AI summaryCambridgeshire and Peterborough Combined Authority Skills Committee noted progress on the £4.5m Further Education Cold Spots Skills Capital Programme, with most projects facing timeline extensions and two awaiting Funding Panel decisions in January 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedSeven projects updated, further report due March 2026
Money£4.5m committedCitizen Hub saving approximately £200k against original budget
What happens nextReport in March 2026Funding Panel decisions expected in January 2026
Who it affectsFE cold spot areas and providersSt Neots, East Cambridgeshire, Huntingdon, Soham, Ely, Wintringham
What was decided
The Committee noted progress with the Further Education Cold Spots Skills Capital Programme. Report P1
The Committee noted that a further progress report would come to the Skills Committee in March 2026. Report P1, 2.1
Why
The report was presented to give the Skills Committee an update on the seven projects within the FE Cold Spots Skills Capital Programme and to flag potential changes. Report 1.1, 2.1
The programme aims to improve skills infrastructure in cold spot areas identified as St Neots and East Cambridgeshire, addressing low participation and skills shortages in sectors such as construction, health and social care. Report 3.1, P3
What happens next
A further report will come to the Skills Committee in March 2026 with a position on each of the projects and an update on outcomes. Report 2.1
Two West Suffolk College projects await Funding Panel decisions in January 2026, representing 62.12 per cent of the whole programme.
Back 2 Work Complete Training is expected to submit a project change request in the next few weeks, as the provider considers options after struggling to source a suitable property in St Neots.
The money
£4.5m Total grant funding committed to the FE Coldspots Capital Fund stream Report 3.1, P11
£455,000 Back 2 Work Complete Training, green tech and construction centre in St Neots
£330,000 Cambridge Regional College, green construction skills centre at Huntingdon campus
£416,000 Cambridge Regional College, immersive learning rooms at Huntingdon and Cambridge campuses
£399,000 Cambridge Regional College, linked immersive learning room at St Neots Citizen Hub
£1,450,000 West Suffolk College, health and science education centres in Soham and Ely
£1,300,000 West Suffolk College, modular micro-construction facility in St Neots
£100,000 Steadfast Training, three electric vehicles for mobile training centres
£399,414 Original cost of Citizen Hub immersive room project, reduced to approximately £100,000 Report 3.3
£1,449,000 West Suffolk College, health and science education centre in Ely plus Soham skills hubs
£1,298,000 West Suffolk College, modular green skills workshop at Wintringham
£2,797,000 Combined value of the two West Suffolk College projects awaiting Funding Panel
£455,331 Back 2 Work Complete Training, green technology and house building training centre in St Neots
approximately £200k Saving against original Citizen Hub budget Report P11
Implications
Financial: The Authority has committed £4.5m in skills capital, with most change requests adjusting timings without changing the funding amount from the Combined Authority. Report P11
Financial: The Citizen Hub project in St Neots is reducing its funding requirement by approximately £200k while maintaining outputs, representing a saving against the original budget. Report P11
Legal: Standard grant funding agreements will be issued for the remaining four projects under the delegations obtained for the funding, with any changes to funding usage needing to go through the single assurance framework project change request process. Report P11
Other: Capital expenditure on three Cambridge Regional College projects will extend into the 2026/27 financial year, with output monitoring continuing until the end of the 2028/29 academic year. Report 3.3
Who and where
Residents in St Neots, East Cambridgeshire, Huntingdon, Soham, Ely and Wintringham cold spot areas Report 3.1
Cambridge Regional College, West Suffolk College, Back 2 Work Complete Training and Steadfast Training as funded providers
Employers in construction, health, social care, education and green skills sectors Report 3.1
Timeline
2024: Feasibility study outlined demand for specialist provision in cold spot areas Report 3.1
6 February 2025: Combined Authority Board approved the grant funding approach and delegated authority to enter into grant agreements Report 3.1
16 June 2025: Skills Committee received a report on the outcome of the Grant Funding application process Report 3.1
1st October 2025: Grant Fund Agreement for Cambridge Regional College linked immersive rooms project signed and sealed Report 3.3
10 November 2025: Previous progress update provided at the Skills Committee Report 3.1
early January 2026: Remaining Steadfast electric vehicles expected for delivery, with EV charging points being installed
January 2026: Funding Panel decisions anticipated on the two West Suffolk College extension requests
March 2026: Further progress report scheduled for the Skills Committee Report 2.1
June 2026: Extended timeline end for the Cambridge Regional College linked immersive rooms project Report 3.3
15 July 2026: Grant Fund Agreement for Back 2 Work Complete Training signed and sealed (as stated in the report)
September 2026: Extended timeline ends for the Cambridge Regional College Huntingdon workshop project and the Citizen Hub St Neots immersive room project Report 3.3
end of 2028/29 academic year: Output monitoring on the three extended Cambridge Regional College projects will continue until this point Report 3.3
Plain English for the jargon
FE Cold Spots: Areas identified as having low participation in skills and limited access to further education provision; St Neots and East Cambridgeshire were defined as such
CPCA: Cambridgeshire and Peterborough Combined Authority
Single assurance framework: The process through which project change requests must be considered
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
A. To note progress with the Further Education (FE) Cold Spots Skills Capital Programme. B. To note that the Skills Committee will receive a further progress report in March 2026. A. To note progress with the Further Education (FE) Cold Spots Skills Capital Programme. B. To note that the Skills Committee will receive a further progress report in March 2026.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note progress with the Further Education (FE) Cold Spots Skills Capital Programme. B To note that the Skills Committee will receive a further progress report in March 2026.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s): ☒ Growth ☒ Jobs ☐ Resilience ☐ Connectivity ☐ Homes ☐ Performance This programme of work relates to the Jobs Objective within the Corporate Plan, specifically the aim of improving skills infrastructure by collaborating with employers to implement Skills Capital projects.
1. Purpose
1.1To provide the Skills Committee with an update on the Further Education (FE) Cold Spots Skills Capital Programme
2. Proposal
2.1This report is to provide an update on progress with each of the projects and to provide advance notice of some potential change. Of the seven projects with approved funding, one is progressing as planned, three have been successfully extended via the change request process, two have been submitted to Funding Panel for extension, and one is awaiting detailed information on project changes from the training provider.
Background
3.1The FE Coldspots Capital Fund stream encompasses a £4.5m grant funding secured to address low participation in skills and limited access to provision in priority places. St Neots, East Cambridgeshire were defined as FE Cold Spots areas and a feasibility study conducted in 2024 outlined the demand for specialist provision in health, social care, education, entry-level, and work readiness skills. The aim was to ensure residents are equipped with the transferable skills employers demand and that those residents who are economically inactive are supported into work. Skills provision was also needed across key sectors such as Construction, to address the skills shortages needed to build houses and meet local house building targets. On 6 February 2025, the Combined Authority Board approved the grant funding approach and delegated authority to the Assistant Director for Skills and Employment, in consultation with the Chief Finance Officer and Monitoring Officer, to enter into grant agreements with selected providers. On 16 June 2025, the Skills Committee received a report that outlined the outcome of the Grant Funding application process: Further Education Cold Spots.pdf. The Committee was informed that the Authority was proceeding to enter into Grant Funding Agreements with the chosen suppliers and that a progress report would be brought back to the Committee in approximately six months. A progress update was provided at the Skills Committee on 10 November 2025. � 3.2 The seven successful projects are: Provider Project Funding approved Back2 Work Complete Green Tech, construction and housing training centre £455,000 Training in St Neots Cambridge Regional Green construction skills centre, workshop and £330,000 College training bays on their Huntingdon campus. Cambridge Regional Immersive learning rooms in Huntingdon and £416,000 College Cambridge campuses. Cambridge Regional Linked immersive learning room in St Neots Citizen £399,000 College Hub West Suffolk College Purchase and fit out of new buildings for health and £1,450,000 science education centres in Soham and Ely West Suffolk College Modular micro-construction training facility for £1,300,000 construction and green tech skills in St Neots Steadfast Training 3 electric vehicles for mobile training centres £100,000 covering a variety of sectors
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Skills Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe Minutes of the meeting held on 15 June 2026 were approved as an accurate record. The Action Log was noted by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.