Local Remediation Acceleration Plan KD2025/037

Approved Committee 2 papers

Combined Authority Board approved this item on Tuesday 22 July 2025. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

It was resolved to: A Approve the Local Remediation Acceleration Plan 2025 (LRAP) as the strategic framework for remediation activity across the region. B Approve the drawdown of the £225,000 grant allocation to support staffing, data monitoring, and regulatory coordination as outlined in the LRAP (see appendix) and include it within the Authority’s budget. The funding is intended to be used in the 2025/26 and 2026/27 financial years and aims to support the vital role of coordinating regulatory activity to deliver the LRAP. This includes access to the Joint Inspection Team, guidance, training, and engagement. C Delegate authority to the Executive Director – Place and Connectivity to enter into a Grant Funding Agreement with the Cambridgeshire Fire and Rescue Service (CFRS) in consultation with the Chief Finance Officer and Monitoring Officer and oversee implementation and reporting, including quarterly updates to Ministry of Housing, Communities & Local Government (MHCLG) and strategic partners. D Note the alignment of the LRAP with the Combined Authority’s strategic objectives on resilient communities, good growth and high performance.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendations

A Approve the Local Remediation Acceleration Plan 2025 (LRAP) as the strategic framework for remediation activity across the region. B Approve the drawdown of the £225,000 grant allocation to support staffing, data monitoring, and regulatory coordination as outlined in the LRAP (see appendix) and include it within the Authority’s budget. The funding is intended to be used in the 2025/26 and 2026/27 financial years and aims to support the vital role of coordinating regulatory activity to deliver the LRAP. This includes access to the Joint Inspection Team, guidance, training, and engagement. C Delegate authority to the Executive Director – Place and Connectivity to enter into a Grant Funding Agreement with the Cambridgeshire Fire and Rescue Service (CFRS) in consultation with the Chief Finance Officer and Monitoring Officer and oversee implementation and reporting, including quarterly updates to Ministry of Housing, Communities & Local Government (MHCLG) and strategic partners. D Note the alignment of the LRAP with the Combined Authority’s strategic objectives on resilient communities, good growth and high performance.

Strategic Objective(s):

The proposals within this report fit under the following strategic objective(s): x Achieving good growth – by unlocking stalled developments. x Resilience – by addressing risk. x Achieving Best Value and High Performance – through coordinated, data-led action.

1. Purpose

1.1To agree a Cambridgeshire and Peterborough strategy, and associated deployment of resources, to support the remediation of medium and high-rise buildings. 2. Proposal

2.1The Local Remediation Acceleration Plan (LRAP) 2025 outlines a clear delivery model for identifying, auditing, and remediating buildings over 11m, with a focus on those with unsafe cladding. It includes a robust monitoring framework using the National Remediation System (NRS) and quarterly data shares from MHCLG. The funding and wider initiatives are designed to support the CPCA in convening and coordinating regulatory activity effectively. This includes providing access to the Joint Inspection Team, offering guidance, training, and engagement opportunities. 2.2 The Plan addresses key risks such as landlord reluctance, contractor capacity, and developer disputes. Contractor capacity is a risk given this is a nationwide task. The Plan commits to monthly operational reviews and quarterly strategic oversight meetings to ensure progress and accountability. 2.3 The proposal is to use government funding to support staffing, data monitoring, and regulatory coordination as outlined in the LRAP (see appendix). The funding is intended to be used in the 2025/26 and 2026/27 financial years and aims to support the vital role of coordinating regulatory activity to deliver the LRAP.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LRAP 2025Appendix A 3.3 MB Download
PDF
Local Remediation Acceleration Plan KD2025/037Report 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 22 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityCommittee Member, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, present
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, present
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
DJ
Councillor Dennis Jones Peterborough City CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
AS
Councillor Anna Smith Cambridge City CouncilCommittee Member, present
BS
Councillor Bridget Smith South Cambridgeshire District CouncilCommittee Member, present
AK
Al Kingsley Business PanelCommittee Member, present
JO
John O'Brien Integrated Care BoardCo-Optee, present
DP
Darryl Preston Police and Crime CommissionerCo-Optee, apologies
CM
Councillor Christopher Morris Cambridgeshire and Peterborough Fire AuthorityCo-Optee, present

All 22 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Local Remediation Acceleration Plan KD2025/037This decision
  2. Local Remediation Acceleration Plan (LRAP)Noted

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies