RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reason for the decision The list takes account of the views of officers, customers and residents’. Not having a corporate list of KPIs at all would mean that the Council’s performance is not available for Member and public scrutiny.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Corporate Key Performance Indicators – Proposed targets for 2015/16
PI Status Short Term Trends
Alert Improving
Warning No Change
OK Getting Worse
Unknown
Data Only
Commissioned Services
Q3 2013/14 2014/15 Status Short Name 2014/15 Proposed target 2015/16 Rationale for target Value Value Target Target This is an existing contractual Overall customer target within the Mears satisfaction with housing 99.43% 100% 98% 98.00% 98% contract. repairs
This is a provisional target – Percentage of the housing we are waiting for the end of repairs capital programme 87.68% Annual measure 97.50% 95% year result in order to confirm spent whether 95% is a realistic target
Though current performance is Average time to let a council 22.58 strong, it is not feasible to 24.38 24 24 24 home (days) YTD as at Feb reduce the target as performance is heavily
1 Q3 2013/14 2014/15 Status Short Name 2014/15 Proposed target 2015/16 Rationale for target Value Value Target Target dependent on the length of time individual properties remain empty. As just one property being vacant for an extended period before being let can significantly skew the outturn. 24 days is seen as a realistic target.
The target set in existing Service Level Agreement has Average time waiting to be now been improved to reflect seen at the contact centre 8.76 4.4 12.30 12.30 8 general performance levels and (in minutes) the introduction of an appointments scheme.
Average time it takes to answer a telephone call to The target is set in existing 56 21.8 46.20 46.20 46 the contact centre (in Service Level Agreement. seconds)
Target set in existing Service Level Agreement. This is a very Council Tax collected 98.71% 85.73% 86% 98.71% 98.71% challenging target but reflects performance achieved in previous years.
Target set in existing Service Business Rates collected 99.57% 83.96% 88.24% 99.50% 99.5% Level Agreement. This is a very challenging target but reflects
2 Q3 2013/14 2014/15 Status Short Name 2014/15 Proposed target 2015/16 Rationale for target Value Value Target Target performance achieved in previous years.
Target set in existing Service Level Agreement. In previous years performance has been better than target, however in 2015/16 performance may be adversely affected by two factors: The introduction of universal credit, which will remove some Average time to deal with straightforward benefit Housing Benefit and Council 6.26 5.13 8.98 8.98 8.98 cases and leave the Tax Benefit claims and Council dealing with the changes (days) more complex and time consuming ones; and A complete change in the software used to administer benefits, which may impact on processing times, though every effort is being made to minimise any impact
The methodology for People satisfied with their 92.17% Annual measure 92.17% NA – Data only for 2015/16 measuring satisfaction with Marlowe Theatre visit the Marlowe Theatre is being
3 Q3 2013/14 2014/15 Status Short Name 2014/15 Proposed target 2015/16 Rationale for target Value Value Target Target updated to better reflect the views of actual users. Data will be taken from responses to the “Did You Enjoy That?” surveys which are emailed to visitors after the show in order to allow a baseline to be established. This measure will therefore be kept as data only for 2015/16
Target represents realistic growth from current estimate of 909 for 2014/15 and actual outturn of 906 in 2013/14. The Average attendance at a target is based partially on Marlowe Theatre 906 1011 937 889 915 known programming for performance 2015/16 and partially on the expected average for the periods when programming is not yet confirmed.
This is a provisional target based on the 2013/14 outturn Cost to the Council per visit and will therefore be revisited £2.17 Annual measure £2.17 £1.09 to the Marlowe Theatre once the 2014/15 outturn is known, with a view to reducing the cost per visit.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.