Cambridgeshire and Peterborough Combined Authority
Skills Committee, Monday 15 June 2026 at 11.00am

Post 16 Capacity Skills Capital Funding

Noted Committee 2 papers

AI summarySkills Committee noted development of a £12.5 million Full Business Case for a Post-16 Capacity and Construction Skills Capital Programme, ahead of submission through the Combined Authority's Single Assurance Framework.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the Full Business Case and agreed to provide feedback.
Money£12.5 million
What happens nextFunding Committee reviewFull Business Case to be considered by Funding Committee in June 2026.
Who it affectsFE Colleges and Sixth Forms

What was decided

The Committee noted the development of the Full Business Case for the Post-16 Capacity and Construction Skills Capital Programme, ahead of submission through the Combined Authority's Single Assurance Framework. Report P1

Members will provide feedback and commentary, including any questions or suggestions, to inform ongoing programme design and delivery. Report P2

The programme is identified as supporting the Growth, Jobs, Resilience and Performance strategic objectives of the Combined Authority. Report P5, P6

Why

The Combined Authority has been allocated £12.5 million of capital funding from the Department for Education to be invested between 2026 and 2030, to increase post-16 capacity and address construction and technical skills shortages. Report 3.1

The programme will increase post-16 capacity in response to demographic growth in 16 to 19 learners, expand construction and technical training in line with employer demand, and invest in modern training facilities. Report 2.1, P6

The preferred delivery model is a competitive funding application process, enabling targeted investment in areas of greatest need, transparent decision making, and alignment with employer demand.

What happens next

The Full Business Case will be submitted to the Funding Committee in June 2026 through the Single Assurance Framework, following its recommendation for further review by the June Funding Panel. Report 2.1

Following programme level approval, the Combined Authority will invite applications from providers, with individual capital projects developed through a co-production process with FE Colleges and Sixth Forms.

All funded projects will be subject to a robust application, appraisal and due diligence process, with individual approvals taken through the Single Assurance Framework in line with agreed thresholds.

The money

  • £12.5 million Department for Education capital funding allocated for 2026 to 2030 Report 2.1, 3.1, P13
  • £582,108 Capital funding from the FE Cold Spots programme, integrated into the programme subject to SAF approval Report 2.1, P13
  • £107,000 Revenue funding from the FE Cold Spots programme, integrated to strengthen delivery subject to SAF approval Report 2.1, P13

Options considered

  • Chosen: Competitive funding application process as the preferred delivery model. Enables targeted investment in areas of greatest need, transparent decision making, and alignment with employer demand and system priorities
  • Chosen: Grant funding approach rather than traditional procurement. Reflects the restricted statutory further education provider market

Implications

  • Financial: Funding is included within the Medium-Term Financial Plan and will be managed in line with CPCA financial procedures and DfE requirements. Report P13
  • Legal: The programme is designed to comply with DfE funding requirements and Memorandum of Understanding conditions, and CPCA governance and assurance processes. A subsidy control assessment will be required.
  • Other: The programme is expected to contribute to public health outcomes by improving access to education and skills pathways, supporting employment outcomes, and addressing inequalities in access to opportunity.
  • Climate: The programme will support investment in modern, energy-efficient infrastructure, and development of skills aligned to net zero and retrofit activity.
  • Other: Significant economic and social impact is expected, including supporting housing and infrastructure priorities, addressing skills shortages, and establishing a foundation for longer term strategic skills capital investment linked to spatial planning.

Who and where

  • Further education colleges, sixth form colleges and 16 to 19 academies across Cambridgeshire and Peterborough, as the only eligible recipients of DfE funding Report 3.1
  • 16 to 19 learners, particularly in areas of demographic growth Report 2.1, P6
  • Construction and technical industries, addressing labour market shortages Report P6, 3.1
  • Residents across Cambridgeshire and Peterborough seeking inclusive access to education and opportunity Report P6

Timeline

  • 2026 to 2030: Period over which the £12.5 million DfE capital funding is to be invested Report 3.1, P13
  • June 2026: Full Business Case submitted to the June Funding Panel, recommended for further review at Funding Committee Report 2.1

Plain English for the jargon

  • Single Assurance Framework (SAF): The Combined Authority's governance and assurance process for approving funding decisions, including programme and project level approvals.
  • DfE: Department for Education, the UK government department providing the £12.5 million capital funding.
  • FE Cold Spots: An existing Combined Authority programme providing capital and revenue funding that is being integrated into this programme.
  • MTFP: Medium-Term Financial Plan, within which the funding is included.
  • MoU: Memorandum of Understanding, the funding terms and conditions set by the Department for Education.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

RESOLVED to: A. Note the development of the Full Business Case for the Post?16 Capacity and Construction Skills Capital Programme ahead of submission through the Combined Authority’s Single Assurance Framework (SAF). B. Provide feedback and commentary, including any questions or suggestions, to inform ongoing programme design and delivery.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Skills Committee

Recommendations

A Note the development of the Full Business Case for the Post-16 Capacity and Construction Skills Capital Programme ahead of submission through the Combined Authority’s Single Assurance Framework (SAF).

B Provide feedback and commentary, including any questions or suggestions, to inform ongoing programme design and delivery.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☒ Resilience

☐ Connectivity ☐ Homes ☒ Performance The Post 16 Capacity and Construction Skills Capital Programme directly supports delivery of the Combined Authority’s Corporate Plan by enabling sustainable economic growth, improving access to high-quality jobs, and strengthening regional resilience. By investing in additional post 16 capacity and modern training facilities, the programme will equip residents with the skills needed in priority sectors—particularly construction and technical industries—helping to address labour market shortages and support delivery of housing and infrastructure ambitions. The focus on targeted, needs led investment and alignment with employer demand also contributes to improved system performance and value for money, while promoting inclusive access to education and opportunity across Cambridgeshire and Peterborough.

1. Purpose

1.1The purpose of this report is to ensure that the Skills Committee is sighted on the development of the Full Business Case for the Post-16 Capacity and Construction Skills Capital Programme prior to submission to the Funding Committee, and to provide Members with the opportunity to review and provide input. Whilst formal decision-making for funding sits within the Single Assurance Framework, this report reflects the Committee’s role in strategic oversight, challenge and direction of skills provision across the region. 2. Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Full Business CaseAppendix A 1.3 MB Download
PDF
Post 16 Capacity Skills Capital FundingReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
TD
Tim DeerCouncil Staff, expected
LN
Councillor Lucy Nethsingha Mayor's RepresentativeChair, present
KC
Councillor Katy Cole Peterborough City CouncilCommittee Member, present
MD
Councillor Mike Davey Cambridge City CouncilCommittee Member, present
MG
Councillor Mark Goldsack East Cambridgeshire District CouncilCommittee Member, present
DH
Councillor Dr Haq Nawaz Fenland District CouncilCommittee Member, present
DM
Councillor Debbie Mickelburgh Huntingdonshire District CouncilCommittee Member, present
EM
Councillor Edna Murphy Cambridgeshire County CouncilCommittee Member, present
EW
Councillor Eileen Wilson South Cambridgeshire District CouncilCommittee Member, present
CH
Charlotte Horobin Business BoardCo-Optee, present
KD
Katy Davies Business BoardCo-Optee, apologies
SC
Councillor Sarah Caine Cambridgeshire County CouncilSubstitute

All 17 on the meeting page

More from Cambridgeshire and Peterborough Combined Authority Skills Committee

All decisions
MeetingDecisionOutcome
14 Sep 2026 Declaration of InterestsCouncillor Davey declared an interest by virtue of his role as a Director of Cambridgeshire United Football Club. Decided Open
14 Sep 2026 Minutes of the previous meetingThe Minutes of the meeting held on 15 June 2026 were approved as an accurate record. The Action Log was noted by the ... Approved Open
14 Sep 2026 Public QuestionsNo public questions were received. Decided Open
14 Sep 2026 Forward PlanA To note the CPCA’s Forward Plan for September 2026. Noted Open
14 Sep 2026 Director's Highlight ReportA. To note the contents of the report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies