CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Carmarthenshire County Council
ERW Joint Committee (replaced by Y Partneriaeth), Wednesday 21 March 2018 at 10.30am

RISK REGISTER.

Agreed Committee 2 papers

ERW Joint Committee (replaced by Y Partneriaeth) agreed this item on Wednesday 21 March 2018. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

AGREED that the risk register be received and approved with the exception of the central element. This is to be reviewed by the six Directors and resubmitted at the next Joint Committee .
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to ERW Joint Committee (replaced by Y Partneriaeth)

Managing a risk register should be seen as a supportive and helpful way of recording issues and the support required to get the actions in place to mitigate the risk. In a partnership, the process of escalating and sharing each others risks are complex.

Risk register format has matured in recent months and has been agreed by Joint Committee (June 2015) as fit for purpose. Joint Committee agreed that under leadership of Karen Jones (NPT, Head of Corporate Development) that we should further mature process ready for new financial year.

Key Actions:

* Identify Hub and LA owner where necessary. * Collation of LA/Hub risks can be collated for Hub QA, reducing duplication. * Review risk profile after mitigation and actions. * Discuss lessons learnt as part of review process. * Include review at Executive and Joint Committee. * Prioritise risks and order levels of risks. * Link to self evaluations.

Below is the Risk Matrix:- ERW Risk Register January 2018

Central Inherent Risk

Following Mitigation Risk Transfer detail Escalation from LA detail Date appear on ERW Date taken off ERW Nature / Description of Risk Risk Owner Probability Impact Risk Score Treatment Actions to Mitigate Risk Additional Detail LA / Hub Reference (if necessary and date) (if necessary and date) Register Register

Probability Impact Risk Score

Robust self evaluation and monitoring at LA Estyn visits result in LAs being level, with regional strategies to support. placed in follow up / special Transfer to 3rd Party 1 Chief Education Officers Likely High 9 Place on Pembrokeshire Risk Register Email sent Pembrokeshire N/A Likely High 9 March 2015 measures or requiring further / LA Pembrokeshire support network established attention by ERW by mutual consent. Review of evidence work reaims of concern.

Alternative support lead ChAd for schools causing concern required in LA. all alliance members tke ownership on detaila and accountability. Effective BP in place. Risk for all LAs but specifically Pembrokeshire, Inspection of Region or any single Managing Director and 6 where pace of improvement has not been good 2 LA finds less than adequate Likely High 9 Treat and Mitigate Clear plan for improvement as part of All All N/A likely Medium 6 March 2015 Directors enough and high proprtion of secondaries causing standards, provision or leadership improvement planning, but heightned urgency concern. pre inspection. Taken swift effective action against recommendations of Estyn review. Good track record of impact on outcomes. Quality systems secure. Infrastructure clear.

Review leads to need to reaffirm from all LAs the Effective planning Central Team capacity to commitment as set out in legal agreement. Joint coordinate and facilitate change. position committee paper on comparing regions is likely to remains same and is critical Insufficient capacity of Central raise issue and further action is likley. Central Team and Challenge Adviser Team Directors and Managing team capacity discussion with LD 14/10/16. 3 Likely High 9 Treat and Mitigate Discuss with all Directors 24/07/15. All agreed N/A all N/A Likely High 9 March 2015 to deliver Business Plan to high Director Critical 11/12/17, following reports to JC capacity and restructure of Central Team. standard SEptember 2017 - both ChAd and central team Improved planning and training on key capacity matters have not been tackled, and now workload issues. Challenege adviser capacity are increasingly having an impact on the support agreed to maintain at full Sept 2015 given to schools.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REPORTReport 551 KB DownloadRead as text
PDF
RISK REGISTER.Report 120 KB Download

At this meeting

Whole meeting

Who was there

1 of 7 attended
EA
Cllr. Ellen ap Gwynn Ceredigion County CouncilCommittee Member, present
ED
Cllr. Emlyn Dole Carmarthenshire County CouncilCommittee Member, expected
RH
Cllr. Rosemarie Harris Powys County CouncilCommittee Member, expected
RJ
Cllr Rob Jones Neath Port Talbot County Borough CouncilCommittee Member, expected
DP
David PowellOfficer Exempt Access, expected
DS
Cllr. David Simpson Pembrokeshire County CouncilCommittee Member, expected
RS
Cllr. Rob Stewart City and County of SwanseaCommittee Member, expected

On this subject at Carmarthenshire

Search all
  1. RISK REGISTER.This decision
  2. Risk registerAgreed
  3. Risk register and risk policy reviewApproved
  4. Risk registerNoted
  5. Risk registerAgreed
  6. Risk registerNoted

More from Carmarthenshire ERW Joint Committee (replaced by Y Partneriaeth)

All decisions
MeetingDecisionOutcome
17 May 2023 Appointment of chair and vice-chairResolved that the following members will be elected : - 3.1 Councillor Darren Price be appointed as Chair of the ERW ... Decided Open
17 May 2023 Audit wales 2022 audit plan education through regional working joint committeeRESOLVED that the Audit Wales 2022 Audit Plan, as contained within the report, be approved. Approved Open
17 May 2023 Erw statement of accounts for 2021-22 and distribution of erw reserves and balancesResolved by a majority decision (with Powys dissenting) that: 8.3 the distribution of the ERW reserves and balances, ... Approved Open
17 May 2023 Erw joint committee agreement - deed of variationRESOLVED tha t : - 9.1 the draft Deed of Variation, attached to the report, be approved in principle 9.2 the intentio... Approved Open
29 Apr 2022 To sign as a correct record the minutes of the meeting of the joint committee held on the 8th july 2021RESOLVED that the minutes of the ERW Joint Committee meeting held on 8 th July, 2021 be signed as a correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies