Resolved
RESOLVED that Parts 4.5, 4.6 and 4.7 of the Highway Asset Management Plan – Maintenance Manual be adopted.
Cabinet approved this item on Monday 13 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Parts 4.5, 4.6 and 4.7 of the Highway Asset Management Plan – Maintenance Manual be adopted.
CABINET
Date: 13th February 23
Highway Asset Management Plan – Maintenance Manual Parts 4.5, 4.6 & 4.7 Purpose: To adopt sections 4.5 to 4.7 of the Maintenance Manual in support of the Highway Asset Management Plan (HAMP) which was approved by Executive Board in July 2018. The Maintenance Manual forms Part 4 of the HAMP and is being developed as a portfolio of specific manuals covering the management of a range of highway asset categories. Parts 4.1 to 4.4 were adopted in 2021. The sections brought forward at this time cover:
Part 4.5 Highway Drainage Management Part 4.6 Geotechnical Management Part 4.7 Highway Emergency Response
Further sections will be brought forward in future years.
Recommendation: That Parts 4.5, 4.6 and 4.7 of the Highway Asset Management Plan - Maintenance Manual be adopted as detailed. Reasons: To ensure the highway network is maintained in accordance with statutory duties, supports corporate objectives and complies with the revised national code of practice ‘Well Managed Highway Infrastructure’.
Cabinet Decision Required YES (13th February 2023) Council Decision Required NO
CABINET MEMBER PORTFOLIO HOLDER:- Councillor Edward Thomas, Cabinet Member for Transport, Waste and Infrastructure Services.
Stephen Pilliner Head of Highways & [email protected] Transport
Report Authors: Richard Waters H&T Services Manager [email protected] Darren King Highway Services Manager [email protected] Chris Nelson Highway Asset Manager [email protected] CABINET 13TH FEBRUARY 2023 EXECUTIVE SUMMARY
Highway Asset Management Plan – Maintenance Manual Parts 4.5, 4.6 & 4.7
BRIEF SUMMARY OF PURPOSE OF REPORT. In 2018 Council adopted the Highway Asset Management Plan (HAMP) to ensure that the County Council manages and maintains the highway network in accordance with its statutory duties and to comply with best practice. The HAMP is in line with national codes of practice and adopts a risk-based approach which targets limited resources to areas where they are most needed and where our investment will derive greatest value. This does mean that difficult decisions have to be made and the HAMP sets out the overarching policies and methodology to ensure that those decisions are evidence led and based on an equitable and objective analysis which reduces the authority’s exposure to risk and provides best value for the long-term integrity of the highway asset. There are four parts to the HAMP:
Part 1 Explained the supporting role of the highway network in the wider policy context.
Part 2 Set out the highway network policies which are in place or being developed and our objectives adopted in managing the highway network utilising a risk-based approach.
Part 3 Comprises an Annual Statement which informs on the condition of the asset.
Part 4 A Maintenance Manual consisting of a portfolio of topic specific manuals setting out how particular elements of the highway asset are managed in line with the risk- based approach.
In December 2021 Cabinet approved the adoption of Parts 4.1 to 4.4 of the Maintenance Manual*. This covered the following areas:
• Part 4.1 Highway Maintenance Management • Part 4.2 Highway Network Hierarchy • Part 4.3 Highway Safety Inspections & Repairs • Part 4.4 Road Conditions Assessment and Investment Prioritisation * (Public Pack)Agenda Document for Cabinet, 06/12/2021 10:00 (gov.wales) This report concerns is the second set of specific manuals covering the following areas:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIGHWAY ASSET MANAGEMENT PLAN: MAINTENANCE MANUAL PARTS 4.5, 4.6 & 4.7Report | 169 KB | DownloadRead as text |
PDF |
ReportReport | 1.3 MB | Download |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.