Review of Investment Concept Papers and Business Cases

Agreed Committee 3 papers

Combined Authority Board agreed this item on Wednesday 19 March 2025. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

It was resolved to: A Agree the Full Business Case (FBC) for the Peterborough Station Quarter which is being submitted to Department for Transport. With their approval, this would then enable the drawdown of funding from the £47.85m capital investment from HM Government’s Levelling Up Fund. B Note that subject to the Department for Transport's approval of the Final Business Case (FBC), a Grant Funding Agreement will be executed with Peterborough City Council, in accordance with the delegations granted by the Combined Authority Board in March 2023. C Approve the Connect to Work Outline Business case to develop the Connect to Work programme into Full Business Case. D Approve the concept paper for Cambridge Civic Quarter. E Note the Chief Executive Approval Decisions from February 2025. F Note the decisions from Investment Committee held on 13 January 2025 and 10 March 2025.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendations

A To agree the Full Business Case (FBC) for the Peterborough Station Quarter which is being submitted to Department for Transport. With their approval, this would then enable the drawdown of funding from the £47.85m capital investment from HM Government’s Levelling Up Fund. B To note that subject to the Department for Transport's approval of the Final Business Case (FBC), a Grant Funding Agreement will be executed with Peterborough City Council, in accordance with the delegations granted by the Combined Authority Board in March 2023. C To approve the Connect to Work Outline Business case to develop the Connect to Work programme into Full Business Case. D To approve the concept paper for Cambridge Civic Quarter. E To note the Chief Executive Approval Decisions from February 2025. F To note the decisions from Investment Committee held on 13 January 2025 and 10 March 2025.

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s): X Achieving ambitious skills and employment opportunities X Achieving good growth X Increased connectivity X Enabling resilient communities X Achieving Best Value and High Performance

1. Purpose

1.1To agree the Peterborough Station Quarter Full Business Case, and £47.85m to deliver the project, subject to the approval from the Department for Transport – see Section 3 of the report. This follows the approval of the Outline Business Case by the Board and DfT last year and a Board decision in March 2023 which formally approved recommendations to release funding subject to business case approvals. 1.2 To approve the Connect to Work Outline Business case to develop the Connect to Work programme into a Full Business Case as set out in Section 4. 1.3 To approve the investment proposals at concept stage for Cambridge Civic Quarter as set out in Section 5. 1.4 To note the Chief Executive Approval Decisions for February 2025 as set out in Section 6. 1.5 To note the Investment Committee Approval Decisions held on 13 January 2024 and 10 March 2025 as set out in Section 7.

2. Proposal

2.1These items are considered under the Authority’s Strategic Assurance Framework (SAF). 2.2 All items have previously been presented to the Investment Panel and sponsored by the relevant Executive Director. All items (except the Chief Executive Decisions) have also been presented to the Investment Committee (either at its meeting held on 13 January 2025 or 10 March 2025). 2.3 The governance route for approval of the business case is dependent on the financial value of the project and is set out below: • Above £5m – considered by Investment Committee for comment before being presented to the CPCA Board for approval. • Between £1m up to £5m – presented to the Investment Committee for approval. • Below £1m – presented to the Chief Executive for approval. Change proposals involving further funding requests will be taken through the relevant approval channel.

3. Full Business Case – Peterborough Station Quarter

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Connect to Work OBCAppendix C 665 KB Download
PDF
Cambridge Civic Quarter: ConceptAppendix D 550 KB Download
PDF
Review of Investment Concept Papers and Business CasesDecisions 258 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 21 attended
NJ
Dr Nik Johnson Cambridgeshire and Peterborough Combined AuthorityChair, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, present
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, apologies, sent representative
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
DJ
Councillor Dennis Jones Peterborough City CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
AS
Councillor Anna Smith Cambridge City CouncilCommittee Member, present
BS
Councillor Bridget Smith South Cambridgeshire District CouncilCommittee Member, present
AK
Al Kingsley Business BoardCommittee Member, present
JO
John O'Brien Integrated Care BoardCo-Optee, present
DP
Darryl Preston Police and Crime CommissionerCo-Optee, present
EM
Councillor Edna Murphy Cambridgeshire and Peterborough Fire AuthorityCo-Optee, absent

All 21 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Review of Investment Concept Papers and Business CasesThis decision
  2. Review of Investment Concept Papers KD2024/042Approved
  3. Review of Investment Concept PapersApproved

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies