That the Harbour Development Officer be given authority to delegate delivery of specific projects to other engineers whilst containing any costs within the budget available for the role. Reason for the decision: To ensure the Board achieve best value for the allocated budget whilst offering greater resilience planning in the delivery of projects. Record of Voting For: B Baker, Clark, Dixey, Fisher, Spooner, Thomas, Todd, Budden, Moore and Steen (10) Against and abstaining: None
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Director/Head of Service: Director of Resources Tricia Marshall
Decision Issues: These matters are within the authority of the Board.
Classification: This report is open to the public.
CCC Ward(s): Gorrell and Tankerton
To Resolve: Councillors are asked to confirm that the Harbour Development Officer be given authority to delegate delivery of specific projects to other engineers whilst containing any costs within the budget available for the role.
Next stage in process: To progress with project work as required.
SUPPORTING INFORMATION
1. Introduction
In October 2015 the Board approved the creation of a two year fixed post of Harbour Development Officer (25 hours per week). The reasons for creating this post were to enable the harbour to maximise development opportunities, increase user satisfaction and to ensure that the Harbour Board is effectively involved in and updated on projects. The postholder has been in place since March 2016 and this report updates the Board how the role has developed.
2. Detail
Since the appointment of the postholder in March 2016, the Board has made considerable progress in identifying and implementing development opportunities at the Harbour. This includes a major review of the Strategic Plan following a series of public consultations which commenced in May 2016.
The Development Officer has identified that, for some of his tasks, it would be possible for the work to be carried out by more junior staff under his supervision. One example would be the implementation of the pontoon at the harbour. By including other members of the Engineering section within the development role would also offer greater resilience planning for the delivery of the projects planned.
The Board’s approval is therefore sought to use some of the funding for the Development Officer to pay for other engineering staff as appropriate where in the view of the Development Officer it would make sense for the task to be carried out by a more junior officer at a lower cost.
The overall budget for the Development Officer would remain unchanged but the volume of engineering work undertaken would increase slightly as staff used would have a lower charge out rate.
The Development Officer would remain responsible for overseeing any project delegated to another officer.
3. Relevant Council Policy/Strategies/Budgetary Documents
None
4. Consultation planned or undertaken
None planned.
5. Options available with reasons for suitability
Option 1 – To continue with the existing arrangement whereby the Development Officer delivers all the work relating to his role. This provides good consistency and continuity but may lead to tasks being carried out by a more expensive resource than is necessary.
Option 2 (recommended) – to allow the Development Officer to delegate delivery of specific tasks to other engineers whilst containing any costs within the budget available for the role. This would potentially allow some work to be carried out at a lower cost. The Development Officer would retain overall responsibility for delivery of projects.
6. Reasons for supporting option recommended, with risk assessment
To ensure the Board achieve best value for the allocated budget whilst offering greater resilience planning in the delivery of projects.
7. Implications
(a) Financial Implications - This proposal would be financially neutral but could allow a higher volume of work to be carried out from within the existing budget.
(b) Legal Implications - None
(c) Equalities - None
8. Conclusions
As set out above, this proposal would potentially allow work to be delegated to more junior staff, allowing more work to be delivered within the available budget, whilst the Development Officer retains overall responsibility for project delivery.
Contact Officer: Tricia Marshall Job Title Director of Resources Telephone: 01227 862328
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci...
Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.