Resolved
That, subject to circulation of the costs: (a) Temporary toilet provision be arranged for periods of higher demand between the start or April and the conclusion of the expansion. (b) The provision at (a) is to be of high quality.
Whitstable Harbour Board decided this item on Friday 23 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That, subject to circulation of the costs: (a) Temporary toilet provision be arranged for periods of higher demand between the start or April and the conclusion of the expansion. (b) The provision at (a) is to be of high quality.
WHITSTABLE HARBOUR BOARD 23 January 2015
Improvement to the provision of toilets in the Subject: harbour - progress
Director/Head of Service: Assistant Director of Direct Services
Decision Issues: These matters are within the authority of Whitstable Harbour Board
Decision type: Non-key
Classification: This report is open to the public.
CCC Ward(s): Harbour
Summary: This report provides details of the work which has been carried with regards to the improvement of the provision of toilets following the decisions made at the Harbour Board meeting on
To Resolve To agree the timescales and the plans for the works
Next stage in process
Planning committee
SUPPORTING INFORMATION
1. Introduction
Members and officers have been working on plans to improve the toilet facilities at Whitstable Harbour. This work includes increasing the number of toilets and building a changing places facility.
2. Detail
Following a public consultation process in October and November, Members of the Harbour Board considered 3 options,
• Additional facilities at the rear of the RNLI building • Extension to current facilities • Extension to current facilities with extended office space above Members agreed to proceed with the option to extend the current facility with extended office space.
It was originally agreed that the works would be completed by the beginning of the season at Easter 2015.
2.2Update
It became clear soon after the meeting In November that this timescale would not be able to meet this time scale. The reasons for this are
• The need to re draw the plans for the buildings • The two week Christmas close down • The requirement for planning permission (this is likely to take between 8 and 10 weeks) • Other pressures on the Engineers Team arising from the successful bid for the funding for the quay works.
Officers are aware that the current situation is unlikely to be acceptable to members. Whilst the delays have been unavoidable, it is not acceptable that the members were not made aware of the timescales at the time they made their decision on which option. This was due to an error on the part of the officers. This has been reviewed and we are confident this will not happen again in future.
2.3Current Position
Following the last Harbour Board the following work has happened.
• A revised design and drawings for a single storey extension to the existing toilets on Harbour Street has now been completed. - This comprises 3 additional Ladies toilet cubicles and a full specification ‘Changing Places’ cubicle within the proposed extension.
• A Planning application and building control application has been made to the council
• A dedicated project officer has been identified to deliver this project.
2.4Timescale
The timescale to complete the project is set out below
w/c 26 January 2015 – Quotes will be invited from suitably experienced contractors Start on site (subject to grant of planning permission,) – End of March 2015 Project completion – End of June 2015
The existing toilets will be available for use during the period of the works.
3. Relevant Council Policy/Strategies/Budgetary Documents The Harbour strategy plan, shows this piece of work as a strategic priority
4. Consultation planned or undertaken
A consultation was undertake in September - November 2014 in relation to the options available
5. Options available with reasons for suitability
Option 1 (a) Agree the timetable and dedicated project officer (b) Provide funding for additional temporary toilets from Easter to the completion of the work
Option 2 (a) Do not agree the timetable and defer works until after the summer period (b) Do not provide additional toilet facilities
6. Reasons for supporting option recommended, with risk assessment
Options 1 - Although delays have happened with this project, Officers are confident that, subject to planning permission, we will be able to complete the project by the beginning of the summer holidays
7. Implications
(a) Financial Implications – this project is within the agreed budget
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Improvement to the the provision of toilets in the Harbour: Progress reportReport | 61 KB | DownloadRead as text |
Follow Whitstable Harbour Board at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Jun 2026 | Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci... | Decided | Open |
| 26 Jun 2026 | Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,... | Noted | Open |
| 26 Jun 2026 | Membership of the South Quay Task and Finish GroupRESOLVED that: The membership of the South Quay Task and Finish Group remain unchanged. A recorded vote was taken as ... | Decided | Open |
| 26 Jun 2026 | Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc... | Decided | Open |
| 16 Jan 2026 | Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.