RESOLVED TO RECOMMEND TO COUNCIL 1. To progress a Community Infrastructure Levy (CIL) for Carmarthenshire. 2. To authorise the production of a Preliminary Draft Charging Schedule, which will identify the amount of CIL sought from each qualifying development, and to conduct a formal consultation on its content along with the associated evidence base.
Word for word from the decision Carmarthenshire published for this meeting.Source: democracy.carmarthenshire.gov.wales
EXECUTIVE BOARD 30TH NOVEMBER 2015 COMMUNITY INFRASTRUCTURE LEVY (CIL)
RECOMMENDATIONS / KEY DECISIONS REQUIRED: This report seeks approval to progress a Community Infrastructure Levy (CIL) for Carmarthenshire. To authorise the production of a Preliminary Draft Charging Schedule, which will identify the amount of CIL sought from each qualifying development, and to conduct a formal consultation on its content along with the associated evidence base.
REASONS: Legislation has effectively scaled back the scope of Section 106 legal agreements. If the Council does not implement a CIL it will potentially lose out on contributions from developers to fund vital infrastructure, required to implement the Local Development Plan allocations. A decision is required to progress the Carmarthenshire CIL and to authorise a public consultation on the Preliminary Draft Charging Schedule. To ensure that the development set out in the Local Development Plan is brought forward with appropriate infrastructure.
Relevant scrutiny committee to be consulted: Yes, reported on 9th November 2015.
Exec Board Decision Required YES Council Decision Required YES
Directorate: Designations: Tel Nos. / Email addresses: Environment Department
Name of Head of Service: 01267 228918 Llinos Quelch Head of Planning [email protected]
Report Author: 01267 228846 Ian R Llewelyn Forward Planning Manager [email protected] EXECUTIVE SUMMARY EXECUTIVE BOARD 30TH NOVEMBER2015 COMMUNITY INFRASTRUCTURE LEVY (CIL) On the 11th May 2015 the Executive Board resolved to commence work on gathering evidence on the suitability of adopting a CIL Charging Schedule in Carmarthenshire. It was agreed that the Executive Board would receive a further report before commencing work on the Preliminary Draft Charging Schedule.
In order to consider the suitability of introducing a CIL in Carmarthenshire it was essential to firstly conduct a viability exercise to establish the economic viability of charging CIL throughout the County. In addition to this, further work will need to be done to gain a full understanding of Carmarthenshire’s future infrastructure needs and estimated cost of delivering this infrastructure.
It should be noted for clarity that the introduction of a CIL charge is not a mandatory requirement for local authorities and is not intended to replace planning obligations such as Section 106 agreements or Section 38/278 agreements for highway works. In this respect planning obligations will continue to operate irrespective of the adoption of a CIL charge. However, the scope and ability to collect planning obligations have been scaled back and curtailed as a result of the CIL Regulations 2010.
Infrastructure Requirements
The Infrastructure Background Paper was prepared as evidence to support the Local Development Plan. This document describes some aspects of the infrastructure required to support and sustain the planned level of growth in Carmarthenshire up to 2021. It provides a starting point to build a comprehensive picture of the future infrastructure requirements and costs across Carmarthenshire. There are a number of infrastructure types and services which are considered to be potentially suitable for funding through CIL, these broadly fall within the following infrastructure types: Transport and Highways Schools Leisure and Cultural facilities Health facilities Welsh Language Waste facilities The Environment Water, Flooding and Drainage Utilities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.