Draft revenue and capital projections for the Whitstable Harbour Board
NotedCommittee3 papers
Policy Committee - Decomissioned 19/5/22 noted this item on Thursday 11 February 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the report be noted. Reason for the decision There is a requirement in the Constitution for the Whitstable Harbour Board to submit to the Policy and Resources Committee a five year capital programme including funding proposals and three year revenue projections.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Policy Committee - Decomissioned 19/5/22
WHITSTABLE HARBOUR BOARD
29 JANUARY 2016
Subject: Draft Revenue and Capital Projections
Head of Service: Assistant Director Direct Services Assistant Director Finance & Procurement
Decision Issues: These matters are within the authority of the Board
Classification: This report is open to the public
CCC Ward(s): Gorrell, Tankerton
This report gives details of the draft 3 year revenue Summary: projections and future capital projections
To Consider That the budget be approved
SUPPORTING INFORMATION
1. Introduction The attached table (Appendix 1) provides the draft projected budgets for 2016/17 to 2018/19 based on the current years projections, and current plans agreed by the Board.
2. Revenue Projections
Appendix 1 shows the budget for 2016/17 agreed by the Board in October 2015. Additional work has been carried out in conjunction with the Harbour Master, the Assistant Director of Direct Services, Engineers and Estate Officers which has amended the projections for 2016/17 slightly as shown in the table. This is due to rigorous analysis through budget monitoring and detailed projections of fees and charges along with analysing the current market conditions. The budget projections for 2017/18 and 2018/19 are included to show the next two years estimated budgets. However income projections are based on information to date and are assumed to increase as decisions are made and projects completed over the next two years. These increases have not been included. The main assumptions are discussed below. Income levels are anticipated to be lower due to lease agreements within the property schedule and an overall reduction in shipping. This also has an effect on the services charges, wharfage and vessel fees.
The indicative pay award is assumed at 1% and incorporated into 2016/17 budget and continued into future years. The dredging arrangements have been amended to an annual £20,000 budget instead of every three years. This has resulted in an increase service with an annual saving to the harbour of approximately £5,000. The dredging reserve currently has £33,000. At year end the reserve will have a contribution from the revenue account and will be used to fund the dredging activity. The consultants budget has remained, however slightly reduced by 10%. Although the budget was unspent in the current year this is included to cover any additional professional fees that are required for the forthcoming projects. Central Support costs have remained constant from 2014/15 where the budget reduced by 19% from 2013/14. As further reviews and savings take place within the council it is anticipated these may reduce over time. However it depends on the level of service the Whitstable Harbour Board require from each support service. There are currently reviews on all services within the council to establish efficiencies, value for money and overall savings. This will have an effect on the recharges to the harbour and will be closely monitored. It has been assumed that some recharges will reduce in 2016/17 due to the two year fixed post agreed by the board in October 2015. The detail of this impact will be calculated in 2016/17. The depreciation charge reflects the current charge which has been discussed in previous board meetings. Interest on reserves has been reduced to reflect the current interest rates and the amount received on balance sheet reserves. Given the reducing interest rates payable on investments the rate of interest earned by the authority is reducing. The interest payable on reserve balances is 0.5% less than the average rate of investments for the authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.