It was resolved to: A Agree the Full Business Case (FBC) for the Peterborough Station Quarter which is being submitted to Department for Transport. With their approval, this would then enable the drawdown of funding from the £47.85m capital investment from HM Government’s Levelling Up Fund. B Note that subject to the Department for Transport's approval of the Final Business Case (FBC), a Grant Funding Agreement will be executed with Peterborough City Council, in accordance with the delegations granted by the Combined Authority Board in March 2023. C Approve the Connect to Work Outline Business case to develop the Connect to Work programme into Full Business Case. D Approve the concept paper for Cambridge Civic Quarter. E Note the Chief Executive Approval Decisions from February 2025. F Note the decisions from Investment Committee held on 13 January 2025 and 10 March 2025.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To agree the Full Business Case (FBC) for the Peterborough Station Quarter which is being submitted to Department for Transport. With their approval, this would then enable the drawdown of funding from the £47.85m capital investment from HM Government’s Levelling Up Fund. B To note that subject to the Department for Transport's approval of the Final Business Case (FBC), a Grant Funding Agreement will be executed with Peterborough City Council, in accordance with the delegations granted by the Combined Authority Board in March 2023. C To approve the Connect to Work Outline Business case to develop the Connect to Work programme into Full Business Case. D To approve the concept paper for Cambridge Civic Quarter. E To note the Chief Executive Approval Decisions from February 2025. F To note the decisions from Investment Committee held on 13 January 2025 and 10 March 2025.
Strategic Objective(s):
The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Increased connectivity X Enabling resilient communities X Achieving Best Value and High Performance
1. Purpose
1.1To agree the Peterborough Station Quarter Full Business Case, and £47.85m to deliver the project, subject to the approval from the Department for Transport – see Section 3 of the report. This follows the approval of the Outline Business Case by the Board and DfT last year and a Board decision in March 2023 which formally approved recommendations to release funding subject to business case approvals. 1.2 To approve the Connect to Work Outline Business case to develop the Connect to Work programme into a Full Business Case as set out in Section 4. 1.3 To approve the investment proposals at concept stage for Cambridge Civic Quarter as set out in Section 5. 1.4 To note the Chief Executive Approval Decisions for February 2025 as set out in Section 6. 1.5 To note the Investment Committee Approval Decisions held on 13 January 2024 and 10 March 2025 as set out in Section 7.
2. Proposal
2.1These items are considered under the Authority’s Strategic Assurance Framework (SAF). 2.2 All items have previously been presented to the Investment Panel and sponsored by the relevant Executive Director. All items (except the Chief Executive Decisions) have also been presented to the Investment Committee (either at its meeting held on 13 January 2025 or 10 March 2025). 2.3 The governance route for approval of the business case is dependent on the financial value of the project and is set out below: • Above £5m – considered by Investment Committee for comment before being presented to the CPCA Board for approval. • Between £1m up to £5m – presented to the Investment Committee for approval. • Below £1m – presented to the Chief Executive for approval. Change proposals involving further funding requests will be taken through the relevant approval channel.
3. Full Business Case – Peterborough Station Quarter
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Combined Authority Board at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.