Regeneration Committee - Decomissioned 19/5/22 agreed this item on Thursday 30 June 2016. Below is the council's own wording, with the papers it was decided on.
That the new Canterbury Quality Bus Partnership Agreement was approved by Canterbury City Council subject to the removal of the words ‘for expenditure of funding’ from section 4.11. Reason for the decision: The existing Quality Bus Partnership agreement which has been in place since 2004 has helped the city council, the county council and Stagecoach to improve bus facilities, bus services and the bus fleet with the result that bus patronage has more than doubled over the time period. Signing a new agreement would enable the three parties to continue this programme of ... view the full minutes text for item 126.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Regeneration Committee - Decomissioned 19/5/22
REGENERATION & PROPERTY COMMITTEE
30 JUNE 2016
Subject: Quality Bus Partnership Agreement
Director/Head of Service: Ian Brown, Assistant Director Planning & Regeneration
Decision Issues: These matters are within the authority of the Regeneration and Property Committee(CCC) and the Cabinet Member for Environment and Transport (KCC)
Classification: This report is open to the public.
Wards: All
Summary: The report summarises the partnership, sets out the achievements so far and introduces a new quality bus partnership agreement.
To Resolve: That the new Canterbury Quality Bus Partnership Agreement is approved by Canterbury City Council.
Next stage in process Approval of the new Quality Bus Partnership agreement, subject to the views of the Cabinet Member for Environment and Transport (KCC)
SUPPORTING INFORMATION
1. Introduction
1.1The Quality Bus Partnership (QBP) is a voluntary agreement between Stagecoach, KCC and CCC to invest in improvements to bus routes and bus services across the district. KCC and CCC agreed to provide improvements to infrastructure such as bus lanes, bus priority measures, improved access at bus stops and Stagecoach agreed to commence a programme of investment in new vehicles with lower emissions and low floors for easy access with a target for increasing bus frequencies to and from Canterbury. The aim of the agreement is to make public transport more attractive, to encourage its use to help people travel more easily, to reduce the effects of traffic congestion and pollution and to help Canterbury’s economy.
1.2It was set up in 2004 and in the intervening time the patronage of buses has increased by approximately 10% per year in contrast to a nationally falling trend and buses now make a significant contribution to the district’s transportation policy.
2. Detail
2.1The QBP meets quarterly to discuss local issues and constraints as well as network improvements and targets. Short notes of the particular action points or successes of the partnership are produced and posted on the City Council’s transportation web pages.
2.2Summary for website – August 2015 – January 2016: the partners in the QBP have: Provided an opportunity for Stagecoach to be updated on planning developments, the local plan and related transport strategy to help the group collectively plan for related public transport and infrastructure improvements.
Provided a forum for Stagecoach to update on planned network developments to ensure all partners were aware and assisted with infrastructure where possible to support these. Recent network improvements have included 4 additional buses per hour into St Dunstan’s, 2 of which go via Station Road West and 2 of which go via North Lane; and a revision to the timetable on the 25 route to K and C Hospital to run every 10 minutes through the day.
Stagecoach are looking into possibility of launching a bus users’ group so that views of local residents/passengers can be considered in network planning.
Stagecoach introduced an hourly service provision on Boxing Day (ran a service on the Triangle & Gold service). Patronage and feed- back from this service was good.
Provided a forum to discuss congestion issues and potential solutions.
Upgrades to 7 shelters across the District (CCC) have been undertaken and related kerb works (KCC) to improve the accessibility of the shelters and general appearance.
Commenced a programme of bus stop upgrades across the district. It is envisioned that all stops with concrete poles will be upgraded in 2016/17.
Publicised the Rural Bus Shelter Grant which provides match funding from KCC for new/ upgraded shelters delivered by Parish Councils.
3. New Quality Bus Partnership Agreement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Regeneration Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
Election of a Vice-Chair for 2021-22RESOLVED – That Councillor I.Stockley be elected Vice Chair of the Regeneration Committee for the Council Year 2021/22.
The future of Canterbury Boot FairRESOLVED that the council consults on ceasing to run a boot fair using its own staff but offers the opportunity for a...
Reference from the Canterbury ForumThat a report be considered by the council which set out what the alternative sites for the expanded park and ride pr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.