RESOLUTION FOR SHARED USE PATH ALONG HEOL ELLI AND HEOL TROSTRE, LLANELLI

Decided Committee 2 papers

Environment (Pre May 2022) decided this item on Thursday 11 March 2021. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED that the council proceed with the resolution to convert the existing footway adjacent to Heol Elli and Heol Trostre to a shared use cycle way with a pedestrian right of way
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Environment (Pre May 2022)

EXECUTIVE BOARD MEMBER DECISIONS MEETING FOR ENVIRONMENT

11TH MARCH 2021 Executive Board Member: Portfolio: Cllr. H Evans Environment

Resolution for Shared Use Path along Heol Elli and Heol Trostre, Llanelli

Recommendations / key decisions required: That the Executive Board Member for Environment makes a resolution to convert the existing footway to a Cycle Track with a pedestrian right of way.

Reasons: It is necessary that clear evidence is shown i.e. resolution, that the Authority has exercised its powers under the Highways Act 1980 Section 66(4) and 65(1).

Directorate: Environment Name of Head of Service: Designation Tel No. Name of Head of Service: 01267 228150 S G Pilliner Head of Highways & Transport E Mail Address: Report Author: [email removed]. uk Mike Jacob Traffic & Road Safety Manager Declaration of Personal Interest (if any): None

Dispensation Granted to Make Decision (if any): N/A

DECISION MADE:

Signed: ____________________________________________________________DATE:_______ EXECUTIVE BOARD MEMBER

The following section will be completed by the Democratic Services Officer in attendance at the meeting Recommendation of Officer YES / NO adopted Recommendation of the Officer was adopted subject to the amendment(s) and reason(s) specified:

Reason(s) why the Officer’s recommendation was not adopted: EXECUTIVE SUMMARY EXECUTIVE BOARD MEMBER DECISIONS MEETING FOR ENVIRONMENT 11 MARCH 2021 Resolution for Shared Use Path along Heol Elli and Heol Trostre, Llanelli

1. Purpose It is proposed to convert the existing footway adjacent to Heol Elli and Heol Trostre Llanelli to a shared use facility for both cyclists and pedestrians. The proposals will form a wider Welsh Government grant funded road safety and active travel scheme for the area in question which will aim to encourage the increase in walking and cycling by improving existing paths and enhancing road safety especially for those travelling to local schools. The procedure to convert a footway to a cycle track involves removing the footway under Section 66(4) of the Highways Act 1980 and constructing a new cycle track with a right of way on foot under Section 65(1) of the Act. The footway will be widened to a minimum of 2.0metres and have general width of 2.5 - 3.0metres where necessary in anticipation of the proposed conversion. The new facility will be classed as a cycle track; however, it will have pedestrian right way, hence the term ‘shared use’.

2. Consultation All statutory stakeholders have been consulted, including properties fronting the path and do not object to the scheme.

3. Monitoring and Evaluation The scheme has been subjection to a Stage 2 RSA (Road Safety Audit) and will be subject to a further Stage 3 RSA upon completion and Stage 4 12months after completion. Monitoring and evaluation of the location will also be undertaken post scheme.

4. Recommendation: To proceed with the resolution to convert the remaining footway to a cycle track with pedestrian right of way.

Recommendations That the Executive Board Member for Environment

1. Make the necessary resolution

Detailed report attached: No Attached: - Appendix 1 – Shared Use Path Extents IMPLICATIONS

I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:

Signed: S. G. Pilliner - Head of Transportation and Highways

Policy and Legal Finance ICT Risk Organisational Physical Crime & Management Development Assets Disorder Issues

NONE YES YES NONE YES NONE NONE

1. Legal Exercise its powers under the Highways Act 1980 Section 66(4) and 65(1).

2.Finance All associated costs will be borne by a Welsh Government Grant

3 Risk management issues The Council has statutory duties to maintain the highway, to investigate accidents and prepare a plan for interventions subject to resource availability. It also has a duty to promote road safety. CONSULTATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 3.5 MB Download
PDF
RESOLUTION FOR SHARED USE PATH ALONG HEOL ELLI AND HEOL TROSTRE, LLANELLIReport 269 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 6 attended
HE
Cllr. Hazel EvansCommittee Member, present
GM
Gaynor MorganSecretary, expected
LJ
Llinos JenkinsOfficer Exempt Access, expected
RW
Richard WatersOfficer, in attendance
MJ
Mike JacobOfficer, in attendance
KJ
Kevin J ThomasSecretary, in attendance

More from Carmarthenshire Environment (Pre May 2022)

All decisions
MeetingDecisionOutcome
3 Dec 2021 Decisions record - 13th october 2021RESOLVED that the decision record of the meeting of the Cabinet Member for Environment held on the 13 th October 2021... Decided Open
3 Dec 2021 Stopping up of public highway at dyffryn farm, byneaRESOLVED that the Head of Administration and Law be instructed to process the stopping up of a redundant length of pu... Decided Open
3 Dec 2021 STOPPING UP OF PUBLIC HIGHWAY AT B4300 Nr. THE POLLEN, NANTGAREDIGRESOLVED that the Head of Administration and Law be instructed to process the stopping up of a redundant length of pu... Decided Open
3 Dec 2021 Stopping up of public highway at glanrhydsaeson farm, manordeilo, llandeiloRESOLVED that the Head of Administration and Law be instructed to process the stopping up of a redundant length of pu... Decided Open
13 Oct 2021 Decisions record - 25th june 2021RESOLVED that the decision record of the meeting of the Executive Board Member for Environment held on the 25 th June... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies