Cabinet, Monday 26 January 2026 at 10.00am

DEVELOPMENT FUND APPLICATION

Approved Executive 2 papers

AI summaryCarmarthenshire Cabinet approved £240,000 from the Development Fund to install a new ANPR barrier system at Pembrey Country Park, repaid over five years from 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedANPR barrier system at Pembrey Country Park
Money£240,000From the Development Fund, repaid over five years
What happens nextRepayments begin 2026/27£48,000 per annum, from increased income and reduced expenditure
Who it affectsPembrey Country Park visitors and staffExisting barrier system to be replaced

What was decided

Cabinet approved £240,000 to introduce a new ANPR barrier system at Pembrey Country Park, intended to reduce expenditure and generate additional income. Report P4

The £240,000 will be repaid from the Development Fund over five years at £48,000 per annum, with repayments starting in 2026/27. Report P5, P6, P20

Why

The Authority has around £804,000 available in the Development Fund for new projects, and the ANPR scheme is expected to be self-funding through increased income and lower running costs. Report P13, P20

Staffing efficiencies are expected by redeploying staff resources elsewhere in the business, both financially and in customer relations. Report P21

What happens next

The Head of Financial Services will draw the £240,000 from the Development Fund and arrange repayments of £48,000 a year starting in 2026/27. Report P10, P11, P20

The new ANPR barrier system will be installed at Pembrey Country Park to replace the existing barrier system. Report P14

The money

  • £240,000 Development Fund loan for new ANPR barrier system at Pembrey Country Park Report P4, P20
  • £48,000 Annual repayment to the Development Fund, over five years Report P20
  • £804k Estimated balance in the Development Fund available for new projects Report P13, P20

Options considered

  • Chosen: Approve £240,000 Development Fund application for a new ANPR barrier system at Pembrey Country Park. Expected to generate increased income and reduce expenditure, with repayments of £48,000 per year over five years Report P4, P14, P20

Implications

  • Financial: Repayments of £48,000 per year will be made from increased income and reduced expenditure generated by the new barrier system. Report P20
  • Staffing: Efficiencies are expected by using staff resources elsewhere in the business, financially and in customer relations. Report P21

Who and where

  • Visitors and staff at Pembrey Country Park Report P4, P21
  • The Authority's Development Fund, which currently holds an estimated £804k Report P13, P20

Timeline

  • 26th January 2026: Cabinet considered and approved the Development Fund application Report P1
  • 2026/27: First repayment of £48,000 to the Development Fund is due to commence Report P6, P20

Plain English for the jargon

  • ANPR: Automatic Number Plate Recognition, a system that reads vehicle number plates to control entry and exit.
  • Development Fund: An internal council fund used to finance projects, with repayments returned to the fund over an agreed period.
  • Cabinet: The decision-making committee of Carmarthenshire County Council's executive.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

RESOLVED that: 9.1 Approval be given in the sum of £240,000 for the introduction of a new ANPR barrier system at Pembrey Country Park; 9.2 The repayment for the scheme be over five years; 9.3 The repayments commence in 2026/27.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Cabinet

CABINET 26th JANUARY 2026

DEVELOPMENT FUND APPLICATION

Recommendations / key decisions required:

1. Approval is given in the sum of £240,000 for the introduction of a new Automatic Number Plate Recognition (ANPR) barrier system at Pembrey Country Park, reducing expenditure and generating additional income.

2. That the repayment for the above scheme be over five years.

3. That the repayments will commence in 2026/27.

Reasons: To provide Cabinet with an update on the latest position of the Development Fund, and to seek Cabinet approval of a recent application to the Fund.

Cabinet Decision Required YES Council Decision Required NO

CABINET MEMBER PORTFOLIO HOLDER: Cllr. Alun Lenny (Resources)

Corporate Services Directorate Tel No: 01267 224886 Name of Head of Service: Designations: E Mail Address: Randal Hemingway Head of Financial Services [email protected]

Report Author: Randal Hemingway EXECUTIVE SUMMARY CABINET 26th JANUARY 2026

DEVELOPMENT FUND APPLICATION

The report provides a brief update on the Development Fund and identifies that the Authority has £804k of funds available for new projects.

This report seeks approval for the sum of £240,000 to fund the replacement of the existing barrier system with a new and improved ANPR barrier system, generating increased income. It is proposed that the repayment for the above scheme be over five years.

DETAILED REPORT ATTACHED? YES IMPLICATIONS

I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:

Signed: R Hemingway Head of Financial Services

Policy, Crime Legal Finance ICT Risk Staffing Physical Biodiversity and & Disorder Management Implications Assets Climate Change and Issues Equalities

NONE NONE YES NONE NONE YES NONE NONE

3. Finance Based on the latest profile of spending, it is estimated that there is some £804k available for new projects. The application is for £240,000 with the fund repayments of £48,000 per annum being made from increased income and reduced expenditure.

6. Staffing There are efficiencies to be gained by utilising staff resources elsewhere in the business, both financially and in terms of customer relations. CONSULTATIONS

I confirm that the appropriate consultations have taken in place and the outcomes are as detailed below Signed: R Hemingway Head of Financial Services

1. Scrutiny Committee request for pre-determination Not applicable If yes include the following information: - Scrutiny Committee Date the report was considered: Scrutiny Committee Outcome/Recommendations:

2.Local Member(s) N/A 3.Community / Town Council N/A 4. Relevant Partners N/A 5.Staff Side Representatives and other Organisations N/A

Section 100D Local Government Act, 1972 – Access to Information List of Background Papers used in the preparation of this report: THESE ARE DETAILED BELOW Title of Document File Ref No. Locations that the papers are available for public inspection

Development Fund County Hall, Carmarthen Application

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DEVELOPMENT FUND APPLICATIONReport 95 KB DownloadRead as text
PDF
ReportReport 104 KB Download

At this meeting

Whole meeting

Who was there

9 of 18 attended
CG
Cyng. Glynog DaviesCommittee Member, present
CH
Cyng. Hazel EvansCommittee Member, present
CL
Cyng. Linda EvansCommittee Member, present
CP
Cyng Philip HughesCommittee Member, present
CC
Cyng. Carys JonesCommittee Member, present
CA
Cyng. Alun LennyCommittee Member, apologies
CE
Cyng. Emlyn SchiavoneCommittee Member, present
CE
Cyng. Edward ThomasCommittee Member, present
CJ
Cyng. Jane TremlettCommittee Member, present
CA
Cyng. Aled Vaughan OwenCommittee Member, present
NS
Nia SellickOfficer Exempt Access, in attendance
CD
Cyng. Deryk CundyNon-Committee Member (Observer), in attendance, virtual

All 18 on the meeting page

On this subject at Carmarthenshire

Search all
  1. DEVELOPMENT FUND APPLICATIONThis decision
  2. Development fund proposal – shared back office support between queen elizabeth high school, carmarthen and ysgol dyffryn amman, ammanford.Approved
  3. Development fund proposal - shared back office support between queen elizabeth high school, carmarthen and ysgol dyffryn amman, ammanfordDeferred
  4. Shared prosperity fund - business research & development grantDecided
  5. Ten towns capital development fundApproved
  6. Development fund applicationApproved

More from Carmarthenshire Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. Decided Open
21 Sep 2026 Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. Decided Open
21 Sep 2026 Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. Approved Open
21 Sep 2026 Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. Approved Open
21 Sep 2026 Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies