Whitstable Harbour Board, Friday 4 March 2011 at 3.00pm

Harbour Action Plan

Agreed Committee 1 paper

Whitstable Harbour Board agreed this item on Friday 4 March 2011. Below is the council's own wording, with the papers it was decided on.

Item605

Resolved

It was agreed that this item would be removed from the Action Plan. Ref 4.2D(c): Confirm marketing approach to key decision makers for contracted support services to wind-farm industry and liaise with Vestas / Vattenfall to determine support service opportunities – There would be continued liaison with Vestas / Vattenfall. The wind farm would be considered under a later item on the agenda. Ref. 4.2D(e): Support marketing activities for pleasure craft activities and construct suitable embarkation facilities for pleasure craft – A Member asked if the Board had seen the proposals and plans for the embarkation facilities. It was agreed that these would be included on the next Harbour Board agenda. Another Member requested that they should also be included on the next ... view the full minutes text for item 605.
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Whitstable Harbour Board

Whitstable Harbour Work Plan February 24, 2011

Ref Action Priority Officer Lead Board Due date Observations Responsible Member

CURRENT ISSUES

1 Conclude on lease arrangements with WOFC 1 MCB n/a 03/11 Verbal update to meeting

2 Review of future of South Quay Shed 1 MCB n/a 03/11 Report on agenda

3 Relocation of tenants from Faversham 2 MW n/a 04/11 PM&HM to report in April

12 Whitstable Harbour Work Plan February 24, 2011

Ref Action Priority Officer Lead Board Due date Observations Responsible Member

DEVELOPMENT ISSUES [References to Development Issues relate to sections of the Board's Strategic Plan]

4.1(a) Determine marketing approach in conjunction with other 2 MW MWG 03/11 Verbal update to meeting (KB) parties within the Harbour and with other parties who are developing the profile of the town

4.1(a) Prepare structure and content of Harbour website for 2 MW MWG 03/11 Website expected to be in operation inclusion within CCC website or for separate but linked site

4.1(e) Review regeneration plans for Angling Club building 2 MCB n/a ongoing

4.1(e) Determine nature and extent of upgrade to toilet facilities 1 DH n/a ? Executive deferred approval to funding

4.1(e) Introduce parking facilities for cyclists 1 MW n/a 03/11 Facilities being incorporated within Dead Man's Corner Remove from Plan 4.2D(c) Confirm marketing approach to key decision makers for 2 MW n/a ongoing Existence of formal decommissioning programme contracted support services to wind-farm industry confirmed

4.2D(c) Liaise with Vestas/Vattenfall to determine support service 2 MW n/a ongoing opportunities Whitstable Harbour Work Plan February 24, 2011

Ref Action Priority Officer Lead Board Due date Observations Responsible Member

4.2D(e) Support marketing activities for pleasure craft activities 2 MW MWG 04/12

4.2D(e) Construct suitable embarkation facilities for pleasure craft 2 MW SQWG 09/2011 Included in South Quay repairs

4.2B(a) Develop weather-resistant accommodation for retail trading 2 MCB SQWG 03/11 WG to meet

4.2B(b) Develop accommodation for small business and business 2 MCB SQWG 03/11 WG to meet start-up units

4.2B(c) Develop accommodation for creative enterprises 2 MCB SQWG 03/11 WG to meet

4.2B(d) Support and help co-ordinate the grant funding and 1 MDB n/a 03/11 Contract awarded. Work on target. Community development of Dead Man's Corner involvement arranged

4.2B(e) Provide land area for the construction of a barge museum. 1 MCB SQWG 03/11 Museum undertaking investigations. Report concerning Consideration to be given to expanding the role of the facility rent on agenda.

4.3(c) Liaise with WRWUG to ensure the optimal use of land and 3 MW CW/JH 03/11 Awaiting formal response. appropriate facilities are in place on the Long Beach

4.3(d) Assess the development potential for additional beach huts 2 MDB n/a 03/11 Work has started dependent on demand conditions and CCC's alternative supply and pricing arrangements

4.3(d) Establish timetable for painting of existing beach huts 3 MDB JH 03/11 Tester hut painted. Remainder to be completed with new huts. Offer of modest contribution from WIT.

STANDING ISSUES (ANNUAL) Whitstable Harbour Work Plan February 24, 2011

Ref Action Priority Officer Lead Board Due date Observations Responsible Member

S1 Review and update Harbour Board Constitution n/a JT Board Mar

S2 Review Port Marine Safety Code issues and compliance n/a MW Board Mar Defer to April meeting in absence of PM&HM

S3 Review annual financial results n/a MJ n/a Jun

S4 Prepare Annual Report and Annual Meeting n/a MW ARWG Sep

S5 Recruit new Harbour Board member(s) n/a DH MD Nov Recruitment to commence May 2011

S6 Review dredging requirements n/a TE DWG Nov

S7 Submit five year revenue and capital expenditure summary n/a MJ n/a Nov

S8 Submit and approve annual budget and five year forecast n/a MJ n/a Jan

S9 Confirm adjustments to port charges n/a MW Board Jan

Officers and Working Groups Board members Working Group members

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Harbour Action PlanReport 54 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Harbour Action PlanThis decision
  2. Harbour Action PlanDecided
  3. Harbour Action PlanDecided
  4. Harbour Action PlanDecided
  5. Harbour Action PlanNoted
  6. Harbour Action Plan (confidential items)Decided

More from Canterbury Whitstable Harbour Board

All decisions
MeetingDecisionOutcome
26 Jun 2026 Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci... Decided Open
26 Jun 2026 Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,... Noted Open
26 Jun 2026 Membership of the South Quay Task and Finish GroupRESOLVED that: The membership of the South Quay Task and Finish Group remain unchanged. A recorded vote was taken as ... Decided Open
26 Jun 2026 Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc... Decided Open
16 Jan 2026 Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc... Decided Open