Regeneration Committee - Decomissioned 19/5/22 agreed this item on Thursday 9 July 2015. Below is the council's own wording, with the papers it was decided on.
AGREED. RECOMMENDED (to Policy and Resources ): That the budget for the repairs to the Kings Hall be increased to allow the expenditure of £222,568 and the acceptance of the tender from company 1. That a working group be set up to consider the Kings Hall and ways to reduce its financial burden on the council. Reason for the decision : To re-roof the Kings Hall by replacing the leaking roof covering and to replace the corroded roof railings in order that ongoing repair costs, risks of commercial failure to premises’ events from water leaks and continued risk of railing collapse are reduced. The tender from company 1 was selected being the lowest tender received.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Regeneration Committee - Decomissioned 19/5/22
Subject: Kings Hall Re-roofing and Railing Replacement
Director/Head of Service: Tricia Marshall
Decision Issues: These matters are within the authority of the Policy and Resources Committee
Classification: This report is open to the public.
CCC Ward(s): BELTINGE
Summary: To re-roof the Kings Hall by replacing the existing time expired and leaking roof covering.
To replace the corroded and unsafe roof railings
To Recommend (to the The approval of the expenditure of £260,000 for the Policy and Resources contract works. Committee):
Next stage in process Building Services to advise actual tendered value when known. Recommend acceptance to Policy & Resources Committee for expenditure in excess of £200.000
SUPPORTING INFORMATION
1. Introduction The Kings hall was built at the turn of the 20th Century and is an early example of the use of precast concrete construction. The concrete roof was last recovered with asphalt about 18 years ago and for the past 3 years has allowed rainwater to leak through into the theatre accommodation below. The railings which are original have become unsafe and require replacement.
2. Detail
a. Patch repairs to the existing asphalt roof covering have proved only partially successful and it is evident that failures are becoming more frequent. It is proposed to employ a dark grey liquid membrane roofing system with a 20 year guarantee. These systems are suitable for both foot traffic and use in an exposed location. The use of this method will not require removal of the existing surface with subsequent disruption to the hall’s activities. Neither will it affect the roof’s structural loading. The walkway up The Downs which forms part of the roof structure will be treated with a similar system but suitable for vehicular traffic, as used in multi-storey car parks . b. Railings were installed around the roof perimeter at the time of construction. During the previous asphalt re-roofing the cast iron railings were raised to meet new height standards for safety. These alterations and over 100 years of exposure to a marine environment have caused the railings to corrode and crack to the extent that they became unsafe for public protection. An additional fence was erected across the roof 5 years ago to keep the public away from the railings. The condition of all the railings around the roof has given serious concern for the longer term safety of the remainder of the roof protection and the edge protection to the walkway. Temporary railings and supports have been installed and additional iron work welded in place to strengthen the installation. This is only a holding situation. It is proposed to replace the original railings with steel laser cut panels and matching posts to a similar design as the existing. This work is to run concurrent with the re-roofing works and under the same contract.
c. The additional fence can be retained to secure the lower roof areas from skateboarders and other misuse. It also has the potential for allowing chargeable events to take place on the lower roof by providing a controllable access point.
3. Relevant Council Policy/Strategies/Budgetary Documents
Capital Budget £120K unused from 14/15…specifically for this project. Balance from Building Maintenance Reserve.
4. Consultation planned or undertaken Conservation planning. Specialist roofing companies and metal foundries.
5. Options available with reasons for suitability
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Regeneration Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
Election of a Vice-Chair for 2021-22RESOLVED – That Councillor I.Stockley be elected Vice Chair of the Regeneration Committee for the Council Year 2021/22.
The future of Canterbury Boot FairRESOLVED that the council consults on ceasing to run a boot fair using its own staff but offers the opportunity for a...
Reference from the Canterbury ForumThat a report be considered by the council which set out what the alternative sites for the expanded park and ride pr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.