Cambridge City Council
Joint Development Management Committee, Wednesday 19 November 2025 at 10.00am

25/00016/FUL Trinity Hall Farm Industrial Estate

Approved Committee 4 papers

AI summaryCambridge approves Trinity Hall Farm Industrial Estate redevelopment for offices, labs, retail and cafe, by 8 votes to 1, subject to conditions and a Section 106 agreement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved8 votes to 1, subject to conditions and S106
MoneyS106 obligations to followSpecific sums not stated in papers
What happens nextS106 agreement to be completedThen planning permission issued
Who it affectsTrinity Hall Farm Industrial EstateEast Chesterton ward, Cambridge

What was decided

Application 25/00016/FUL was approved, subject to the planning conditions and informatives in Section 28 of the officer report, with delegated authority to amend conditions in consultation with the Chair and Vice Chair.

Conditions 10, 15, 16, 20, 24, 31 and 40 were updated at committee, including changes to re-planting timescales, DCEMP school access, water metering, and correcting 'project' to 'protect'.

Approval is also subject to completion of a Section 106 Agreement under the Town and Country Planning Act 1990, and to a reasoned conclusion on EIA effects with notifications under regulations 29 and 30 of the 2017 EIA Regulations.

Why

Officers considered the principle of office and lab-enabled redevelopment acceptable under Local Plan Policies 2, 14, 15, 40 and 41, supporting Cambridge's knowledge economy in the Cambridge Northern Fringe East Area of Major Change. Report 12.4, 12.7, 12.13, 2.8

The scheme is estimated to deliver c.300 construction jobs, c.1,750 operational jobs, and a GVA contribution of £53m in the construction phase and £87.9m operational. Report P139, P140, 12.6

The design approach was supported by the Urban Design Officer and Cambridgeshire Quality Panel as a sophisticated gateway scheme, with massing stepped to respect nearby residential context. Report 6.26, 6.38, 13.21, 13.29

What happens next

Officers to negotiate, settle and complete a Section 106 Agreement covering employment and skills, affordable workspace, transport mitigations, public art, and monitoring fees, before permission is issued. Report P110, P111

Officers to issue a reasoned conclusion on environmental effects and carry out notifications under regulations 29 and 30 of the EIA Regulations 2017.

A Grampian-style condition will restrict occupation until a strategic foul water solution is confirmed with Anglian Water, whose objection stems from lack of capacity at Cambridge Water Recycling Centre. Report 1.6, 6.7, 6.8, 6.9

The money

  • £53m Estimated net additional GVA contribution during construction phase Report 12.6
  • £87.9m Estimated net additional GVA contribution during operational phase Report 12.6
  • 2.6 l/s Agreed surface water discharge rate into Anglian Water 375mm surface water network Report 6.12, P82

Options considered

  • Chosen: Approve subject to conditions and Section 106 Agreement (officer recommendation). Development complies with planning policy, brings economic benefits, and subject to conditions addresses consultee concerns Report P12, 1.10
  • Rejected: Refuse. One member voted against; no detailed reason given in the papers

Implications

  • Financial: Applicant commits to financial contributions towards County Highways schemes in the NEC area, plus affordable workspace, employment and skills, and public art, secured via Section 106. Report 1.7, P110, P111
  • Legal: Permission is conditional on completion of a Section 106 Agreement and compliance with EIA Regulations 2017, including regulations 26, 29 and 30. Report P61, P65
  • Equalities: Greater Cambridge Access Officer welcomed improvements including a changing places toilet, with minor comments on seating, doorways, colours and signage addressed at design stage.
  • Climate: Development targets net-zero carbon with all-electric heating/cooling, BREEAM Excellence, a 65% improvement over the 2018 Wat 01 baseline, and biodiversity net gain exceeding the 10% statutory minimum. Report 1.5
  • Risk: Anglian Water holds a holding objection due to lack of wastewater capacity at Cambridge WRC; addressed through a Grampian-style occupation condition, with Anglian Water feasibility review expected by June 2026. Report 1.6, 6.7, 6.8, 6.9
  • Staffing: Estimated c.300 construction jobs and c.1,750 operational jobs at full occupation, with 150 construction jobs expected to be taken up by city residents. Report P139, P140
  • Other: Environmental Statement covers air quality, landscape and visual, noise and vibration, surface water drainage and hydrogeology, townscape, transport and water resources; an ES Addendum was submitted in June 2025. Report P59, P66

Who and where

  • East Chesterton ward residents, including properties on Milton Road and Gainsborough Close Report P4, 2.6
  • Existing businesses on the industrial estate, to be demolished and redeveloped Report P5, 2.2, 12.10
  • Future office and lab tenants, plus onsite affordable workspace users Report 12.4, P111
  • Cyclists and pedestrians using Milton Road, the Guided Busway and Nuffield Road Report 3.7, 13.14, 13.15
  • Cambridge Past Present and Future and Cambridge Cycling Campaign, who submitted representations Report P123, P124, 9.2, P126

Timeline

  • 3 July 2024: Second Cambridgeshire Quality Panel review Report 10.2
  • 08/01/25: 120 neighbouring properties notified by letter
  • 16/01/2025: Site notices posted near the site Report 6.2
  • 13 June 20025: Minor application amendments received and re-consulted Report 6.4
  • 1 September 2025: Anglian Water updated its consultation response to a holding objection
  • 17 November 2025: Member site visit Report P9
  • 19 November 2025: Joint Development Management Committee decision to approve
  • By June 2026: Anglian Water feasibility review on Cambridge WRC capacity expected to conclude Report 6.8

Plain English for the jargon

  • GIA: Gross Internal Area, a measure of total floor space within a building.
  • Section 106 Agreement: A legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations from a developer.
  • Grampian condition: A planning condition that restricts development or occupation until a specified off-site matter is resolved.
  • BREEAM Excellence: A high rating under the Building Research Establishment Environmental Assessment Method for sustainable buildings.
  • EIA Regulations 2017: Town and Country Planning (Environmental Impact Assessment) Regulations 2017, governing environmental assessment of certain developments.
  • Use Class E(g)(i) and E(g)(ii): Town planning use classes covering offices, and research and development uses.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/28/JDMC

Resolved

Resolved (by 8 votes to 1) to approve application 25/00016/FUL subject to: (a) the planning conditions and informatives as set out in Section 28 of the planning officer’s report with delegated authority to carry through amendments to those conditions and informatives (including additional / revised conditions as appropriate and necessary) in consultation with Chair and Vice Chair of Committee prior to the issuing of planning permission. With the following updates to the planning conditions: · Updates to conditions 15, 16 and 31 as outlined in the amendment sheet. · Update to condition 24 to change the word ‘project’ to ‘protect’. · Updates to the following conditions as agreed by Members at Committee: i. Update to condition 10 – timeframe for re-planting; ii. Update to condition 40 – take account of school access times and routes in the DCEMP; iii. Update to condition 20 – provision of commercial water metering data. (b) the prior completion of a Section 106 Agreement under the Town and Country Planning Act 1990 with delegated authority to officers to negotiate, settle and complete such an Agreement as referenced in the Heads of Terms within this report including any other planning obligations considered appropriate and necessary to make the development acceptable in planning terms; and (c) a reasoned conclusion of the significant effects of the development on the environment and the carrying out of the appropriate notifications under regs. 29 and 30 in accordance with the Town and Country Planning (EIA) Regulations 2017, delegated to officers.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Joint Development Management Committee

25/00016/FUL – Trinity Hall Farm Industrial Estate, Nuffield Road, Cambridge Application details

Report to: Joint Development Management Committee

Lead Officer: Joint Director of Planning and Economic Development

Ward/parish: East Chesterton

Proposal: Demolition of existing buildings and the erection of buildings for Use Class E(g)i (offices) and E(g)ii (research and development) with Class E(a) (retail) and E(b) (sale of food and drink) uses on the ground floor together with Public Garden, landscaping and associated infrastructure works.

Applicant: MA Propco 11 Limited (a company within the Brockton Everlast group of companies)

Presenting officer: Cuma Ahmet

Reason presented to committee: The provision of a non-residential building where the GIA floor space to be created is 1,000m2 or more and the site is more than 1 hectare.

Member site visit date: 17 November 2025

Key issues:

1. Principle of Development 2. Design, scale and massing 3. Sustainable Design and Construction 4. Water Resources 5. Drainage and Flood Risk 6. Highway Safety and Transport impacts 7. Planning Obligations 8. Planning Balance

Recommendation: Approve subject to conditions and completion of a Section 106 Agreement.

Report contents Document Document heading section 1 Executive Summary 2 Site Description and Context 3 The Proposal 4 Relevant Site History 5 Policy 6 Consultations 7 Third Party Representations 8 Member Representations 9 Local Groups 10 Planning Background 11 Assessment 12 Principle of Development 13 Design 14 Landscape and Townscape Effects 15 Heritage Assets 16 Trees, Ecology and Biodiversity 17 Sustainable Design and Construction 18 Water Resources 19 Drainage and Flood Risk 20 Highway Safety and Transport Impacts 21 Residential Amenity 22 Miscellaneous Matters 23 Third Party Representation 24 Planning Obligations (S106) 25 Planning Balance 26 Conclusion 27 Recommendation 28 Planning Conditions & Informatives Appendix 1 – Local Plan and National Planning Policies Appendix 2 – Cambridgeshire Quality Panel Reports

Table 1: Contents of report 1. Executive Summary 1.1 The application seeks full planning permission for the comprehensive redevelopment of an existing industrial site for research and development led mixed-uses that includes flexible office and lab space, retail and café at ground level with associated supporting infrastructure.

1.2The principle of the proposals for new office and lab-enabled buildings is consistent with both national and local planning policy objectives which seek to support and maintain Cambridge’s role as a world leading location for knowledge-based industries.

1.3The proposed design-led approach is considered to set a new benchmark for science and innovation-led developments which moves away from generic, large format campus models towards more people focussed environments that enhances public realm and wider urban fabric.

1.4It is considered that the proposed layout and form, scale and massing, architectural detailing and quality of materials of the proposed development, including landscaping positively responds to the surrounding character.

1.5The proposed development is aiming for net-zero carbon status by adopting a passive strategy for enabling a reduction in (carbon) emissions and operational energy use to achieve BREEAM Excellence as a minimum. In terms of water conservation, BREEAM 5 WAT 01 water credits (including exemplary/innovation credit) are targeted which represents a 65% improvement over the 2018 (Wat 01) baseline. Circular design principles and the ‘whole life’ waste approach are also integral to its sustainability objectives including exceeding the minimum statutory 10% increase in biodiversity onsite.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25.00016.FUL Appendix 2a CQP report Trinity Hall Farm Industrial Estate 14th December final /28/JDMCAppendix 285 KB Download
PDF
25.00016.FUL Appendix 2b CQP2 Report Trinity Hall Industrial Estate 3rd July final /28/JDMCAppendix 307 KB Download
PDF
25.0016.FUL Appendix 1 Policy Glossary /28/JDMCAppendix 137 KB Download
PDF
25/00016/FUL Trinity Hall Farm Industrial EstateReport 908 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 20 attended
PF
Councillor Peter Fane South Cambridgeshire District CouncilChair, present
SS
Councillor Simon Smith Cambridge City CouncilVice-Chair, present
TG
Councillor Tim Griffin Cambridge City CouncilCommittee Member, apologies, sent representative
IF
Councillor Ingrid Flaubert Cambridge City CouncilCommittee Member, apologies, sent representative
AN
Councillor Antoinette Nestor Cambridge City CouncilCommittee Member, apologies
KP
Councillor Katie Porrer Cambridge City CouncilCommittee Member, present
MS
Councillor Martin Smart Cambridge City CouncilCommittee Member, present
AB
Councillor Anna Bradnam South Cambridgeshire District CouncilCommittee Member, present
MC
Councillor Martin Cahn South Cambridgeshire District CouncilCommittee Member, present
TH
Councillor Tumi Hawkins South Cambridgeshire District CouncilCommittee Member, present
RS
Councillor Richard Stobart South Cambridgeshire District CouncilCommittee Member, present
RW
Councillor Richard Williams South Cambridgeshire District CouncilCommittee Member, present

All 20 on the meeting page

More from Cambridge Joint Development Management Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 26/01403/FUL Chapter House, Howes Place, Cambridge, CB3 0UWResolved (by 10 votes to 1) to grant the application for retrospective planning permission in accordance with the off... Decided Open
21 Oct 2026 National Scheme of DelegationResolved (by 9 votes to 0, with 2 abstentions) to: i. Note the report. ii. Approve the revised November 2026 Greater ... Noted Open
19 Aug 2026 26/01691/REM Land North of Cambridge North StationResolved (by 4 votes to 0 with 5 abstentions) to approve the reserved matters application subject to the conditions a... Approved Open
19 Aug 2026 25/04604/FUL 1 Kings Meadow, CambridgeResolved (by 7 votes to 0, with 2 abstentions) to approve application 25/04604/FUL subject to the planning conditions... Approved Open
17 Jun 2026 Election of Chair and Vice-ChairResolved by 10 votes to 2 that Councillor Porrer be elected as Chair for the ensuing year. Councillor Porrer took ove... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies