Resolved
RESOLVED that the Five Year Capital Programme 2017/18 – 2021/22 be endorsed.
Policy & Resources Scrutiny Committee decided this item on Wednesday 11 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Five Year Capital Programme 2017/18 – 2021/22 be endorsed.
POLICY & RESOURCES SCRUTINY COMMITTEE 11/01/17
FIVE YEAR CAPITAL PROGRAMME – 2017/18 - 2021/22
To consider and comment on the following issues: As part of the budget consultation, members are asked to examine the attached capital programme and in particular consider the projects relating to the Policy & Resources Scrutiny Committee’s service areas.
REASONS: To undertake consultation with the Policy & Resources Scrutiny Committee on the five year Capital Programme for 2017/18 to 2021/22.
To be referred to the Executive Board for decision: Yes
EXECUTIVE BOARD MEMBER PORTFOLIO HOLDER:- Cllr. David Jenkins (Resources)
Directorate: Corporate Services Tel No. 01267 224160 Report Author: Designation: E Mail Address: Chris Moore Director of Corporate Services [email removed] .uk EXECUTIVE SUMMARY POLICY & RESOURCES SCRUTINY COMMITTEE 11/01/17
FIVE YEAR CAPITAL PROGRAMME – 2017/18 - 2021/22
The report provides members with an initial view of the 5 year Capital Programme from 2017/18 to 2021/22.
The report will form the basis of the budget consultation process with members and other relevant parties. Feedback from this consultation process along with the outcome of the final settlement will inform the final budget report which will be presented to members in February 2017.
DETAILED REPORT ATTACHED ? YES
IMPLICATIONS I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report : Signed: C. Moore Director of Corporate Services
Policy, Crime Legal Finance ICT Risk Staffing Physical & Disorder Management Implications Assets and Issues Equalities
NONE NONE YES NONE NONE NONE YES Finance The updated Capital Programme is projected to be funded for the first 4 years from 2017/18 to 2020/21. There is currently a shortfall of £3.123m in 2021/22 which will be reviewed before the final budget report is approved by County Council. The programme includes potential grant funding sources that are yet to be confirmed and as the programme develops these proposals may need to be revisited if anticipated funding is not forthcoming.
Physical Assets New assets created from the Capital Programme will be added to the Council’s portfolio. In addition the Programme proposes expenditure to improve the existing assets and comply with statutory responsibilities CONSULTATIONS
I confirm that the appropriate consultations have taken in place and the outcomes are as detailed below Signed: Chris Moore Director of Corporate Services
1. Scrutiny Committee - Relevant Scrutiny Committees will be consulted. 2.Local Member(s) - N/A 3.Community / Town Council - N/A 4. Relevant Partners - Consultation with relevant partners will be undertaken and results will be reported during the budget process. 5. Staff Side Representatives and other Organisations - Consultation with other organisations will be undertaken and results will be reported during the budget process. Section 100D Local Government Act, 1972 – Access to Information List of Background Papers used in the preparation of this report: These are detailed below
Title of Document File Ref No. Locations that the papers are available for public inspection
2016-21 Capital Corporate Services Dept, County Hall, Carmarthen Programme 2017-22 Capital Corporate Services Dept, County Hall, Carmarthen Programme
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
APPENDIXAppendix | 48 KB | Download |
PDF |
FIVE YEAR CAPITAL PROGRAMME: 2017/18: 2021/22Report | 135 KB | DownloadRead as text |
PDF |
REPORTReport | 85 KB | Download |
Follow Policy & Resources Scrutiny Committee at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2022 | Revenue & capital budget monitoring report 2021/22RESOLVED to receive the report. | Decided | Open |
| 16 Mar 2022 | Environment departmental business plan 2022/23RESOLVED to note the Plan. | Noted | Open |
| 16 Mar 2022 | Domestic abuse, domestic violence & sexual violence policyRESOLVED that the proposed Domestic Abuse, Domestic Violence & Sexual Violence Policy be endorsed. | Decided | Open |
| 16 Mar 2022 | Tic programme position statementRESOLVED that the report be received. | Decided | Open |
| 16 Mar 2022 | Carmarthenshire public services board (psb) minutes - november 2021RESOLVED that the minutes of the PSB meeting held on the 24 th November, 2021 be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.