It was agreed that where appropriate this distinction would be highlighted in future reports. The reason for its inclusion was so the committee were aware of how the service was functioning across all districts. It was pointed out that the Business Rates collection for Canterbury was excellent with a target collection rate of 99.5%, which was exceptional. Reference was also made to the regular client review meetings at which any local issues were raised and discussed. A Member asked if were there any financial implications for the Payroll service if the audit review remained at reasonable/limited? It was noted that the review had looked at the operation of payroll in the first year and found that strategic management was not as good as they would have liked. Due to the forthcoming review in 2014, it was anticipated that the council would be looking forwards and it was accepted that there was little value in putting resource into rectifying historic issues given the changes that were proposed. RESOLVED – that the report be noted.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
East Kent Audit Partnership Update Subject: report
Director/Head of Director of Resources Service:
Decision Issues: This matter is within the authority of the Audit Committee.
Decision: Non-key
Classification: Non confidential.
Ward: All
Summary: This report informs members of progress against the audit plan approved by them in March 2012.
To Resolve That this committee accept the results of audit work and make comments, if required to Full Council.
SUPPORTING INFORMATION
1. Issues for consideration The Committee is asked to agree the options set out below because: In order to comply with best practice, the Audit Committee should independently contribute to the overall process for ensuring that an effective internal control environment is maintained. This report includes the summary of the work of the East Kent Audit Partnership since the last Audit Committee meeting together with details of the performance of the EKAP to the 31st December 2012.
1.2AUDIT REPORTING For each Audit review, management has agreed a report, and where appropriate, an Action Plan detailing proposed actions and implementation dates relating to each recommendation. Reports continue to be issued in full to the relevant Directors, as well as an appropriate manager for the service reviewed. Follow-up reviews are performed at an appropriate time, according to the status of the recommendation, timescales for implementation of any agreed actions and the risk to the Council.
An Assurance Statement is given to each area reviewed. The assurance statements are linked to the potential level of risk, as currently portrayed in the Council’s risk assessment process. The assurance rating given may be Substantial, Reasonable, Limited or No assurance.
Those services with either Limited or No Assurance are monitored, and brought back to Committee until a subsequent review shows sufficient improvement has been made to raise the level of assurance to either Reasonable or Substantial. A list of those services currently with such levels of assurance is attached as Appendix 2 to the EKAP report.
The purpose of the Council’s Audit Committee is to provide independent assurance of the adequacy of the risk management framework and the associated control environment, independent review of the Authority’s financial and non-financial performance to the extent that it affects the Authority’s exposure to risk and weakens the control environment, and to oversee the financial reporting process.
To assist the Committee meet its terms of reference with regard to the internal control environment an update report is regularly produced on the work of internal audit. The purpose of this report is to detail the summary findings of completed audit reports and follow-up reviews since the report submitted to the last meeting of this Committee.
1.3SUMMARY OF WORK There have been eight Internal Audit reports that have been completed for the period. These have been allocated assurance levels ranging from substantial to reasonable: three were substantial and three were classified as providing a reasonable assurance rating and one was Reasonable / Limited assurance rating. It was not required to provide an assurance level for the last report. Summaries of the report findings are detailed within Annex 1 to this report.
In addition, three follow up reviews have been completed during the period. It is usual to find when the follow up review is undertaken, that the vast majority of recommendations that were agreed by management have been implemented and that management are actively strengthening the internal control environment. Indeed, many of the recommendations in each of the areas previously reviewed have been implemented, however one review remains partially limited.
For the period to 31st December 2012, 127 chargeable days were spent out of a planned total of 180 days. Approximately 70% of the plan has therefore been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.