PLANNING ENFORCEMENT

Decided Scrutiny 2 papers

AI summaryCarmarthenshire's Place, Sustainability and Climate Change Scrutiny Committee received a planning enforcement report noting over 85% of cases are investigated within an 84 day target. The service is funded from planning application fees and council tax, with no fee income from investigations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedScrutiny committee received the planning enforcement update for consideration
MoneyNot stated
What happens nextNot stated
Who it affectsPlanning service usersResidents, developers, and complainants in enforcement cases

What was decided

The committee resolved to receive the planning enforcement report. Report P4, P5

Why

Members asked for the item to be added to the forward work plan to keep abreast of and scrutinise planning enforcement matters. Report P3

The aim was to formulate views to support service development and continuous improvement. Report P7, P17

What happens next

The committee is asked to consider the information provided and the council's approach to the delivery of the planning enforcement function. Report P5

Performance is to be reviewed across CMT, Planning Committee, and the scrutiny committee, with continued focus on the Positive Action stage. Report P15, P16

Implications

  • Financial: The service is funded mainly from planning application fees set by Welsh Government, with the balance from the council's general fund. The service cannot charge for core investigation services. Report P22
  • Legal: Enforcement is a formal process that may be scrutinised in the courts. The council can apply to the courts to recover costs and use the Proceeds of Crime Act. Report P22, P23
  • Risk: There is a risk of court costs awards if the process is not followed and documented, and the council can be reported to the Local Government Ombudsman for maladministration. Report P23
  • Staffing: Focus on the Positive Action stage is likely to increase prosecutions, injunctions and legal action, raising pressure on internal legal support services. Report P24
  • Equalities: Policy, Crime and Disorder, and Equalities implications are noted, with planning enforcement underpinning the wider Development Management function. Report P21
  • Climate: Biodiversity and climate change are considered in formal enforcement decisions under section 6 of the Environment Act and the council's Nature Emergency declaration. Report P24

Who and where

  • Residents and developers subject to planning enforcement Report P13
  • Council tax payers, who fund the gap between fee income and service costs Report P22
  • Internal legal services, facing increased demand from Positive Action cases Report P24

Timeline

  • 2022: Planning Enforcement Statement published Report P14
  • 2023 to 2024: Investigation performance significantly improved, backlogs reduced Report P16
  • 2025 to 2026: Resource prioritised to the Positive Action stage Report P16
  • 84 days: Target timeline for investigating planning enforcement complaints Report P16
  • 10th March 2026: Report considered by the Place, Sustainability and Climate Change Scrutiny Committee Report P1, P10

Plain English for the jargon

  • Positive Action: Stage where formal enforcement, negotiation, appeals or prosecution occur
  • CMT: Corporate Management Team
  • Section 6 Environment Act: Statutory duty on public authorities to maintain and enhance biodiversity
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that the Planning Enforcement report be received.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Place, Sustainability & Climate Change Scrutiny Committee

PLACE, SUSTAINABILITY & CLIMATE CHANGE SCRUTINY COMMITTEE 10TH MARCH 2026

PLANNING ENFORCEMENT

Purpose: Scrutiny Members requested to include this item onto the Committee’s Forward Work Plan in order to keep abreast of and scrutinise planning enforcement matters.

THE SCRUTINY COMMITTEE IS ASKED TO:-

Consider the information provided and the Councils approach to the delivery of the Planning Enforcement function

Reason

To formulate views to support service development and continuous improvement

CABINET MEMBER PORTFOLIO HOLDER:- Cllr. Carys Jones – Cabinet Member Rural Affairs, Communities and Welsh Language

Directorate: Place, Infrastructure & Designations: Tel Nos. Economic Development 01267 222828 Name of Head of Service: Head of Place & Sustainability 01558 825373 Rhodri Griffiths

E Mail Addresses: Report Author: Senior Development & rdgriffiths@carmarthenshir Hugh Towns Enforcement Manager e.gov.uk ahtowns@carmarthenshire. gov.uk EXECUTIVE SUMMARY PLACE, SUSTAINABILITY & CLIMATE CHANGE SCRUTINY COMMITTEE 10TH MARCH 2026

PLANNING ENFORCEMENT

1. BRIEF SUMMARY OF PURPOSE OF REPORT.

Planning enforcement ensures development complies with planning law while protecting public amenity and the environment. Unauthorised development includes building without permission or breaching planning conditions. Enforcement is discretionary and must be proportionate, focused on remedying harm rather than punishing individuals.

Carmarthenshire County Council’s Planning Enforcement Statement (2022) sets out clear processes, priorities, and performance targets. About half of complaints result in no breach being found, a quarter are resolved through the investigation phase and around a quarter lead to formal action.

The service operates a structured continuous improvement approach, with performance routinely reviewed at multiple levels of the Council’s governance framework. The Planning Enforcement team monitors case progress and key performance indicators on an ongoing basis, supported by Directorate-level oversight through the Place, Infrastructure & Economic Development management team. Corporate Management Team (CMT) receives regular updates to ensure alignment with wider organisational priorities and to oversee resource allocation. Further democratic oversight is provided through the Planning Committee, which examines enforcement trends and operational effectiveness, and the PSCC Scrutiny Committee, which periodically reviews performance data, emerging pressures, and the effectiveness of improvement actions. This layered scrutiny structure ensures transparency, accountability, and a consistent focus on improvement of the Authority’s planning enforcement and related functions.

Since 2023–24, investigation performance has significantly improved, with backlogs reduced and targets consistently met. The target timeline for the Authority to investigate planning enforcement complaints is within 84-days. The Authority currently investigates over 85% of cases within the target consistently exceeding the Welsh Government’s benchmark for a “good performing authority”. In 2025 -2026 the Authority has therefore prioritised resource to provide additional focus on the “Positive Action” stage, where formal enforcement, negotiation, appeals, or prosecution occur. This further action stage often involves complex and lengthy legal processes leading to prosecution through the courts.

The service has continued to improve since 2022 having strengthened its early-stage enforcement performance is now focussing on improving outcomes at the formal stage 2 “positive action” stage. IMPLICATIONS I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:

Signed: Rhodri Griffiths Head of Place & Sustainability

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PLANNING ENFORCEMENTReport 93 KB DownloadRead as text
PDF
ReportReport 139 KB Download

At this meeting

Whole meeting

Who was there

8 of 28 attended
CK
Cyng. Kevin MadgeChairman, present
CK
Cyng. Karen DaviesVice-Chair, present
CS
Cyng. Sue AllenCommittee Member, present, as expected, virtual
CA
Cyng. Arwel DaviesCommittee Member, present, as expected, virtual
CL
Cyng. Lewis DaviesCommittee Member, present, as expected, virtual
CC
Cyng. Colin EvansCommittee Member, present, as expected, virtual
CT
Cyng. Tina HigginsCommittee Member, present, as expected, virtual
CN
Cyng. Neil LewisCommittee Member, apologies
CD
Cyng. Dorian PhillipsCommittee Member, present, as expected, virtual
CG
Cyng. Gareth ThomasCommittee Member, apologies
LG
Lle GwagCommittee Member, expected
LG
Lle GwagCommittee Member, expected

All 28 on the meeting page

On this subject at Carmarthenshire

Search all
  1. PLANNING ENFORCEMENTThis decision
  2. Planning enforcement statementApproved
  3. Draft planning enforcement statementDecided
  4. Planning enforcement - case closure protocolApproved
  5. Planning enforcement and monitoring performance indicatorsDecided
  6. Planning enforcement and monitoring performance indicators.Decided

More from Carmarthenshire Place, Sustainability & Climate Change Scrutiny Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 School transport policyRESOLVED TO RECOMMEND TO CABINET that the revised School Transport Policy, effective from 1 st October 2026, for impl... Approved Open
23 Jul 2026 Forthcoming itemsRESOLVED that the list of forthcoming items to be considered at the next scheduled meeting on the 11 th September 202... Noted Open
23 Jul 2026 To sign as a correct record the minutes of the meeting of the committee held on the 2nd june 2026RESOLVED that the minutes of the meeting of the Committee held on 2 nd June 2026 be signed as a correct record. Decided Open
2 Jun 2026 Place, sustainability & climate change scrutiny committee annual report 2025/26RESOLVED that 4.1 the Place, Sustainability and Climate Change Scrutiny Committee Annual Report for 2025/26 be receiv... Decided Open
2 Jun 2026 Forward work plan for 2026/27RESOLVED that the Place, Sustainability and Climate Change Forward Work Plan for 2026/27 with the addition of the Sec... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies