Improvement Plan Highlight Report

Noted Finance 3 papers

Audit and Governance Committee noted this item on Thursday 20 June 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The Committee RESOLVED to note: a) the progress in March against the identified areas of ongoing concern set out in the Best Value Notice received in January 2024. b) the update from the Chair, Independent Improvement Board following the meeting held on 7 May 2024
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Audit and Governance Committee

Recommendations

A Note the progress in March against the identified areas of ongoing concern set out in the Best Value Notice received in January 2024. B Note the update from the Chair, Independent Improvement Board following the meeting held on 7 May 2024

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s): x Achieving ambitious skills and employment opportunities x Achieving good growth x Increased connectivity x Enabling resilient communities x Achieving Best Value and High Performance The identified improvements set out in this report aim to meet the concerns of the External Auditor and Best Value Notice. By making necessary improvements, the capacity, culture and governance of the Combined Authority will support and enable the delivery of identified priorities and objectives set out in the Corporate Plan and result in the CPCA being seen as achieving best value and high performance.

1. Purpose

1.1This report provides the Audit and Governance Committee with an opportunity to review the progress made in the improvement programme, phase 3, up to the end of March to address the concerns set out in the Best Value Notice dated January 2024.

2. Purpose 2.1 Best Value Notice January 2024

A new Best Value Notice was received by the Combined Authority on 30 January 2024 for a further six month period.

The Cambridgeshire and Peterborough Combined Authority (CPCA) Board in March 2024 agreed the Improvement plan, phase 3 to address the identified concerns set out in the Best Value Notice (January 2024): • Continue to implement and embed the changes agreed by the Combined Authority Board as part of the improvement plan. • Continue to implement and monitor cultural change across the organisation, for both officers and members, with a focus on measurable outcomes. • Commit, through strong partnership working at both officer and member level, to develop the strategic priorities and aspirations for the area that will benefit local residents, and a credible delivery strategy for progressing these. We hope that this can be achieved through consensus but, if not all stakeholders are ready to fully engage, the opportunity should be left open for them to do so when they feel ready to. This work is also important in informing CPCA’s approach to further devolution. • Continue with the independent Improvement Board, making full use of its support and engaging with its recommendations over the next six months. • Continue to engage regularly with the Department at official level throughout the period of this Notice.

2.2Overall progress

Overall the programme is rated as 'Green / Amber' at the end of March 2024, meaning 'successful delivery of the improvement plan to time, cost and quality appears to be highly likely', reflecting the positive trends across the three themes set out in the highlight report attached as Appendix 1.

A significant amount of further activity is planned across all three workstreams and set out in the Improvement Plan agreed by the CPCA Board in March 2024.

It is positive that two workstreams are RAG rated as ‘Green’ at this stage in the programme, with the 3rd having an ‘Green / Amber’ status recognising the challenges of culture change within the Member environment.

The Improvement Group, chaired by the Executive Director, Resources and Performance continues to assess progress against the agreed plan and address any programme issues or risks.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Improvement Plan Highlight Report March 2024Appendix 1 260 KB Download
PDF
CPCA IIB May OverviewAppendix 2 98 KB Download
PDF
Improvement Plan Highlight ReportReport 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 20 attended
JP
John Pye Independent PersonChair, present
DH
David HarwoodIndependent Person, present
MT
Councillor Mike Todd-Jones Cambridge City CouncilCommittee Member, apologies, sent representative
GW
Councillor Graham Wilson Cambridgeshire County CouncilCommittee Member, apologies, sent representative
DB
Councillor David Brown East Cambridgeshire District CouncilCommittee Member, present
GC
Councillor Gary Christy Fenland District CouncilCommittee Member, present
PH
Councillor Paul Hodgson-Jones Huntingdonshire District CouncilCommittee Member, present
CH
Councillor Christian Hogg Peterborough City CouncilCommittee Member, apologies
GH
Councillor Geoff Harvey South Cambridgeshire District CouncilCommittee Member, absent
SC
Councillor Sam Carling Cambridge City CouncilSubstitute
AW
Councillor Alison Whelan Cambridgeshire County CouncilSubstitute, present as substitute
MS
Councillor Martin SmartCommittee Member, present as substitute

All 20 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Improvement Plan Highlight ReportThis decision
  2. Cambridgeshire & Peterborough Local Skills Improvement Plan, Submission and Transition to DeliveryApproved
  3. Local Skills Improvement PlanApproved
  4. Local Skills Improvement PlanApproved
  5. Local Skills Improvement PlansNoted
  6. Improvement Plan ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Audit and Governance Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... Noted Open
10 Sep 2026 Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... Decided Open
10 Sep 2026 Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. Decided Open
10 Sep 2026 Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... Noted Open
10 Sep 2026 CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies