Resolved
RESOLVED – that a) The report be noted b) That the Overview and Scrutiny Committee express their thanks to Housing Department for achieving 100% gas maintenance check success.
Overview Committee (02-15) noted this item on Wednesday 20 May 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – that a) The report be noted b) That the Overview and Scrutiny Committee express their thanks to Housing Department for achieving 100% gas maintenance check success.
OVERVIEW AND SCRUTINY COMMITTEE
20 May 2009
Subject: Planned Maintenance Works – Technical Risks
Director/Head of Service: Head of Housing
Decision Issues: No decision required
Decision type: N/A
Classification: This report is open to the public.
CCC Ward(s): All Wards
Summary: This report relates to the planned maintenance works carried out to Council-owned housing properties. It sets out how we mitigate the risks involved in the programming and the scope of each element of work.
To Consider: The contents of this report
Next stage in process None
SUPPORTING INFORMATION
1. Introduction
Members of the Overview and Scrutiny Committee requested a report outlining how we mitigate risks involved in planned maintenance works.
In order to maintain and prolong the life of the Council’s housing stock, and to provide high quality, modern accommodation, capital investment is required in a programmed and efficient manner.
Historic investment and stock condition dictates the current programme of improvement works with the level of investment set by the Housing Revenue Account Business Plan. This in turn sets the budget for each individual element of works over a 30 year projection with the initial five years set out in more detail.
This report sets out the various risks involved when carrying out each of the capital works elements.
2. Detail
To ensure that no one area or part of the stock is allowed to fall into disrepair, various improvement works programmes are planned and carried out relating to both internal and external elements. These key priorities are defined using he technical stock condition information we collect about our properties, Once prioritised using stock condition information, works programmes are set using the age of the element as the priority, with the replacement age recommended by Government and Industry recommendations.
The elements of work relate to the major components of each dwelling, as follows:
• Roof covering replacement • Window replacements • Door replacements • Kitchen replacements • Bathroom replacements • Heating system replacement or upgrades • Electrical system upgrades
As each element has been carried out previously at differing times in various properties, and the lifespan of each element varies, there is a constant cycle of works being carried out. We try to mitigate as many programming risks as possible, ranging from disruption to the tenant due to a constant series of improvements being carried out, to avoiding disruptive works to recently completed improvements.
This may give the impression that the works are not coordinated, but the priorities are set by the criteria stated above. There are occasions when two cycles of differing work coincide and are then carried out at the same time. However, there are occasions when the cycles are slightly out of sequence and one element will follow another. We make every effort to avoid this by adjusting the annual programmes whenever possible without compromising the safety or integrity of the property.
Each element of work is competitively tendered and all our contracts now have an option to extend them based on the performance of the contractor. This ensures continuity of service and encourages continuous improvement. In addition it enables more accurate long-term programming. We are able to confidently publish a forward programme, in some cases up to five years in the future. Tenants are thus well informed as to when these major works are likely to be carried out to their home. We are also able to inform leaseholders in advance when they are likely to incur expenditure.
With this long-term programme, there is a more coordinated and efficient approach to the works with the separate contractors working more as a team rather than simply concentrating on their specialised area.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planned maintenance works: technical risksReport | 90 KB | DownloadRead as text |
Follow Overview Committee (02-15) at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Mar 2015 | Exclusion of the press and publicRESOLVED – That under Section 100(A)(4) of the Local Government Act 1972, the press and public be excluded from the m... | Decided | Open |
| 25 Jun 2014 | Exclusion of the press and publicRESOLVED – That under Section 100(A)(4) of the Local Government Act 1972, the press and public be excluded from the m... | Decided | Open |
| 14 May 2014 | Election of ChairmanRESOLVED – That Councillor O’Dea be elected Chairman of the Committee for the Council Year 2014/15. (Councillor O’Dea... | Decided | Open |
| 14 May 2014 | Election of Vice-ChairmanRESOLVED – That Councillor Baker be elected Vice-Chairman of the Committee for the Council Year 2014/15. | Decided | Open |
| 14 May 2014 | Appointment of Working Groups for the Council Year 2014/15RESOLVED – That the following Working Groups be re-appointed for the Council Year 2014/15 with the membership indicat... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.