The Committee received and noted the report which outlined the O&S Budget Working Group’s feedback from the budget sessions and the informal committees discussions in December.
Overview and Scrutiny Committee noted this item on Thursday 16 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee received and noted the report which outlined the O&S Budget Working Group’s feedback from the budget sessions and the informal committees discussions in December.
Overview and Scrutiny Committee 16 January 2025
Title: Medium Term Financial Plan & O&S Consultation Feedback Report of: Cllr Antunes – Budget Working Group & Anne Gardiner – Governance Manager & Statutory Scrutiny Officer
Overview and Scrutiny Committee Key Principle:
To examine all decision-making through the lens of integrated decision-making, to drive out silo approaches and ensure CPCA strategy is not operating in isolation, considers wider impact across corporate plan priority areas, and considers future devolution opportunities and benefits.
Strategic Objective(s):
The topics within this report fit under the following strategic objective(s): ☐ Achieving ambitious skills and employment opportunities ☐ Achieving good growth ☐ Increased connectivity ☐ Enabling resilient communities ☒ Achieving Best Value and High Performance
Topic Scoring
Numerical Score Public Interest 3 Rating Scores Strategic Value 2 1 = Low Risk to Combined Authority 1 2 = Medium Alignment to Corporate Priorities 2 3 = High Financial Value 1 Issue of concern for partners? 1 Will the CA be able to achieve an effective outcome? 2 Will there be potential benefits for a significant part of the 1 Combined Authority area/partners/stakeholders?
Scrutiny Value Score [right click on the value and “update field” to total the score] 13 1. Background
3.1A Budget Scrutiny Working Group was set up by the Overview and Scrutiny Committee to consider the budget setting process and Medium-Term Financial Plan (MTFP) for the Combined Authority. This work of the group was undertaken over two phases – the first phase to consider the in-year position and future impact, and the second phase to consider the draft budget proposals from 2025/26.
3.2The findings of the Working Group were fed back to a scrutiny committee workshop in order to prepare the scrutiny feedback to the Combined Authority Board for consideration when setting the 2025/26 budget and Medium-Term Financial Plan for the period 2025-2029.
2. Proposal
2.1The Committee are requested to review and note the discussion points below. 2.2 An overview of the discussion and findings of the working group included:
• Slippage against project spend and how this could be improved in relation to realistic spend profiles and improved delivery, which also led to the need to consider the pipeline of projects and opportunities • Consideration of how strategic hurdles could be tackled • The need for robust performance recording and management • Evidencing value for money in spending decisions – including beyond practical completion and into measuring success and capturing lessons learnt • Requiring a proactive approach to risk and how this was shared between public and private investment.
2.3During the committee workshop a presentation was provided by the Executive Director Resources on the draft budget and the following points were raised and discussed:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Working Group FeedbackReport | 173 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Apologies for AbsenceApologies were received from Cllr Neish, substituted by Cllr Hogdson-Jones. | Decided | Open |
| 8 Sep 2026 | Declaration of InterestsThere were no declaration of interests made. | Decided | Open |
| 8 Sep 2026 | Public QuestionsNo public questions were received. | Decided | Open |
| 8 Sep 2026 | Minutes of the previous meetingThe minutes of the meeting on 30 July 2026 were approved as an accurate record. The Action Log was noted by the Commi... | Approved | Open |
| 8 Sep 2026 | Corporate Performance Report, Q1 2026/27The Committee discussed and noted the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.