Resolved
On being put to the vote, proposed by the Chair and seconded by Cllr MacDonald, the motion was not supported. An update on the MATS proposal would therefore be re-presented at a future meeting.
Transport Committee decided this item on Wednesday 26 June 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
On being put to the vote, proposed by the Chair and seconded by Cllr MacDonald, the motion was not supported. An update on the MATS proposal would therefore be re-presented at a future meeting.
A Take note of the progress on March Area Transport Study (MATS). B Recommend to the Combined Authority Board to approve the MATS Full Business Case 2 (FBC 2) C Recommend to the Combined Authority Board, approve the drawdown of £7,000,000 of the Medium- Term Financial Plan (MTFP) from subject to approval to approved for the MATS project to be spent in Financial Years 2024/2025 and 2025/2026. D Recommend to the Combined Authority to delegate authority to the Assistant Director of Transport in consultation with the Chief Finance Officer and Monitoring Officer to enter into Grant Funding Agreements with Cambridgeshire County Council.
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): X Achieving good growth – March Area Transport Study aims to facilitate housing and employment growth across March and Regeneration of March Town Centre. X Enabling resilient communities – March Area Transport Study aims to improve local environmental conditions. X Increased connectivity - March Area Transport Study aims to address existing traffic congestion and safety issues.
1. Purpose
1.1This paper seeks to provide an update on the work on March Area Transport Study (MATS) and approve the drawdown of £7,000,000 from the Medium-Term Financial Plan (MTFP) to continue the project. 2. Proposal
2.1This paper provides an update on the work undertaken to date on MATS. The paper also proposes to seek the drawdown of the allocated £7,000,000 funds in the MTFP to continue the project.
3.1The MATS was first approved for inclusion in the Transport Programme at the March 2018 by the Combined Authority. Following this Cambridgeshire County Council (CCC) took forward the study to establish the issues and find potential solutions to address these in an efficient and effective manner. 3.2 Fenland District Council’s (FDC) vision for the area is outlined within its Local Plan published in 2014. The aim is ‘to maximise the potential of the area and deliver jobs, skills, improved housing and new infrastructure’, and make the district ‘a better place to live, work and visit’. The Local Plan includes the delivery of 4,200 new homes in March as well 30 hectares of employment land to provide new jobs 3.3 The 2011 MATS Study provided the transport evidence base for the Local Plan and assessed the impact of traffic growth resulting from its implementation. In addition, it proposed measures to improve the towns transport network for both current and future traffic demand. The current MATS builds upon this work and assesses potential improvement options to deliver future economic and housing growth 3.4 The MATS Strategic Outline Business Case (SOBC) was submitted in October 2020 and the Outline Business Case (OBC) was tabled at the Combined Authority Board in November 2021 along with approval for the next stage of the MATS project including Full Business Case (FBC) and Detailed Design. This paper also outlined within its Other Significant Implications section that the Future High Street Fund (FHSF) scheme was reliant on the MATS Broad Street project undertaking detailed design and commencing construction. 3.5. In summary the MATS project has a number of different workstreams since the project began as shown in the table below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
March Area Transport Study FBC2Appendix A | 6.3 MB | Download |
PDF |
March Area Transport StrategyReport | 2.7 MB | DownloadRead as text |
Follow Transport Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi... | Approved | Open |
| 9 Sep 2026 | Forward PlanA. That the Combined Authority Forward Plan be noted A. That the Combined Authority Forward Plan be noted. ACTION: 1.... | Noted | Open |
| 9 Sep 2026 | Developer Funding Governance(Unanimous) A. To note the CPCA action plan to improve governance and delivery of developer funding for bus services ... | Noted | Open |
| 9 Sep 2026 | Bus Services Reimagined – Final Service Change ProposalsA. To note the outcome of the contracted bus services review, including the evidence base, consultation feedback and ... | Noted | Open |
| 9 Sep 2026 | Local Transport Delivery Plan(Unanimous) To recommend to the Combined Authority Board that they: A. Approve the (LTDP) – Cambridgeshire County Cou... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.