(a) That the proposal to connect the riverside path between North Lane and Westgate Parks is undertaken as shown on the drawing in Appendix 2 of the report. (b) That the proposal to relocate the bus stop in North Lane and to repave between the bus stop and the Westgate Towers is undertaken as shown on the drawing in Appendix 2 of the report. (c) That officers are given delegated authority to make any minor modifications to the layout that are be required in order to comply with the Section 278 agreement with KCC. For the proposal (9): Councillors A Baker, Eden-Green, Fisher, Fitter-Harding, L Jones, Spooner, I Stockley, J Stockley, I Thomas, and R Thomas Against the proposal (1): Councillor Hirst Abstaining from the proposal: None
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Regeneration Committee - Decomissioned 19/5/22
REGENERATION AND PROPERTY COMMITTEE
26th JANUARY 2017
Subject: Proposed Riverside Path Link : North Lane to Westgate Parks
Director/Head of Service: Ian Brown Assistant Director, Planning & Regeneration
Decision Issues: These matters are within the authority of the Regeneration and Property Committee
Classification: This report is open to the public.
CCC Wards: Westgate
Summary: This report sets out proposals to enhance the riverside path between North Lane and the Westgate Parks which will improve the quality of the visitor experience and help implement the adopted Riverside Strategy.
To Resolve: a) That the proposal to connect the riverside path between North Lane and Westgate Parks is undertaken as shown on the drawing in Appendix 2
b) That the proposal to relocate the bus stop in North Lane and to repave between the bus stop and the Westgate Towers is undertaken as shown on the drawing in Appendix 2
c) That officers are given delegated authority to make any minor modifications to the layout that are be required in order to comply with the Section 278 agreement with KCC
Next stage in process: Works will be carried out, subject to a Section 278 Agreement with KCC.
SUPPORTING INFORMATION
1. Introduction The adopted Riverside Strategy (August 2016) sets out a vision for the riverside that includes providing a “welcoming, connected, accessible network of routes and spaces for everyone to use”. The benefits of this vision are stated as follows:-
To encourage more people to walk and cycle off road thereby reducing traffic congestion and air pollution To encourage people to be more active to improve their health and well-being To provide an opportunity for people to have contact with the natural environment and wildlife To optimise the potential multi-functional benefits of well-designed and managed riverside open space To increase the interest of the city as a destination for visitors and businesses.
The Strategy identifies as ‘Section B’ the riverside path route between Westgate Parks to Barton Mill.
2. Detail
2.1Currently there is a break in connectivity on this section between Westgate Parks and North Lane, adjacent to the Westgate Towers.
At present anyone wishing to walk along the riverside from the Millers Field/St Radigunds area into the Westgate Parks and beyond towards Toddlers Cove, does not have a convenient or direct route. This ‘break’ is indicated on the plan in Appendix 1.
The only realistic safe option is a 150m detour using the pelican crossing in St Peters Place which takes people away from the riverside. Although there is a gap in the flint wall near the Guildhall that some pedestrians use as a shorter route, it cannot be signed or promoted as part of the riverside network as it is not step-free.
2.2Therefore it is proposed to undertake repaving and kerbing works to create a more direct route for pedestrians that will enable the riverside path to be used as a continuous and safe route by all users. The proposed changes are shown on the drawing in Appendix 2.
2.3The works comprise the following main elements :-
New sawn and textured yorkstone paving to replace the different materials in the area e.g. pre-cast concrete slabs, reclaimed yorkstone, granite setts, tarmac. Adjusting the surface levels to provide an even and trip-free pedestrian route Adjusting kerblines to reduce the width of carriageway that pedestrians need to cross – note this adjustment will not prevent any legal vehicle manoeuvres (including the potential for a future bus route through the Towers). Improvements to street lighting
2.4The proposals will also provide the following secondary benefits :-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Regeneration Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
Election of a Vice-Chair for 2021-22RESOLVED – That Councillor I.Stockley be elected Vice Chair of the Regeneration Committee for the Council Year 2021/22.
The future of Canterbury Boot FairRESOLVED that the council consults on ceasing to run a boot fair using its own staff but offers the opportunity for a...
Reference from the Canterbury ForumThat a report be considered by the council which set out what the alternative sites for the expanded park and ride pr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.