Canterbury City Council
Joint Transportation Board, Tuesday 21 February 2012 at 7.00pm

Highway Works Programme 2011/12

Noted Committee 1 paper

Joint Transportation Board noted this item on Tuesday 21 February 2012. Below is the council's own wording, with the papers it was decided on.

Item84

Resolved

RESOLVED – That the report be noted.
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Joint Transportation Board

Subject: Highway Works Programme 2011/12

Director/Head of Service: Director of Highways, Kent County Council

Decision Issues: These matters are within the authority of the Board

Decision: Non-key

Ward/Division: All

Summary: This report updates Members on the identified schemes approved for construction in 2011/12.

To Recommend: This report is for Members’ information.

Classification: THIS REPORT IS OPEN TO THE PUBLIC Introduction

1. This report is an update on that made to previous meetings of the Board and summarises the identified schemes that have been programmed for construction by Kent County Council- Highways and Transportation (KCC H&T) 2011/12.

Road Surface Treatments

Thin surfacing - see Appendix A1

Highway Maintenance Schemes

Footway Schemes – see Appendix B1 Street Lighting Schemes - see Appendix B2 Weather Damage Repairs – see Appendix B3 Local Transport Plan Funded Schemes - see Appendix C1 Countywide Schemes- See Appendix C2 Public Rights of Way– see Appendix C3 Developer Funded Schemes (Delivered by KCC H&T) - see Appendix C4

Other Works

Bridge Works - see Appendix D1 Borough Council Funded Schemes - see Appendix D2 County Member Funded Works - see Appendix D3 -See also additional Annex 1 attached to this report Drainage – see Appendix D4 Major Capital Projects - see Appendix D5

Conclusion

3. This report is for Members’ information.

Contact Officers:

Toby Howe Highway Manager (East) Chris Maw District Manager Mary Gillett Resurfacing Manager Sue Kinsella Street Lighting Manager Andy Corcoran Traffic Schemes and Members Highway Fund Manager Andrew Hutchison Public Rights of Way Area Manager (East) Tony Ambrose Structures Manager Katie Lewis Interim Flood and Drainage Manager APPENDIX A – ROAD SURFACE TREATMENTS

APPENDIX A1 – THIN SURFACING: 15 – 24mm depth

Location Description Parish Budget Status A290 Honey Hill Pean Hill/Clapham Blean £674,825 Completed Hill-Tyler Road- A299 Roundabout A28 Wincheap & From A2 over Canterbury City £176,122 Complete Nov Thanington bridge – Simmonds 2011. High Road (Nearest friction railway bridge) Surfacing still to complete A2050 Rheims Way London Road Canterbury City £63,872 Complete Nov & London Road roundabout 2011. (including Knight Avenue entrance) St. Georges Place & St. Georges Canterbury City £54,585 Complete Nov St. Georges roundabout 2011. roundabout including St. Georges Place exit from Canterbury to Waitrose car park entrance. London Road Approach to St. Canterbury City £11,644 March 2012 Canterbury Dunstan’s Street roundabout B2205 Canterbury Joy Lane – Whitstable £88,270 March 2012 Road Whitstable Belmont Road

APPENDIX B – HIGHWAY MAINTENANCE SCHEMES

APPENDIX B1 – FOOTWAY SCHEMES

Location Description Parish Budget Status Queens Road Whole Length Whitstable £96,463 Completed

Upper Bridge Between St.Georges Canterbury City £100,000 To be Street Place and Old Dover programmed: Road March 2012 Rhodaus Town Between Old Dover Canterbury City £75,000 To be Road and Rhodaus Programmed: Close February/March 2012 APPENDIX B2 – STREET LIGHTING

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Works Programme 2011/12Report 123 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Highway Works Programme 2011/12This decision
  2. Highway Works ProgrammeAgreed
  3. Highway Works ProgrammeAgreed
  4. Highway Works ProgrammeAgreed
  5. Highways Works Progress ReportNoted

More from Canterbury Joint Transportation Board

All decisions
MeetingDecisionOutcome
24 Mar 2026 Highway Works ProgrammeIt was agreed an update would be provided at the next meeting. The white lining in the report only referred to major ... Agreed Open
24 Mar 2026 Update on Richmond Street and Dolphin Street One WayIt was agreed that the Chair and Vice Chair would write to the KCC Cabinet member for transport to conduct a full rev... Agreed Open
21 Oct 2025 Highway Works ProgrammeIt was agreed that this would be raised with KCC colleagues to add to the list of works. Some of the street lighting ... Agreed Open
18 Jun 2024 Active Travel UpdateIt was agreed to include this in AOB (JTB10) to be picked up by relevant officers. The report was NOTED. Agreed Open
19 Mar 2024 Annual Parking ReviewAGREED by general assent. RECOMMENDED (to the KCC Cabinet Member for Highways and Transport): a. To action the follow... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies