RESOLVED – That conventional dredging was still the best option for Whitstable Harbour and that there should be adequate notification regarding the dredging. This method should be used for the next dredge, due about September 2014. However, if more information became available about the effects of water injection dredging carried out adjacent to shellfish beds close to the time that the next dredge was due, then the situation might be reviewed.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Director/Head of Service: Head of Planning and Regeneration
Decision Issues: These are within the authority of the Board
Decision: Non Key
Ward: Harbour
Summary: This report re-examines the use of water injection dredging as opposed to conventional dredging, which is currently carried out at the harbour, and makes recommendation as to the way forward.
To Resolve: That conventional dredging is still the best option for Whitstable Harbour. This method should be used for the next dredge, due about September 2014. However, if more information comes available about the effects of water injection dredging carried out adjacent to shellfish beds close to the time that the next dredge is due, then the situation may need to be reviewed.
Classification: This report is open to the public.
SUPPORTING INFORMATION
1. Introduction
Members will recall that the possibility of water injection dredging (WID) being carried out at the harbour has been discussed a number of times. At the November 2010 meeting of the board it was resolved that conventional dredging be carried out for the foreseeable future and the situation be reviewed in three years time when more information on WID, and its potential effects on shellfish beds, might become available. Members have asked for an update on the situation and this report summarises the present situation.
2. Background The current practice for dredging the harbour is that it is carried out on an “as and when required” basis. This is when the silt level has built up to such an extent that the larger vessels have difficulty in entering/leaving the harbour except on the higher spring tides. Generally this is when there is about 8,500 m3 of silt within the harbour basin and particularly when the silt is high between the East and West Quays. Dredging of the harbour has in the past therefore been necessary on average once every three years. The method of dredging has always been the conventional method of grab or bucket dredging from a floating pontoon/barge and transportation from the harbour in a bottom-emptying barge for disposal at a designated marine disposal area. The current disposal area is located 1.2 km offshore of Long Rock. The last dredge was completed in September 2011 and 7,500m3 was removed at a cost of £74,416. This was actually £3,500 cheaper than the cost of the dredge in 2008. A FEPA Licence, operated by the Marine Management Organisation (MMO), has always been required for conventional dredging and disposal at sea and this usually takes about four months to receive from initial application. The Licence requires that the silt is tested for potential contaminants, which all must be below certain stipulated levels. The Licence procedure also requires consultation with and the approval of various authorities including Natural England, Environment Agency and Kent & Essex Sea Fisheries Committee. An alternative method of dredging is by the Water Injection Dredging (WID) method and this possibility has been discussed by the Harbour Board on a number of occasions in the past. WID is likely to be cheaper than conventional dredging in the long term and could be carried out on an annual basis to keep the silt continually at a lower level. WID is quite commonly used elsewhere and is a tried and tested method. The major concern about WID is that it could affect the shellfish beds outside the harbour. A further concern is that from 1st April 2012 it will also require a FEPA Licence and in view of the internationally designated marine nature conservation site immediately to the west of the harbour, as well as potential risk to the shellfish beds, the licence conditions are likely to be severe. A full Environmental Impact Assessment (EIA) would also be needed.
3. Relevant Council Policy/Strategies/Budgetary Documents
Whitstable Harbour Strategic Plan 2010.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci...
Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.