(a) That works are carried out to create a disabled parking bay with a short term mobility vehicle parking area incorporating a recharging point subject to an approximately cost £2,500. (b) That additional works be carried out to lower of a small section of footway kerbing, provision of a removable bollard with fixed timber bollards and an electrical power outlet for a designated concession, subject to an approximate cost of £2,000. Reasons for the decisions: The proposals are considered to be Harbour beneficial, and in accordance with the Strategic Plan and objectives.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Subject: 1. Additional Disabled Parking Bay with mobility vehicle parking and charging point.
2. Designated site for Ice Cream concession.
Director/Head of Service: Larisa Reed
Decision Issues: These matters are within the authority of the Harbour Board.
Classification: This report is open to the public.
CCC Ward(s): Gorrell & Tankerton Wards
Summary: Remove one staff parking bay and provide a fully compliant disabled parking bay adjacent to the Changing Places facility in Harbour St toilets.
Works to include resurfacing of the footway to create an improved access ramp to a short term parking area for mobility vehicles, with an electric recharging point and road line markings.
Carry out additional engineering works to lower a section of kerb, provide fixed and removable bollards and an electrical power outlet for an ice cream concession.
To Recommend/ A) Works are carried out to create a disabled Resolve/Consider: parking bay with a short term mobility vehicle parking area incorporating a recharging point. Estimated cost of works £2500
B) Additional works to lower of a small section of footway kerbing, provision of a removable bollard with fixed timber bollards and an electrical power outlet for a designated concession. Estimated cost £2000
Next stage in process To proceed with the civil and electrical works works subject to Harbour Board approval. SUPPORTING INFORMATION
1. Introduction
The new Changing Places facilities were completed in September 2015 and have been very well received by local charities and the general public. Currently the only disabled parking in the Harbour is on the west side with no parking facilities adjacent to the Harbour St Disabled toilets.
As part of the works to provide a closer parking bay, an opportunity also exists to create a short term parking for mobility vehicles on the pavement in an underutilised recess behind the toilets. It is considered this would generally improve the overall disabled facilities offered within the Harbour Estate and increase the attraction for visitors.
Additionally another underutilised area adjacent to the East Gate entrance has been identified as suitable for a designated concession site, being a pedestrian safe zone. This area is also conveniently situated near to the ‘zebra’ pedestrian crossing point on Harbour St. connecting with the Gorrell Tank Carpark. Concession access would be controlled by fixed timber and lockable bollards.
Through provision of a metered electrical supply, exhaust emissions from the concession vehicle over long periods would be dramatically reduced and contribute to the Harbour’s low carbon planning. Enforcement of non-authorised concessions and parking in the Harbour would be made easier due to the Authority’s provision of a licenced site. 2. Detail
All works are in accordance with the details shown on the Plan. Works would involve realignment of kerbs, resurfacing of the footway to remove the current trip hazards, installation of timber bollards to match the existing, white lining and the installation of the appropriate electrical power outlets.
3. Relevant Council Policy/Strategies/Budgetary Documents
6. Reasons for supporting option recommended, with risk assessment
To improve the facilities offered within the Harbour, its accessibility and attraction.
7. Implications
(a) Financial Implications
Funds are initially taken from Harbour Reserves to complete the project in time for the 2016 summer season. Funds are transferred back once retention sums held by Southern Water are returned from adoption of the drainage system following their final inspection.
All works would then be within the allocated budget for the Changing Places Disabled Toilets
(b) Legal Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci...
Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.