Application No.CA/24/00224/OUT Land at Bodkin Farm, Thanet Way, HB

Agreed Planning 3 papers

AI summaryCanterbury Planning Committee approves outline application for up to 300 homes, a secondary school and care home at Bodkin Farm, Thanet Way, subject to a legal agreement and conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedVote: 5 for, 0 against, 3 abstentions
MoneyNot specified in reportS.106 contributions to be secured via legal agreement
What happens nextHead of Planning to grant permissionSubject to section 106 agreement and safeguarding conditions
Who it affectsNot stated

What was decided

The Planning Committee agreed to grant outline planning permission for a mixed use development at Bodkin Farm, subject to a section 106 legal agreement and safeguarding conditions. Report P56

The decision was taken by 5 votes in favour, 0 against and 3 abstentions, following a deferral in April 2026. Report P7

Conditions were updated to cover sewerage phasing, retained trees, accessible and overlooked play areas, and future-proofing for a bus route. Report P47, P68, P110

Why

The Council cannot demonstrate a 5-year housing supply, triggering the tilted balance in favour of the development under the National Planning Policy Framework. Report P2, P3, P17, P53

The site is allocated for housing in the draft Local Plan, supported by 7 years of evidence, including assessments of the loss of the Green Gap balanced against housing and school need. Report P5, P19, P20

There is a clear need for affordable and older persons' housing and a secondary school for the coastal communities; the applicant will transfer land to the Education Authority for the school. Report P1, P14, P24, P25, P54

What happens next

The Head of Planning is authorised to grant permission once the section 106 legal agreement is completed to secure developer contributions, including a 40mph speed limit on the A2990 Thanet Way and play area delivery. Report P26, P27, P37, P46, P143, P144

Southern Water is required to deliver sewerage network upgrades within 2 years of any grant, with a condition phasing occupation of new homes to align with the upgrades. Report P31, P32, P110

Reserved matters applications for access, layout, scale, appearance and landscaping must be submitted within 3 years, with development to begin within 2 years of the last reserved matters approval. Report P59, P61

Options considered

  • Chosen: Grant outline planning permission subject to a section 106 agreement and safeguarding conditions (officer recommendation). Tilted balance applies due to lack of 5-year housing supply; site allocated in draft Local Plan; clear need for housing and a secondary school outweigh Green Gap and other concerns Report P2, P3, P17, P20, P53, P54, P55, P56
  • Rejected: Refuse the application. Not explicitly addressed as an option, but the previous application was refused 10 years ago under a different planning context Report P18, P20

Implications

  • Legal: Section 106 legal agreement required to secure developer contributions, including land transfer for the secondary school (held available for 20 years), community infrastructure contributions, and a scheme to reduce the A2990 Thanet Way speed limit to 40mph. Report P27, P37, P46, P144
  • Financial: Developer will fund sewerage network upgrades via Southern Water; the Education Authority will collect developer contributions from a range of sites to pay for the school construction. Report P25, P31
  • Equalities: 20% of new homes must meet Building Regulations M4(2) accessibility and adaptable dwellings standard; care home and older persons' housing included. Report P1, P118
  • Climate: Reserved matters must demonstrate sustainability and energy measures from the Turley Sustainability and Energy Statement; surface water drainage must accommodate the climate change-adjusted 100-year storm. Report P98, P104, P106
  • Risk: Phase 1 of development will be delivered before the secondary school at Thornden Wood Close; occupation of homes must be phased to align with Southern Water sewerage upgrades to avoid flooding. Report P26, P32, P110

Who and where

  • Future residents of up to 300 new dwellings, including affordable and older persons' housing Report P1, P14
  • Kent County Council as Education Authority, which will receive land for a secondary school with sixth form and indoor and outdoor sports Report P24, P25, P26
  • Pedestrians, cyclists and road users on the A2990 Thanet Way, where the speed limit will be reduced to 40mph Report P37, P144
  • Residents of Herne Bay and the wider district needing a new secondary school to serve coastal communities Report P54
  • Future users of the local centre (up to 500m2 of Class E retail), two LEAP/NEAP play areas, a MUGA, and open space Report P68, P137, P143

Timeline

  • 28th April 2026: Planning Committee previously resolved to defer the application for further information Report P7
  • 21st July 2026: Planning Committee agreed to grant outline planning permission subject to a section 106 agreement and conditions
  • Within 3 years of the date of the outline permission: First reserved matters application must be made to the local planning authority Report P59
  • Within 5 years of the outline permission: All subsequent reserved matters applications must be made Report P59
  • Within 2 years of approval of the last reserved matters: Development must commence Report P61
  • Within 2 years of any grant of planning permission: Southern Water is required to deliver necessary sewerage network upgrades Report P31
  • Prior to the 50th occupation: At least one play area must be open to the public Report P137
  • Prior to the 200th occupation: The local centre must be delivered and operational Report P143
  • Prior to the 250th occupation: All play areas must be open to the public and kept open thereafter Report P138

Plain English for the jargon

  • Outline planning permission: A planning approval that establishes the principle of a development, with details (called 'reserved matters') submitted and approved later.
  • Tilted balance: A planning test under the NPPF that presumes permission should be granted for sustainable development where a council cannot demonstrate a 5-year housing supply, unless harms significantly outweigh benefits.
  • Section 106 agreement: A legal agreement between a developer and the local authority, used to secure planning obligations such as affordable housing, infrastructure contributions or land transfers.
  • Reserved matters: Details of a development (such as layout, scale, appearance, landscaping or access) that are not decided at outline stage but submitted for later approval.
  • MUGA: Multi-Use Games Area, an outdoor sports surface designed for multiple activities.
  • LEAP / NEAP: Local Equipped Area for Play / Neighbourhood Equipped Area for Play, designed play spaces for different age groups.
  • TRO (Traffic Regulation Order): A legal order made by a highway authority to regulate traffic, for example to set speed limits.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item221

Resolved

AGREED. A record of the vote was taken as follows: For the proposal (5): Councillors Edwards, McKenzie, Prentice, I Stockley and Thomas Against the proposal (0): Abstained from voting (3): Councillors Buckman, Dixey and D Smith
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Planning Committee

Background

1. This planning application was reported to the Planning Committee in April 2026. That report set out the evidence-base that demonstrates the need for housing (including affordable and older persons' housing) and a secondary school in the district.

2. The Council cannot demonstrate a 5-year supply of housing nor is it delivering enough housing to meet local housing needs, as identified in the adopted Local Plan.

3. The legal effect of this is that when planning applications for housing are being considered, there is a ‘tilted balance’ in favour of the development. This means that planning applications that will help to make up the shortfall in housing supply and lack of delivery should be given significant weight in the decision-making process.

4. In the previous report, the planning committee was advised of this and recommended that planning permission be granted.

5. The site is included within the draft Local Plan as a strategic housing allocation to meet the overall housing need for the district to 2043. The inclusion of the site in the draft Plan was based upon thorough assessments of its sustainability. The draft Local Plan will shortly be submitted to the Secretary of State for public examination and therefore now has some weight in the planning decision-making process.

Introduction

6. At its meeting on 28th April 2026, the planning committee resolved to defer this application for the Head of Planning for further information to be obtained from the applicant on the following points:

(a) How the Green Gap policy in the 2017 Local Plan had been assessed in the tilted balance compared with the previous application that had been refused.

(b) To gain greater clarity and certainty from Southern Water about wastewater disposal arrangements.

(c) Agreeing with KCC that the speed limit of the Thanet Way in the site's vicinity needed to be reduced below a 50-mile-an-hour limit.

(d) How the play areas will be integrated throughout the site, ensuring they were suitable for children's and young people’s safety.

(e) The possibility of introducing a bus route in and out of the development site.

7. I have received comments from the applicant on the matters raised by the Committee, and I have also contacted Southern Water Services and KCC Highways for further clarification about the infrastructure issues that the planning committee has queried. I also engaged with South-East Water, given the recent incidents locally with the water supply.

Update and appraisal of matters raised by the planning committee on 28th April 2026

8. The following is an appraisal of each of the matters raised by the planning committee, taking account of the further information provided by the applicant and the consultees.

How the Green Gap policy in the 2017 Local Plan was assessed in the tilted balance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Application No.CA/24/00224/OUT Land at Bodkin Farm, Thanet Way, HBPlan 418 KB Download
PDF
CA/24/00224/OUT: Land at Bodkin Farm, Thanet Way, HB: REPORTReport 274 KB DownloadRead as text
PDF
CA/24/00224/OUT: Land at Bodkin Farm, Thanet Way, HB: SITE PLANPlan 5.7 MB Download

At this meeting

Whole meeting

Who was there

8 of 14 attended
PP
Paul PrenticeChair, present
KB
Keith BothwellCommittee Member, apologies
DB
Dane BuckmanCommittee Member, present
MD
Michael DixeyCommittee Member, present
PE
Pat EdwardsCommittee Member, present
HM
Harry McKenzieCommittee Member, present
DS
Dan SmithVice Chair, present
IS
Ian StockleyCommittee Member, present
DT
David ThomasCommittee Member, present
ST
Simon ThomasOfficer, in attendance
CW
Cath WallenOfficer, in attendance
AJ
Andrea JamesOfficer, expected

All 14 on the meeting page

On this subject at Canterbury

Search all
  1. Application No.CA/24/00224/OUT Land at Bodkin Farm, Thanet Way, HBThis decision
  2. Application No. CA/24/01903/FUL North of Bullockstone Road / Canterbury Road Roundabout, Sth of Thanet Way, Herne BayAgreed
  3. Application No. CA//19/00276/FUL - 3 South Street, Whitstable, CT5 3DRAgreed
  4. Application No. CA//15/00844/OUT Land at Herne Bay Golf Course, Thanet Way A2990, Herne, CT6 7PGAgreed
  5. Application No. CA//18/01280/OUT Land at Ladesfield, Vulcan Close, Whitstable, CT5 4LZAgreed
  6. Application No. CA//17/00519/OUT Land at and adjacent to Cockering Farm, Thanington WithoutAgreed

More from Canterbury Planning Committee

All decisions
MeetingDecisionOutcome
6 Jan 2026 Application No. CA/25/00208/FUL Land S of Ridgeway, WhitstableAGREED. A record of the vote was as follows: For the proposal (8): Councillors Dixey, Edwards, Jones, McKenzie, Melli... Agreed Open
6 Jan 2026 Application No. CA/25/01822/FUL 97 Clare Road, WhitstableAGREED. A record of the vote was as follows: For the proposal (8): Councillors Dixey, Edwards, McKenzie, Mellish, Pre... Agreed Open
9 Dec 2025 Application No. CA/24/02263/FUL Land at junction with May Street, Sweechbridge Road, HBAGREED. A record of the vote was as follows: For the proposal (6): Councillors Dixey, Edwards, Jones, Prentice, Stock... Agreed Open
11 Nov 2025 Exclusion of the press and publicRESOLVED that under Section 100(A)(4) of the Local Government Act 1972, the press and public be excluded from the mee... Decided Open
14 Oct 2025 Exclusion of the press and publicRESOLVED that under Section 100(A)(4) of the Local Government Act 1972, the press and public be excluded from the mee... Decided Open