that the committee accept the results of the audit work. A record of the voting on the proposal was taken as follows: For the proposal: Councillors S Cook, Eden-Green, Glover, I Stockley, R Thomas, Walker and Warley (7). Against/abstaining from the proposal (0).
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Subject: EAST KENT AUDIT PARTNERSHIP UPDATE REPORT
Director/Head of Service: Deputy Chief Executive
Decision Issues: This matter is within the authority of the Audit Committee
Classification: This report is open to the public.
CCC Ward(s): All
Summary: This report informs members of progress against the audit plan approved by Audit Committee in March 2017.
To Resolve: That this committee accept the results of audit work and make comments, if required to Full Council.
Next stage in process To receive the results of internal audit work and to make comments as considered appropriate.
SUPPORTING INFORMATION
1. Introduction
Issues for consideration The Committee is asked to agree the options set out below because: In order to comply with best practice, the Audit Committee should independently contribute to the overall process for ensuring that an effective internal control environment is maintained. This report includes the summary of the work of the East Kent Audit Partnership since the last Audit Committee meeting.
2. Detail
2.1AUDIT REPORTING For each Audit review, management has agreed a report, and where appropriate, an Action Plan detailing proposed actions and implementation dates relating to each recommendation. Reports continue to be issued in full to the relevant Directors, as well as an appropriate manager for the service reviewed.
Follow-up reviews are performed at an appropriate time, according to the status of the recommendation, timescales for implementation of any agreed actions and the risk to the Council.
An Assurance Statement is given to each area reviewed. The assurance statements are linked to the potential level of risk, as currently portrayed in the Council’s risk assessment process. The assurance rating given may be Substantial, Reasonable, Limited or No assurance. Those services with either Limited or No Assurance are monitored, and brought back to Committee until a subsequent review shows sufficient improvement has been made to raise the level of assurance to either Reasonable or Substantial. A list of those services currently with such levels of assurance is attached as Appendix 2 to the EKAP report.
Part of the remit of the Council’s Audit Committee is to provide independent assurance of the adequacy of the risk management framework and the associated control environment, independent review of the Authority’s financial and non- financial performance to the extent that it affects the Authority’s exposure to risk and weakens the control environment, and to oversee the financial reporting process.
To assist the Committee meet its terms of reference with regard to the internal control environment an update report is regularly produced on the work of internal audit. The purpose of this report is to detail the summary findings of completed audit reports and follow-up reviews since the report submitted to the last meeting of this Committee.
2.2SUMMARY OF WORK There have been two Internal Audit reports completed for the period. These have been allocated assurance levels ranging from reasonable to limited; one was reasonable and one was limited assurance. Summaries of the report findings are detailed within Annex 1 to this report.
In addition, two follow up reviews have been completed during the period. It is usual to find when the follow up review is undertaken, that the vast majority of recommendations that were agreed by management have been implemented and that management are actively strengthening the internal control environment.
Performance figures for the East Kent Audit Partnership for 2017-18 show performance against target.
3. Relevant Council Policy/Strategies/Budgetary Documents
None
4. Consultation planned or undertaken
Management Team has considered this report.
5. Options available with reasons for suitability
To consider the results of audit work and to make such observations and recommendations to the Council as the committee sees fit.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the press and publicRESOLVED - That under Section 100(A)(4) of the Local Government Act 1972, the press and public be excluded from the m...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.