Internal Audit Strategy 2026/27 - 2028/29, including the 2026/27 Internal Audit Plan

Approved Finance 1 paper

AI summaryCambridgeshire and Peterborough Combined Authority's Audit and Governance Committee approved the 2026/27 Internal Audit Plan and the associated Internal Audit Charter from provider RSM, covering 10 reviews across the year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal Audit Plan and Charter from RSM approved
MoneyNot stated
What happens nextDelivery of 2026/27 planRSM to begin work from May 2026
Who it affectsCombined Authority governanceRisk-based assurance across CA activities

What was decided

The Audit and Governance Committee approved the Internal Audit Plan for 2026/27, with RSM delivering 10 risk-based and core assurance reviews plus follow-up, advice and management activity. Report P5, P6, P12

The Committee also approved the associated Internal Audit Charter, which sets out RSM's mandate, authority, independence, responsibilities and quality assurance arrangements for the function. Report 3.2, P107, P151

The plan covers key areas including Bus Franchising, AI Governance, Peterborough Station Quarter, Subsidiary Company Governance, EDI Equality Strategy, Grant Funding Agreements, Key Financial Controls, Data Quality and Performance Management, and Skills Programmes. Report P15, P18, P21, P24, P28, P32, P34, P36, P38

Why

Approval of the plan and charter is required to give RSM the formal mandate to provide the Combined Authority with independent, risk-based assurance, advice and insight on its governance, risk management and internal controls. Report 3.2, P107, P124

The plan has been developed by analysing the Combined Authority's corporate objectives, risk profile and assurance framework, and by discussing priorities with senior management and the Committee. Report P4, P50

RSM's approach generally conforms to the requirements of the IIA Standards, and the firm's services are designed to conform to the Global Internal Audit Standards in the UK Public Sector, with the next external quality assessment due in 2026. Report P9, P103, P105, P106

What happens next

RSM will deliver the ten planned reviews, plus follow-up work, ad-hoc advice and consultancy, and management activity such as planning, AGC attendance and liaison with external audit, between May 2026 and June 2027. Report P6, P42, P44, P45

Progress will be reported through six AGC meetings, pre-meetings, and the regular cycle of draft and final reports, with annual opinion provided at financial year end to inform the Annual Governance Statement. Report P6, P150

The charter and plan are to be reviewed annually with the head of internal audit, and the plan will remain flexible to respond to changes in risks and organisational priorities. Report P5, P126, P134

Options considered

  • Chosen: Approve the Internal Audit Plan and associated Internal Audit Charter. Formalises the mandate and gives RSM authority to deliver the 2026/27 programme. Report P5, P151

Implications

  • Legal: Approval meets the requirement to establish an internal audit charter under the Global Internal Audit Standards, and provides the legal basis for RSM's access, authority and reporting lines. Report 3.2, P107, P108, P124
  • Risk: The plan targets the Combined Authority's highest-rated strategic risks, including bus reform delivery, equalities compliance, AI adoption, Peterborough Station Quarter delivery and subsidiary company governance. Report P17, P20, P23, P26, P30
  • Staffing: Internal audit is outsourced to RSM, led by Dan Harris as Partner and Head of Internal Audit, supported by Nick Fanning as Managing Consultant and other specialists as required. Report P6, P152

Who and where

  • Cambridgeshire and Peterborough Combined Authority and its senior management, who will receive independent assurance on governance, risk and controls Report P5, 3.2, P107
  • The Audit and Governance Committee, which will receive six progress reports, induction and training, and pre-meetings during 2026/27 Report P6
  • Subsidiary companies of the Combined Authority, whose governance arrangements will be reviewed under the Subsidiary Company Governance audit Report P28, P29, P30

Timeline

  • May 2026: Grant Funding Agreements audit fieldwork starts Report P32
  • June 2026: Data Quality and Performance Management audit fieldwork starts Report P34
  • July 2026: Peterborough Station Quarter audit fieldwork starts Report P24
  • August 2026: AI Governance audit fieldwork starts Report P21
  • September 2026: EDI Equality Strategy audit fieldwork starts Report P18
  • October 2026: Bus Franchising audit fieldwork starts Report P15
  • November 2026: Key Financial Controls audit fieldwork starts Report P36
  • December 2026: Subsidiary Company Governance audit fieldwork starts Report P28
  • January 2027: Skills Programmes and Follow Up audits start Report P38, P42

Plain English for the jargon

  • AGC: Audit and Governance Committee of the Combined Authority
  • RSM: RSM UK Risk Assurance Services LLP, the external provider of internal audit services
  • IIA: Institute of Internal Auditors, the body that sets the Global Internal Audit Standards
  • EQA: External Quality Assessment, an independent review of an internal audit function required every five years
  • PSQ: Peterborough Station Quarter, a major project subject to a 2026/27 audit review
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17c

Resolved

It was resolved to: A. approve the Internal Audit Plan and the associated Internal Audit Charter.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Audit and Governance Committee

Appendices

2.1Internal Audit Strategy 2026/27............................................................................................................................................... 10

3.1Your Internal Audit Service ..................................................................................................................................................... 14

3.2Internal Audit Charter .............................................................................................................................................................. 15

2 EXECUTIVE SUMMARY Our approach to developing your internal audit plan is based on analysing your corporate objectives, risk profile and assurance framework as well as other, factors affecting Cambridgeshire & Peterborough Combined Authority in the year ahead, including changes within the sector.

Our Internal Audit Plan for Cambridgeshire & Peterborough Combined Authority has been presented and approved previously by the Audit & Governance Committee (AGC). We have however now formalised the plan into our fully compliant strategy document for approval at this meeting. The Committee are asked to approve the Internal Audit Plan and associated Internal Audit Charter. During the year, we will continue to work with management and hold regular meetings to deliver an internal audit programme which remains flexible and agile to ensure it meets your needs. The key points to note from our plan are:

Your core team are Dan Harris, Partner, your Head of Number of deliverables 10 (including follow up). We will Internal Audit and Nick Fanning, Managing Consultant who also provide an annual opinion, an audit plan, issue clients are supported by specialists, as required. briefings, attend six AGC meetings and AGC induction and training sessions, AGC pre-meetings and hold our regular update meetings with key senior officers.

Flexible and agile approach to deliver in order to respond All of our work is costed in line with our contract with to your needs. you, including the work delivered by specialists.

Technology toolkit – 4questionnaires, Alteryx, Internal Audit Charter, at Section 3.2. PowerBi

‘RSM generally conforms to the requirements of the IIA Standards’ and RSM IA also generally conforms with the other Professional Standards and the IIA Code of Ethics’.

3 Annual Internal Audit Plan

01 and Methodology

01 4 1.1 INTERNAL AUDIT PLAN 2026/27 The table below shows each of the reviews that we propose to undertake as part of the internal audit plan for 2026/27. The table details, as applicable, the strategic risks which have focused our internal audit coverage. This review of your risks allows us to ensure that the proposed plan aligns with the organisation’s assurance needs for the forthcoming and future years.

Audit Proposed AGC Proposed timing approach Reporting

Risk Based / Driven Internal Audit Activity

Bus Franchising Risk based October 2026 January 2027

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Strategy 2026/27: 2028/29, including the 2026/27 Internal Audit PlanReport 569 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
RJ
Rhys Jarvis Independent PersonChair, present
IA
Councillor Imtiaz Ali Peterborough City CouncilCommittee Member, present
RC
Councillor Rory Clark Cambridgeshire County CouncilCommittee Member, present
GC
Councillor Gary Christy Fenland District CouncilCommittee Member, apologies
LD
Councillor Laurence Damary-Homan South Cambridgeshire District CouncilCommittee Member, present
PH
Councillor Paul Hodgson-Jones Huntingdonshire District CouncilCommittee Member, present
MI
Councillor Mark Inskip East Cambridgeshire District CouncilCommittee Member, apologies, sent representative
MT
Councillor Mike Todd-Jones Cambridge City CouncilCommittee Member, present
DH
David HarwoodIndependent Person, present
PF
Councillor Peter Fane Cambridgeshire County CouncilSubstitute
QF
Councillor Qaiser Farid Peterborough City CouncilSubstitute
DM
Councillor Douglas Mcllwain Huntingdonshire District CouncilSubstitute

All 15 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Internal Audit Strategy 2026/27 - 2028/29, including the 2026/27 Internal Audit PlanThis decision
  2. Internal Audit - Progress ReportNoted
  3. Internal Audit - Progress ReportNoted
  4. Internal Audit - Draft Annual Internal Report 2025/26Noted
  5. Internal Audit Action Tracker ReportNoted
  6. Internal Audit - Progress ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Audit and Governance Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 Corporate Risk Register and Deep DivesA. To endorse the Corporate Risk Register, Dashboard and Heatmap for August 2026 (Appendices A-C) B. To undertake a d... Noted Open
10 Sep 2026 Exclusion of Press and PublicIt was RESOLVED that the press and public be excluded from the meeting on the grounds that Appendices D and E to item... Decided Open
10 Sep 2026 Re-admittance of Press and PublicIt was RESOLVED to re-admit the press and public. Decided Open
10 Sep 2026 Rewiring the State and Opportunities for Cambridgeshire and PeterboroughThe Committee noted the update on ‘Rewiring the State’ Cabinet Statement and recent Government announcements, the opp... Noted Open
10 Sep 2026 CPCA UpdateThe Assistant Director Finance and IT provided an update on recent CPCA activities. Decided Open