RESOLVED 10.1 that the Solar Photovoltaic (PV) Project be funded as part of the capital programme; 10.2 that Councillor D.M. Jenkins, Executive Board Member for Resources, be appointed to sit on the Board of the Community Benefit Society, Egni Sir G â r .
Word for word from the decision Carmarthenshire published for this meeting.Source: democracy.carmarthenshire.gov.wales
On 11th May 2015, Executive Board accepted the tender submitted by British Gas and Generation Community Ventures (GCV) for a solar PV community rent-a-roof programme.
GCV is a social enterprise funded by charitable foundations, which has partnered with British Gas Solar and Social Finance to deliver large scale community energy projects for local authorities and housing associations.
Under this proposed programme, solar PV systems were to be installed on the roofs of all suitable properties in the Council’s housing stock and non-domestic property portfolio. The programme was initially estimated to have an approximate capacity of 10 MW at a capital cost of £10-15m.
Whilst the programme was fully financed and could be delivered at no cost to the Council, there were options for mutual ownership via a public share offer plus an opportunity for the Council to directly invest. An attraction of this innovative scheme was that some of the income arising from the receipt of Feed In Tariff (FIT) and Export Tariff payments would be made available to establish a community fund.
A new community benefit society named ‘Egni Sir Gar Cyfyngedig’ was established in August 2015 as the operating vehicle to own and install the systems, and be responsible for maintaining them.
Matters were progressing well until the Government announced a consultation on 27th August 2015 that proposed significant cuts to the FIT rates payable to solar PV installations. The Government proposal was to cut the domestic FIT by some 87% effective from 1st January 2016, with similar cuts also proposed for larger systems up to 5 MW.
Based on the severity of these proposed cuts, coupled to the imminent implementation date, it was announced at the meeting of Council on 9th September 2015 to suspend the development of an installation programme for domestic properties and to instead concentrate on maximising the programme for solar PV on the Council’s non-domestic property portfolio. Accordingly, applications were submitted to Ofgem to pre-register as many properties as possible in order to secure the current FIT rates, which would be payable for installations completed within the next 12 months (this route was only available to community energy schemes / schools and excluded domestic properties). Unfortunately, the Government, at very short notice, closed this pre-registration route. It is understood that Ofgem received a more than 1,000 pre-registration applications, 95 of these being submitted by Egni Sir Gar Cyfyngedig for various Carmarthenshire County Council properties (mainly schools). Under this scheme, individual installations were effectively capped at 50 kWp and must be completed before the end of August 2016 to receive the secured FIT rates.
Note: The Government announced the outcome of its FIT consultation in December 2015. This th reduced the severity of the proposed cuts from 80+% to 60+% effective from 15 January 2016 th (payable from 8 February 2016). These revised FIT rates still make the Council’s originally proposed programme financially unviable.
Current Position
Discussions are currently on-going with Western Power Distribution (WPD) regarding connecting the 95 properties pre-registered with Ofgem to the grid. Unfortunately, there are significant constraints on the local grid which require major reinforcement works. Whilst some of this work forms part of WPD’s planned work programme over the next few years, the cost of some of the less major reinforcement would be payable by potential developers. In order to ensure the programme is financially viable, only properties where there are no costs for grid reinforcement works are viable. As a consequence, WPD has to-date only given consent for some 30 properties to be connected at the grid with most of these at a reduced capacity compared to that pre-registered with Ofgem. The total potential capacity of the programme is currently some 1.2MW.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.