The Council does not defer any further action on the Canterbury west multi storey car park, that a conceptual diagram of the Canterbury West Station area as an integrated transport hub be produced and made available to Councillors, and that work continue with stakeholders and partners to realise this. Reason for the decision: The car park did not work against the integrated transport hub and instead offered more opportunities for it to be improved.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Regeneration Committee - Decomissioned 19/5/22
REGENERATION AND PROPERTY COMMITTEE 27TH SEPTEMBER 2018
Subject: Canterbury West Station : Integrated Transport Hub
Director Ian Brown, Director of Development
Decision Issues: These matters are within the authority of the Regeneration and Property Committee
Classification: This report is open to the public
CCC Ward(s): Westgate
Summary: The report responds to a question raised at the Canterbury Area Member Panel on 11th June 2018 and includes the recommendation made by the Canterbury Forum 10 September 2018.
To Note: The report setting out the proposals for an Integrated Transport Hub at Station Road West.
Next stage in process: The committee will be kept updated on any developments as and when they progress. The recommendation from the Canterbury Forum will be referred to the Policy and Resources Committee.
SUPPORTING INFORMATION
1.0Introduction
1.1At the Canterbury Area Member Panel meeting on 11th June, the panel asked that a report be prepared outlining what is being undertaken to achieve a fully integrated transport hub at the Canterbury West railway station and what opportunities there are in this regard.
2.0Detail
2.1In 2013, Canterbury City Council and Network Rail carried out improvement works to the forecourt with the objective of creating an integrated transport hub and quality ‘gateway’ into the city. (Exec minute 220 3/03/11).
The works included the following main aspects :-
A 10m wide pedestrian concourse outside the station building with seating and trees A direct raised pedestrian route from the station entrance to a new bus stop installed on Station Road West 6 passenger drop off bays Taxi bays increased from 6 to 8.
2.2The £500k investment completely transformed the station forecourt and enabled all transport modes (train, bus, taxi, car, cycle) to be accommodated creating an integrated transport hub at the station as shown on the plan below.
An integrated transport hub is defined as a place where multi-modal interchange occurs between different forms of public transport i.e. train and bus.
It is also worth comparing before and after photos to appreciate the positive impact these improvements had both in appearance, as well as for transport integration. 2.3 The proposed multi-storey car park will build on these improvements by not only providing an additional 250 parking spaces but the project will also include a minimum of 16 additional cycle racks in a secure enclosure, cycle hire docking stations, and will create a 6.0m wide footway all the way from the station to St Dunstans Street. The car park will also include electric charging points.
2.4It is important to plan for future rail passenger increases and to investigate ways to improve transport integration (this is an action in the Transport Strategy) and we know that Network Rail is forecasting a three percent annual increase in use of the station. One potential option that is being explored is for Network Rail to lease parking spaces on the upper deck of the proposed multi-storey car park for their season ticket holders. This would enable their small surface car park to be more effectively used for other purposes such as: increased taxi provision, additional cycle storage, bus improvements as well as enhanced passenger/ticketing facilities.
The new car park will therefore provide the opportunity to further enhance the effectiveness of this transport hub and further integrate transport options.
Stagecoach currently only runs one service direct to the station and the council intends to set a priority action for them, through the Quality Bus Partnership, to ‘Investigate better bus links to Canterbury West Station and through ticketing”.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Regeneration Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
Election of a Vice-Chair for 2021-22RESOLVED – That Councillor I.Stockley be elected Vice Chair of the Regeneration Committee for the Council Year 2021/22.
The future of Canterbury Boot FairRESOLVED that the council consults on ceasing to run a boot fair using its own staff but offers the opportunity for a...
Reference from the Canterbury ForumThat a report be considered by the council which set out what the alternative sites for the expanded park and ride pr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.