Resolved
RESOLVED, that the future maintenance programme for Burry Port Harbour and funding proposals be approved.
Cabinet approved this item on Monday 6 February 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, that the future maintenance programme for Burry Port Harbour and funding proposals be approved.
Managing the harbour is becoming increasingly difficult without a major dredge, with mooring fees having to be frozen, and the window of opportunity for berth holders to access and egress the harbour being reduced each year. This in turn reduces the harbour’s appeal to boat owners and is resulting in a loss of potential income, as well as attracting adverse publicity. Approximately 6,000m3-10,000m3 of sand and silt enters the harbour every year, with around 80,000m3 of material (mainly silt) needing to be removed as part of the immediate capital dredge. The Harbour walls are also in a poor condition, meaning that East Dock is no longer used.
The income currently generated by the harbour covers most of its current revenue costs including the annual sand dredge of the approach channel. The Outer Harbour has a capacity for 330 berths, with 137 occupied and over half of the remaining 193 not serviceable due to the siltation problems. A further 104 berths in East Dock are out of commission due to the issues with the Harbour walls. 10 additional vessels are moored in West Dock where there are no pontoons. For every additional 50 boats mooring at an average of £750 pa (£125/m x 6m boat), this generates an extra £37.5K of income pa at current prices.
If the planned regeneration of the harbour area is undertaken, complete with 250+ new harbour side homes and many extra facilities, there is every chance the take-up of pontoon berths and thus income, will increase substantially in a well maintained harbour, making the facility more sustainable. With full occupation of East Dock and the outer Harbour, the facility could generate an additional £223k of income pa for the authority at current charging rates. Charging rates have been kept purposely low over recent years, due to the access / egress issue associated with the limited dredging regime.
2. Costs and funding
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 232 KB | Download |
PDF |
BURRY PORT HARBOUR: FUTURE MAINTENANCEReport | 206 KB | DownloadRead as text |
PDF |
Masterplan with HarbourReport | 1 pages | Download |
PDF |
Proposed PlanReport | 255 KB | Download |
PDF |
ReportReport | 594 KB | Download |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.