Transport, Waste and Infrastructure Services, Tuesday 17 March 2026 at 10.00am

WASTE STRATEGY UPDATE

Decided Committee 2 papers

AI summaryCarmarthenshire's Transport, Waste and Infrastructure Services committee approved a phased rollout of kerbside sort collections to 29,387 properties in the Carmarthen area, from an interim site at Nantyci. Phase 1 will cost £4,748,560.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedWest area, from Nantyci interim site
Money£4,748,560Phase 1 total spend
What happens nextOctober 2026Phase 1 rollout, subject to vehicles
Who it affects29,387 properties31.4% of the county

What was decided

The committee approved a phased rollout of the Blueprint collection model to the West area of the county, operating from an interim site at Nantyci.

It agreed to continue planning and investment for the long term, county wide transition, including development of a permanent central depot at Nant y Caws.

It agreed to put in place the operational, communication and risk mitigation measures needed for the transition.

Why

An options appraisal found a phased rollout was the only viable short term option after a previous planning application for a central depot was refused. Report P2, P3

The current comingled collection has 32 per cent contamination and is not expected to reach a potential 80 per cent recycling target by 2030. Report P4, P5

The interim phase lifted the recycling rate from 61.8 per cent in 2021/22 to 71.37 per cent in 2024/25, above the statutory minimum but short of Welsh Government ambitions. Report P2

What happens next

Procure 18 new recycling recovery vehicles and establish the interim depot at Nantyci, with combined Phase 1 costs of about £4.75 million. Report P95, P100

Confirm a definitive rollout date in Spring 2026, with options of October 2026, November 2026 or February 2027 depending on vehicle delivery. Report P97

Create five new project posts to support the Waste Transformation Project, and continue dialogue with Welsh Government on Phase 2 funding. Report P113, P125

The money

  • £4,748,560 Phase 1 total spend Report P100
  • £2,207,080 Welsh Government contribution confirmed for Phase 1 Report P102
  • £2,541,480 Carmarthenshire County Council contribution for Phase 1 Report P104
  • £1,175,000 Cost of establishing the interim facility at Nantyci Report P95, P100, P104
  • £2,732,960 Phase 1 RRV Collection Vehicles Report P100
  • £490,600 Phase 1 Reusable Recycling Containers Report P100
  • £350,000 Phase 1 Nantycaws Infrastructure Report P100
  • £31,474,480 Indicative total cost for Phase 2 county wide rollout Report P109, P112
  • £19,110,960 Welsh Government in principle contribution to Phase 2 Report P112
  • £12,363,520 Carmarthenshire County Council estimated contribution to Phase 2 Report P112
  • £36 million Total estimated project costs as of November 2025 Report P124
  • c. £15.5m Welsh Government capital funding originally approved in 2021/22 Report P98

Options considered

  • Chosen: Option 5: Phased rollout. Only viable short term solution following the options appraisal Report P3
  • Rejected: Option 6: Central depot at Cross Hands across three sites. Land restrictions under the Joint Venture clause and higher costs across three sites; not viable after engineering and property design reviews Report P3
  • Rejected: Option 7: Central depot at Capel Hendre. Insufficient space for service requirements Report P3
  • Chosen: Model A: Blueprint delivered from a single existing depot at Cillefwr. Most efficient routes, easier communication, fewer spare vehicles, focused rollout, easier training and crewing Report P7, P8, P34
  • Rejected: Model B: Blueprint distributed across three depots at Cillefwr, Glanamman and Trostre. Less efficient routes, more spare vehicles, harder communication for residents and staff Report P7, P8, P34

Implications

  • Financial: Two parallel collection systems will run during the transition, with revenue and cost implications. Report P115
  • Financial: Phase 2 funding remains uncertain, with rising infrastructure and fleet costs and pressure to increase the share of ultra low emission vehicles. Report P110, P115
  • Risk: A planning permission for the Nant y Caws central depot may not be obtainable until 2028/29 because of required A48 road upgrades. Report P117, P123
  • Risk: The Cross Hands depot lease ends in October 2027, which constrains future planning for Phase 2. Report P116
  • Legal: The Emissions Trading Scheme, due in the waste sector by 2028, could pass costs to the council if residual waste is not reduced. Report P4
  • Equalities: Some 2,660 properties (8 per cent of the Carmarthen depot area), including flats and hard to reach homes, will not transfer to Blueprint at this stage. Report P46
  • Staffing: The depot's vehicle capacity will rise from 22 to 30 and staffing from 50 to 73, with five new project posts to be created. Report P95, P125
  • Climate: The transition supports the Net Zero 2030 strategy. Phase 1 is projected to add 1.4 per cent to the recycling rate and Phase 2 a further 2.8 per cent. Report P44

Who and where

  • 29,387 properties in the Carmarthen depot area, about 31.4 per cent of the county Report P46
  • 2,660 properties (8 per cent) in the Carmarthen depot area that will remain on the existing blue bag service for now Report P46
  • Residents in listed towns and villages across the West area including Carmarthen, St Clears, Whitland, Kidwelly, Newcastle Emlyn, Llandysul, Laugharne, Pencader and others Report P46, P47, P48, P49, P50, P51, P52, P53, P54, P55, P56, P57, P58, P59, P60, P61, P62, P63, P64, P65, P66, P67, P68, P69, P70, P71, P72, P73, P74, P75, P76, P77, P78, P79, P80, P81, P82, P83, P84, P85, P86, P87, P88, P89, P90, P91, P92
  • Electoral wards of Glyn, Llanddarog, Llanybydder, Llangyndeyrn, Pontyberem, Gorslas and Llanegwad (partial impact) Report P93
  • Areas served by Glanamman and Trostre depots, which will remain on the current blue bag service during Phase 1 Report P46

Timeline

  • October 2021: Cabinet approved the Waste Strategy with targets of 70 per cent recycling by 2025 and zero waste by 2050 Report P2
  • January 2023: Interim phase launched with weekly comingled dry recycling, three weekly residual, separate glass and continued food waste Report P2
  • July 2024: Cabinet approved full Blueprint rollout and a centralised depot at Nantycaws Report P2
  • January 2025: Pre-Application Consultation refusal from SWTRA for the Nantycaws central depot due to A48 road safety concerns Report P2, P124
  • July 2025: Cabinet approved the phased approach covering around one third of the county Report P3
  • November 2025: Welsh Government confirmed £2,207,080 funding for Phase 1 and an in principle offer of around £19 million for Phase 2 Report P96, P101, P113
  • October 2026: Original Phase 1 rollout date, dependent on full vehicle delivery in September 2026 Report P96, P97
  • February 2027: Later rollout option, constrained by the pre election period for the May 2026 local elections Report P97

Plain English for the jargon

  • Blueprint: Welsh Government model requiring source segregated kerbside collections to improve recycling quality and rates
  • RRV: Recycling Recovery Vehicle, a specialist collection lorry for the new service
  • ULEV: Ultra Low Emission Vehicle
  • ETS: Emissions Trading Scheme, due to be introduced in the waste sector by 2028
  • EPR: Extended Producer Responsibility, a funding scheme whose payments depend on recycling efficiency and material quality
  • AHP: Absorbent Hygiene Products, such as nappies
  • BAU: Business as Usual, the current collection arrangements
  • SWTRA: South Wales Trunk Road Agent, which refused the Pre-Application Consultation
  • WRAP Cymru: Waste and Resources Action Programme in Wales, supporting the council on routing and design
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED to: 6.1 proceed with the phased rollout of the Blueprint collection model to the West area of the County (Carmarthen Depot Operational Area) operating from an interim site at Nantyci; 6.2 continue planning and investment for the long-term, county-wide transition, including the development of a permanent central depot at Nant-y-Caws; 6.3 implement the necessary operational, communication, and risk mitigation measures to ensure a successful transition and maintain public confidence.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Transport, Waste and Infrastructure Services

Detailed Report - Carmarthenshire Waste Service Change Update November 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ReportReport 1.5 MB DownloadRead as text
PDF
WASTE STRATEGY UPDATEReport 135 KB Download

At this meeting

Whole meeting

Who was there

1 of 6 attended
LT
Louise ToveyOfficer Exempt Access, expected
CE
Cyng. Edward ThomasCommittee Member, present, as expected, virtual
DJ
Daniel JohnOfficer Exempt Access, in attendance
MJ
Mike JacobOfficer, in attendance, virtual
JW
Janine WhiteSecretary, in attendance
YT
Yana ThomasOfficer, in attendance, virtual

On this subject at Carmarthenshire

Search all
  1. WASTE STRATEGY UPDATEThis decision
  2. Waste strategy updateNoted
  3. Waste strategy updateNoted
  4. Future waste strategyApproved

More from Carmarthenshire Transport, Waste and Infrastructure Services

All decisions
MeetingDecisionOutcome
17 Mar 2026 To sign as a correct record the decision record of the meeting held on the 28th january 2026RESOLVED that the decision record of the meeting of the Cabinet Member for Transport, Waste and Infrastructure Servic... Decided Open
17 Mar 2026 The county of carmarthenshire (imposition of 30 m.p.h. speed limit) order 2026RESOLVED that: 3.1 the objections as detailed in the report be noted; 3.2 the draft Traffic Regulation Order be made ... Noted Open
17 Mar 2026 Traffic regulation order for disabled parking spaces (llanelli) (variation no 44)RESOLVED that: 4.1 the objections as detailed in the report be noted; 4.2 the advertised Traffic Regulation Order be ... Noted Open
17 Mar 2026 Traffic regulation order for rural waiting restrictions and street parking (variation no 42)RESOLVED that: 5.1 the objection as detailed in the report be noted; 5.2 the advertised Traffic Regulation Order be m... Noted Open