General Purposes Committee decommissioned 13/05/2013 approved this item on Monday 6 February 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That with effect from 1 April 2012, a pay rise of 1% for all employees be awarded, subject to the approval of the council’s budget for 2012/13 by Full Council. (At the commencement of the meeting, Councillor Flaherty declared a personal interest in this item as a member of his family was employed by the city council).
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to General Purposes Committee decommissioned 13/05/2013
Subject: Pay Award for 2012/2013
Director / Head of Service: Chief Executive / Head of Community Development and Outdoor Leisure (Interim EKHR Client)
Decision Issues: These matters are within the authority of the General Purposes Committee
Decision type: Non-key
Classification: This report is open to the public.
CCC Ward(s): All
Summary: This report considers the annual pay award for the financial year 2012/13 against the financial background that currently exists.
To Resolve: Whether the council awards, with effect from 1 April 2012 a pay rise of 1% for all employees, subject to approval of the council’s budget for 2012/13 by Full Council
Next stage in process If approved, the pay increases to be implemented
SUPPORTING INFORMATION
1. Introduction
The council has not been party to the National Terms and Conditions Agreement for staff but its local terms and conditions provided that the council will pay not less than the National settlement for annual pay awards.
In 2009, councils were facing difficult financial circumstances and it was felt that it would be in the council's and staff's interests to have certainty about the pay inflation to include in the budget for the next two years. The agreed position from discussions with the Trade Union and approved by General Purposes Committee in October 2009 was:
• that pay rates at all spinal column points be increased by 1% with effect from 1 October 2010 (note: National Settlement date is 1 April) • that pay rates for 2011/12 be increased by 1% from October 2011 subject to the following provisos:
o that in mid September 2010 consideration will be given to RPI for August 2010 and the award be reconsidered if the marked increase in RPI is greater than 1% and any revised award should then be payable from April 2011
o that any awards will be subject to and over-ridden by any government imposed pay restraint policy.
2011/12 award: Due to the continued difficult financial circumstances councils were facing, and following discussion with the Finance Sub Group of the Executive, officers made the Trade Union an offer which matched the terms of the Chancellor’s statement. That offer was that, instead of the 1% across the board, the council awarded a pay rise of £250 per annum, with effect from 1 October 2010, to those employees on a full time equivalent salary of £21,000 or less, in line with the government’s announcements on public sector pay. For all other staff pay rates remained at current levels. 2. Detail The coalition government Comprehensive Spending Review (CSR) has resulted in plans for the biggest and longest lasting cuts in public finances for decades. The total formula grant (i.e. the total of Revenue Support Grant and Business Rate pool grant) for Canterbury is expected to fall by 28% over the four year period 2011/12 to 2014/15. Through robust financial planning, the budget for 2012/13 is balanced, and only a small funding gap exists for 2013/14. Projections beyond that show an increasing revenue budget gap of £1 million by 2014/15, rising to £2.6 million by 2015/16, although the savings demanded from Heads of Service over that period will have a significant impact on those figures. The budget strategy identifies in detail the implications of reduced government funding over the next four years, and also the measures to be implemented to meet the financial challenge. These include amongst other things:- • Carry out customer focus reviews in all services which are not subject to joint working. Heads of Service have been tasked with reducing gross budgets of at least the equivalent of 20% over the 4 year budget projection term. • Continued potential savings from the phase 1 of shared services. • No general inflation provision other than for contracts. • Introduce a ‘user pays’ principle to highly subsidised services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow General Purposes Committee decommissioned 13/05/2013 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
Exclusion of the press and publicRESOLVED - That under Section 100(A)(4) of the Local Government Act 1972, the press and public be excluded from the m...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.