Decision Making and Determination Process following its approval by the Executive Board Member for Education and Children in September 2018. The current proposal had been developed in response to the impact of the Covid-19 pandemic on the work of the Modernising Education Provision (MEP) Team and the subsequent delays in its work programme of approximately 6 months The Executive Board Member for Education & Children advised Council that if it were to adopt the Executive Board recommendation it would result in the removal of consultation with the Education and Children Scrutiny Committee from Stages 2 and 3 of the process on the Executive Board was able to approve Stage 2 and County Council Stage 3. If adopted, the revision would reduce the consultation process by approximately 2 months. The new process would then be:- Stage 1 – Education and Children Scrutiny Committee and Executive Board Stage 2 – Executive Board Stage 3 – Executive Board and Council It was noted that the Education and Children Scrutiny Committee had endorsed the proposal at its meeting held on the 23 rd November 2020. RESOLVED that the following recommendations of the Executive Board be accepted:- “That the proposal to shorten the Internal School Organisation Decision Making and Determination Process be approved and that the Education and Children Scrutiny Committee be removed from Stages 2 and 3 of the consultation process ”.
Word for word from the decision Carmarthenshire published for this meeting.Source: democracy.carmarthenshire.gov.wales
Department for Education & Children Modernising Education Programme Illustrative Flow Chart for Strategic Review and Statutory Proposals
Step 0.1 - Scoping and information gathering exercise (1-3 months)
Review & Analysis Step 0.2 – MECP Programme Board – to assess any Corporate dimensions/implications (1 month)
Step 0.3 - Analysis complete and School Review Report completed (1-3 months)
Yes
Step 0.4 – School Review Report presented to DMT for decision on whether to engage with stakeholders on options. (2 months) Approval to Engage
STAGE 0 DMT Decision Proposal No Ends
Yes Informal Engagement
Step 0.5 – Engagement commences with Local Member / Headteacher(s) / Chair of Governing Body (2 months)
Step 0.6 – Engagement with ‘other’ schools stakeholders identified in any of the school review options. (1-2 months)
Yes
Step 1.1 – A Proposal Report on preferred option, which includes stakeholder engagement feedback, presented to DMT / Permission to Proceed
CMT / E&C Scrutiny & Executive Board for decision on whether to proceed to formal consultation. (3 months)
DMT
CMT
E&C Scrutiny Committee
Proposal Executive Board No Ends
STAGE 1 Yes
Step 1.2 –At the start of the consultation period consultees provided with a consultation document and given at least 42 days to respond with at least 20 days being school days. It is not mandatory to undertake consultation meetings. (42 days minimum) Referral of consultation document to E&C Scrutiny Committee as well as other interested parties
Step 1.3 - Consultation undertaken with children and young people. As a minimum, this must include consultation with the school councils of the affected schools. This consultation must be completed within the minimum 42 days of the consultation period. Formal Consultation
Step 1.4 - If considered appropriate meetings / Drop in sessions can be held during the consultation period with stakeholders
Step 2.1- Within 13 weeks of the end of the period allowed for responses a consultation report must be published on the Authority’s website summarising each of the issue(s) raised by consultees with the Authority’s responses to the issu(s) raised.
Consultation document issued to ECS Scrutiny Committee for E&C Scrutiny Committee consideration
STAGE 2 Step 2.2 - Executive Board considers Consultation Report, views of E&C Scrutiny and Authority’s comments. Executive Board decision whether to proceed to statutory notice.
Proposal Executive Board No Ends
Yes
Continued on next page.. Continued on next page.. Continued from page 1..
Step 2.3 - Proposals published on Authority website and posted in the named and neighbouring schools and within the locality giving opportunity for statutory objections. One month period provided for written response period. (28 days)
STAGE 2 Step 2.4 - If objections received an objection report must be published providing a summary of the objections and the Authority’s responses to them.
E&C Scrutiny Committee
Step 3.1 - Executive Board considers objection report, views of E&C Scrutiny Committee and Authority’s comments. Executive Board recommendation to County Council for decision whether to approve proposal.
Executive Board
Step 3.2 – An Objection Report presented to County Council to consider any objections received in writing or e-mail and Authority’s responses. County Council makes decision to proceed or withdraw proposals.
Proposal County Council decision No Ends Statutory Procedure
Yes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.