RESOLVED – that: a) the Board supports the role of project manager being undertaken by a council project engineer whose time will be recharged to the project; b) the land upon which the project will be constructed will be made available for at least 5 years at no charge; c) the Council will act as the ‘accountable body’ to administer the grant; d) the future maintenance of the completed structure will be undertaken as part of the routine maintenance of the harbour within the harbour budget. As a point of clarification on Resolution (d), it was confirmed that the Whitstable Improvement Trust was not allowed to assume any liabilities for the future maintenance of the structure.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Director/Head of Service: Head of Property and Engineering Services
Decision Issues: These matters are within the authority of the Board
Decision type: Non-key
Classification: This report is open to the public.
CCC Ward(s): Harbour
Summary: The report provides an update on progress with this project and invites the Board to confirm certain decisions
To Resolve: a) that the Board supports the role of project manager being undertaken by a council project engineer whose time will be recharged to the project;
b) the land upon which the project will be constructed will be made available for at least 5 years at no charge;
c) the Council will act as the ‘accountable body’ to administer the grant;
d) the future maintenance of the completed structure will be undertaken as part of the routine maintenance of the harbour within the harbour budget.
Next stage in process Await outcome of Stage 2 bid
SUPPORTING INFORMATION
1. Introduction
Following the development of ideas over several years for a ‘community area’ at the harbour the Board approved in May 2009 the submission of a bid for £50,000 to the CABE Sea Change programme. Subsequently it became clear that the project was of an insufficiently large scale to qualify for the programme and it was suggested that a bid be made to the Big Lottery Community Spaces Fund instead. Local authorities are not eligible to bid to this fund so Whitstable Improvement Trust agreed to submit the bid provided that the Harbour Board provided financial and other support. The Board had previously agreed, subject to Executive approval, to contribute £25,000 to the project from harbour reserves and the Executive had supported that proposal.
2. Detail Planning permission has been granted for the project. The Stage 1 application to the Big Lottery was successful and I expect the Stage 2 bid to have been submitted by the date of this meeting. The bid facilitator sees it as a strength that the bid is supported by the Council, through the Harbour Board, and that the Council’s resources can be used to facilitate the project by:
a) Providing technical project expertise –
An experienced member of the Council’s civil engineering team will assume the role of project manager to procure and supervise the construction work. The cost of his time will be charged to the project.
b) Providing the necessary land –
Although the size of the grant does not require a legal interest in the site to be granted by the Board to the Whitstable Improvement Trust, the Board is asked to undertake to make the site available for a minimum of 5 years at no charge.
c) Acting as the accountable body for the grant –
The Big Lottery requires a responsible organisation to assume responsibility for administering the grant money. The Council is eligible to undertake this role.
d) Undertaking the ongoing maintenance of the finished construction –
While it is prepared to be the applicant for the grant WIT does not wish to assume any liabilities for the future maintenance of the structure. The materials for the structure have been chosen because of their longevity and the minimal need for maintenance. There is some planting, however, that will require periodic attention, and the area will need to be regularly cleaned. It is considered that this can be included within the harbour’s routine cleaning and maintenance arrangements.
The elements of this support have been discussed informally at Board meetings but formal decisions have not been recorded. The Board is asked to formally confirm the arrangements now.
3. Relevant Council Policy/Strategies/Budgetary Documents
The Harbour Board’s objectives are:
• To meet the ambitions of the local community • To maintain and develop the Harbour’s environs • To support the local economy
This project appears to comply with all of these.
4. Consultation planned or undertaken
There has been, and will continue to be, extensive consultation and community involvement in the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci...
Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.