AGREED, that a working group be formed. 6. The minutes of the working group would be reported to the committee members. 7. The group could look at covering the tennis courts in Memorial Park to increase their usage. 8. The group could also look at moving the museum to the Kings Hall to encourage greater footfall to the hall and improve the museum. 9. In the past two other reports on the feasibility of a marina in Herne Bay had been produced. Both looked at slightly differing locations to the current suggestion and both came to different conclusions. 10. A new report would build on as much of the old reports as possible in order to reduce the costs but there was work for the report to do as the market had changed significantly since the previous reports. 11. The £25,000 request was a top price for the report. Preliminary work by officers should reduce this significantly but until the work was undertaken it was difficult to be more specific. The intention was that the money would be paid for by developer contributions. 12. The report was needed to test the market to see whether it was felt that a marina could be viable. 13. A report would also signal the council’s intentions and help to stimulate interest from potential developers. 14. There were no stopping points for leisure craft between the north Kent cost and Thanet. However, the demand from leisure users had increased. 15. The decision regarding the funding could be deferred until more information about how much it would cost was available. 16. ... view the full minutes text for item 669.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Regeneration Committee - Decomissioned 19/5/22
REGENERATION AND PROPERTY COMMITTEE
17 MARCH 2016
Subject: Progress and future of Herne Bay Regeneration
Director/Head of Service: Caroline Hicks, Head of Business and Regeneration
Decision Issues: These matters are within the authority of the Committee
Classification: This report is open to the public.
CCC Ward(s): Heron
Summary: Update on the regeneration work achieved over the last few years in Herne Bay, current projects and potential future regeneration ideas.
To Resolve: 1) The formation of a Herne Bay Regeneration working group
2) The funding of feasibility work into developing a marina on Herne Bay seafront
Next stage in process
SUPPORTING INFORMATION
1. Introduction
The last few years have seen a great deal of progress on a number of regeneration projects as envisaged in the Herne Bay Area Action Plan 2009, however there is still work to be done and new opportunities to be considered which could help the area to capitalise on growth and investment into the area.
This report aims to give a brief update on positive improvements already completed in the town, projects underway at the moment and what is needed to consider future opportunities.
2. Progress to date
A great number of positive projects have taken place in Herne Bay over the past few years. While not all of these projects have been delivered directly by the Council they all demonstrate that the town offers great potential for investment and growth and is of interest to developers and funders alike. The following is a list of projects which have had a significant effect on the local landscape as well as the local economy.
Significant investment in health and wellbeing facilities with facilities being relocated from the out of date pier sports centre to Herons Leisure Centre and the new Bay Sports Arena in 2011. The demolition of the old sports centre on Herne Bay Pier led to the lease of the now vacant decking being marketed. Herne Bay Pier is now leased to Herne Bay Pier Trust and is home to 32 retail kiosks as well as a number of events and activities. The trust has invested in a number of improvements to the pier including installing new toilets and the new wave canopy which was funded by The People’s Millions. The new units have created accessible space for new retail businesses in the town and the wider programme of activities on the pier has driven footfall along the seafront.
Memorial Park improvements to date include the renovation of the formal seasonal gardens, refurbished seating and gates, new toilet block, new information boards, new interactive playground and the introduction of a kitchen garden.
Herne Bay weekly market moved to Mortimer Street/William Street. While this was in part to facilitate phase 1 of the Central Development Area in King Street Car Park, feedback from visitors and most local businesses shows that this has invigorated the retail offer in the town and improved footfall and business for both market traders and local shops.
Empty business unit rates in the town have remained consistently significantly lower than the national average. In November 2014 – Herne Bay listed as number 31 in top 100 hot retail locations outside Central London by Property Week magazine.
Clocktower refurbishment completed in 2015. Supported by the Heritage Lottery Fund the project also includes a 3 year programme of community engagement work run by the Friends of Herne Bay Clocktower.
Updated lighting scheme on Neptune’s Arm.
New play equipment installed on Herne Bay seafront.
Herne Bay Coastal Park launched with the support of The People’s Millions.
The Seaside Museum in William Street is now operated by Herne Bay Museum Trust, a community group made up entirely of volunteers.
Improvement to a number of seafront properties including The Bun Penny.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Regeneration Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
Election of a Vice-Chair for 2021-22RESOLVED – That Councillor I.Stockley be elected Vice Chair of the Regeneration Committee for the Council Year 2021/22.
The future of Canterbury Boot FairRESOLVED that the council consults on ceasing to run a boot fair using its own staff but offers the opportunity for a...
Reference from the Canterbury ForumThat a report be considered by the council which set out what the alternative sites for the expanded park and ride pr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.