decision made

Plain English for the jargon

  • DRP: Design Review Panel
  • DCF: Development Control Forum
  • LBC: Listed Building Consent
  • S106: Section 106 planning obligation for developer contributions
  • TPO: Tree Preservation Order
  • TVIA: Townscape and Visual Impact Assessment
  • LLFA: Lead Local Flood Authority
  • P&G: Historic Park and Garden designation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/93/Plan

Resolved

Resolved (by 4 votes to 2) to grant the application for planning permission in accordance with the Officer recommendation, for the reasons set out in the Officer’s report, and subject to the conditions recommended by the Officer (with delegated authority to Officers to make minor amendments to the conditions as drafted) including the revisions on the amendment sheet.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Planning

25/02161/FUL – Christ’s College Library, St Andrews Street, Cambridge

Application details Report to: Planning Committee

Lead Officer: Joint Director of Planning and Economic Development

Ward: Market

Proposal: Demolition of 1970’s library and replacement with new library and social and study spaces and including re-provision of bridge to the Bodley Library. Alterations to kitchen, Upper Hall and adjacent areas including new plant, access improvements and alterations to WC provision in the SE range of Second Court. Re- landscaping of Bath Court and ancillary works. Installation of temporary kitchen and dining facility in Second Court for the duration of the works.

Applicant: [name removed] officer: Dominic Bush

Reason presented to committee: Officer referral based on the fact that the application raises complex planning considerations relating to significant heritage assets.

Member site visit date: 27th October 2025

Key issues: 1. Character and Appearance 2. Heritage Impact 3. Residential / Public Amenity 4. Highway Safety Recommendation: Approve subject to conditions

Report contents Document Document heading section 1 Executive summary 2 Site description and context 3 The proposal 4 Relevant site history 5 Policy 6 Consultations 7 Third party representations 8 Local groups / petition 9 Planning background 10 Assessment 11 Principle of development 12 Design, layout, scale and landscaping 13 Trees 14 Heritage assets 15 Carbon reduction and sustainable design 16 Biodiversity 17 Water management and flood risk 18 Highway safety and transport 19 Cycle and car parking provision 20 Amenity 21 Other matters 22 Third party representations 23 Planning obligations (s106) 24 Planning balance 25 Recommendation 26 Planning conditions Table 1 Contents of report

1. Executive summary 1.1 The application seeks planning permission for the demolition of the existing library and its replacement with a contemporary library including social and study space. Further internal and external alterations are proposed including a replacement bridge between the Bodley Library and a temporary kitchen dining facility during the duration of the works.

1.2The application site falls within the Historic Core conservation area with the Christ’s College (College) buildings surrounding the First Court being Grade I listed and the entire college grounds being a designated Historic Park and Garden. The application site is located within the city centre of Cambridge and immediately abuts the public highway of Christ’s Lane to the southeast with the modern Christ’s Lane redevelopment including a mix of retail and residential units on the opposite side of this footpath.

1.3The predominant aspect of this scheme is the demolition and replacement of the existing 1970’s library build that serves the College. This building is deemed to not be fit for purpose, with insufficient study spaces, poor accessibility and lack of sufficient insulation. This has led to the College wanting to improve the library facilities for its students and this planning application coming forward.

1.4This application follows two previous consents on the site for the replacement of the existing 1970’s library. Whilst both have since expired and differ from the current proposal, this application seeks to re-establish the principle of a replacement library in this location to meet the current day needs of the students.

1.5The proposals have been subject to extensive pre-application discussions with officers and relevant consultees, both internally and externally to evolve the design to its current proposed form. This pre-application process included a Design Review Panel (DRP) on the 13th February 2025 in which positive feedback supporting the proposal was received (Appendix 1)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25-02161-FUL Appendix 2 DCF Minutes /93/PlanMinutes 210 KB Download
PDF
25.02161.FUL Appendix 1 DRP Report /93/PlanAppendix 5.2 MB Download
PDF
25/02161/FUL Christs College, St Andrews StReport 544 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
MS
Councillor Martin SmartChair, present
KT
Councillor Katie ThornburrowVice-Chair, present
RD
Councillor Robert DrydenCommittee Member, present
IF
Councillor Ingrid Flaubert Lib Dem (Spokes)Committee Member, present
TG
Councillor Tim GriffinCommittee Member, apologies
MH
Councillor Matthew Howard Green (Spokes)Committee Member, present
BI
Councillor Bob IllingworthCommittee Member, present
MT
Councillor Mike Todd-JonesCommittee Member, present
NB
Councillor Naomi BennettReserve, in attendance

On this subject at Cambridge

Search all
  1. 25/02161/FUL Christs College, St Andrews StThis decision
  2. 16/0405/FUL - Christs College, St Andrews StreetAgreed

More from Cambridge Planning

All decisions
MeetingDecisionOutcome
4 Nov 2026 26/02186/FUL Coldham's Common, Pool Way, Whitehill RoadResolved (by 7 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 25/04187/FUL Hanover Court and Princess CourtResolved (by 4 votes to 3) to grant the application for planning permission in accordance with the Officer recommenda... Agreed Open
24 Jun 2026 25/03323/FUL 73 Newmarket RoadResolved (4 votes to 4 – and on the Chair’s casting vote) to grant the application for planning permission in accorda... Agreed Open
24 Jun 2026 26/01081/FUL 9, 11, 15 and 17 Ashfield RoadResolved (by 6 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open
24 Jun 2026 26/01400/FUL 1, 2, 3, 4, 11, 12 The GreenResolved (by 5 votes to 0) to grant the application for planning permission in accordance with the Officer recommenda... Decided Open