Cabinet, Monday 23 March 2026 at 10.00am

CAPITAL PROGRAMME 2025/26 UPDATE

Noted Executive 2 papers

AI summaryCarmarthenshire Cabinet noted the 2025/26 capital programme update to December 2025 and agreed the new projects listed in the report. Forecast net spend is 92,823 against a working budget net of 131,167, a net variance of -38,345.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCapital programme 2025/26 report, period to December 2025
Money-38,345 (variance, £'000)Forecasted net slippage against working budget
What happens nextSlippage to future yearsMany projects scheduled for delivery in 2026/27 or later
Who it affectsAll capital programme departmentsPublic housing, education, economic development and others

What was decided

Cabinet received the capital programme update report 2025/26 covering the period to December 2025. Report P1

Cabinet noted and agreed the new projects detailed in the report, including housing, infrastructure, regeneration, schools and leisure schemes. Report P19, P22, P33, P48, P62, P64

Why

The main cause of the overall variance is the impact on the housing development programme from delays caused by additional NRW marine nitrate requirements, which are delaying planning consent on a number of developments. Report P19, P22

Welsh Government awarded additional Major Repairs Allowance in December 2025, with further funding possibly received before year end. Report P20

Slippage is widespread across Environmental Infrastructure, Economic Development, Property, Digital and Education, with many schemes planned for 2026/27. Report P33, P37, P48, P49, P60, P61, P62, P63

What happens next

Variance will reduce the level of direct revenue funding required to fund the capital programme, helping offset variances on the revenue budget. Report P19

The Ports project is expected to start incurring significant expenditure in April 2026 and continue into future years. Report P64

Bryngwyn School refurbishment, the Black Bridge project in Llanelli and Active Travel Fund projects will slip to 2026/27. Report P37, P48, P63

The money

  • 232,253 Working budget total expenditure (£'000) Report P8
  • -101,086 Working budget total income (£'000) Report P8
  • 131,167 Working budget total net (£'000) Report P8
  • 162,355 Forecasted total expenditure (£'000) Report P8
  • -69,533 Forecasted total income (£'000) Report P8
  • 92,823 Forecasted total net (£'000) Report P8
  • -38,345 Total net variance for year (£'000) Report P8
  • -19,393 Education net variance (£'000) Report P7
  • -8,711 Economic Development net variance (£'000) Report P4
  • -3,424 Public Housing net variance (£'000) Report P2

Options considered

  • Chosen: Receive the capital programme update report 2025/26. Standard monitoring report to Cabinet
  • Chosen: Note and agree the new projects detailed in the report. Standard approval of new scheme additions

Implications

  • Financial: Forecast net slippage of -38,345 against working budget net of 131,167; slippage reduces direct revenue funding required. Report P8, P19
  • Risk: Housing developments delayed by additional NRW marine nitrate requirements awaiting planning consent. Report P19, P22
  • Financial: Levelling Up Carmarthen West and Pembrokeshire South has a potential overspend due to unforeseen costs, subject to compensation events confirmation. Report P48
  • Equalities: Disabled Facility Grants show 191 applications withdrawn or cancelled, with applicants unable to meet the shortfall between the allowance and contractor quotes. Report P22
  • Other: Capital Investment Fund budget has been assigned to Capital Maintenance for operational buildings. Report P61

Who and where

  • Council tenants and housing applicants, including supported living and disabled adaptations users Report P19, P21, P22
  • Schools, pupils and ALN learners across the county Report P7, P62, P63
  • Local businesses, town centre traders and employment site tenants Report P48
  • Road users, pedestrians and active travel scheme beneficiaries Report P33, P37
  • Llanelli market traders involved in Levelling Up Llanelli relocation plans Report P48

Timeline

  • December 2025: Report period ended; additional MRA awarded by Welsh Government. Report P2, P20
  • April 2026: Ports project expected to start incurring significant expenditure; Transforming Towns Market Street North to be completed (£135k). Report P48, P64
  • August 2026: Arts and Culture retention payment due. Report P64
  • 2026/27: Slippage planned for Active Travel, Road Safety, Bryngwyn School, Ammanford Highway, Pride in Place, Rural Estates, Decarbonisation and other schemes. Report P37, P48, P49, P62, P63

Plain English for the jargon

  • MRA: Major Repairs Allowance, funding for public sector housing repairs
  • NRW: Natural Resources Wales, the Welsh environmental regulator
  • LUF: Levelling Up Fund, UK government regeneration funding
  • ALN: Additional Learning Needs
  • ASD: Autism Spectrum Disorder
  • MEP: Mutual Investment Model or similar match funding programme referenced in education projects
  • SPF: Shared Prosperity Fund, UK government replacement for EU structural funds
  • ICF: Integrated Care Fund
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that : 6.1 the capital programme update report 2025/26 be received; 6.2. the new projects as detailed within the report be noted and agreed.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Cabinet

APPENDIX A

Capital Programme 2025/26 Capital Budget Monitoring - Report for Period Ended December 2025 Working Budget Forecasted Variance for Year Expenditure Income Net Expenditure Income Net £'000 Department £'000 £'000 £'000 £'000 £'000 £'000 Public Housing 42,177 -17,494 24,683 40,933 -19,674 21,259 -3,424

Private Housing 3,238 -761 2,477 3,212 -790 2,422 -55

Social Services 8,100 -5,784 2,316 1,480 -664 816 -1,500 Environmental Infrastructure 48,675 -20,066 28,609 40,940 -13,040 27,900 -709 and Flood Economic Development 51,331 -14,292 37,039 50,606 -22,278 28,328 -8,711

Property 12,436 -2,908 9,528 9,183 -2,326 6,857 -2,671

Chief Executive 1,927 0 1,927 933 0 933 -994

Education 61,483 -38,473 23,010 13,227 -9,610 3,617 -19,393

Leisure 2,887 -1,308 1,579 1,841 -1,151 691 -888 TOTAL 232,253 -101,086 131,167 162,355 -69,533 92,823 -38,345 APPENDIX B

Capital Programme 2025/26 Capital Budget Monitoring - Report for Period Ended December 2025 Working Budget Forecasted

Variance for Year £'000 Expenditure

Expenditure Income

Income £'000

£'000

£'000

£'000

£'000

£'000 Net

Net DEPARTMENT/SCHEMES Comment

SOCIAL SERVICES AND HOUSING The main cause of the variance is the impact on the development programme from delays caused by additional NRW marine nitrate requirements delaying planning consent on a number of - Public Housing 42,177 -17,494 24,683 40,933 -19,674 21,259 -3,424 developments. This variance will however reduce the level of direct revenue funding required to fund the capital programme which will help offset any variances on the revenue budget.

Additional MRA awarded by WG in December 2025. Further funding Public Sector Housing External Funding 673 -17,494 -16,821 810 -19,494 -18,684 -1,863 maybe received before year end.

Electrical Upgrading works and Environmental works to be delivered in Supporting Tenants and Residents: 3,650 0 3,650 3,075 0 3,075 -575 future years.

Investing in Homes: 15,037 0 15,037 17,785 0 17,785 2,748 Increased spend owing to additional demand for minor works. Development programme delayed because of additional NRW marine Delivering More Homes: 18,167 0 18,167 15,109 -180 14,929 -3,238 nitrates requirements which is currently delaying planning consent on a number of developments. Works to Deliver Affordable Warmth & Underspend owing to boiler installs being untaken through the minor 4,650 0 4,650 4,154 0 4,154 -496 Decarbonisation works programme, and insulation works will continue into 2026/27. - Private Housing 3,238 -761 2,477 3,212 -790 2,422 -55 Disabled Facility Grants 2,302 -239 2,063 2,330 -267 2,063 0 Travellers Sites General 200 0 200 203 -1 202 2 Renewal Areas (Private Sector) 0 0 0 38 0 38 38 To be funded from Empty Properties Initiatives budget. ENABLE - Adaptations to Support 522 -522 0 522 -522 0 0 Independent Living Commitment to year end has been lower than projected. 191 applications have withdrawn or cancelled by applicants. Contractor Empty Properties Initiatives 214 0 214 119 0 119 -95 shortages is preventing start/completions within the Grant term. Grant rates are low and applicants are unable to meet the shortfall between the allowance and contractor quotes. - Social Services 8,100 -5,784 2,316 1,480 -664 816 -1,500 Learning Disabilities Accommodation 31 0 31 31 0 31 0 Developments Care Home Schemes 6,192 -5,252 940 398 -158 240 -700 Subject to Planning outcome. ICF Main Capital Programme 323 0 323 323 0 323 0 Housing with Care Fund (HCF) 225 -225 0 199 -199 0 0 All Wales Play Opportunities Grant 307 -307 0 307 -307 0 0 Children's In-house Residential Provision 1,022 0 1,022 222 0 222 -800 Project will be delivered in future years. APPENDIX B

Capital Programme 2025/26 Capital Budget Monitoring - Report for Period Ended December 2025 Working Budget Forecasted

Variance for Year £'000 Expenditure

Expenditure Income

Income £'000

£'000

£'000

£'000

£'000

£'000 Net

Net DEPARTMENT/SCHEMES Comment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendices A & BReport 254 KB DownloadRead as text
PDF
CAPITAL PROGRAMME 2025/26 UPDATEReport 98 KB Download

At this meeting

Whole meeting

Who was there

11 of 14 attended
CG
Cyng. Glynog DaviesCommittee Member, present
CH
Cyng. Hazel EvansCommittee Member, present
CL
Cyng. Linda EvansChairman, present
CP
Cyng Philip HughesCommittee Member, present
CC
Cyng. Carys JonesCommittee Member, present
CA
Cyng. Alun LennyCommittee Member, present
CE
Cyng. Emlyn SchiavoneCommittee Member, present
CE
Cyng. Edward ThomasCommittee Member, present
CJ
Cyng. Jane TremlettCommittee Member, present
CA
Cyng. Aled Vaughan OwenCommittee Member, present
CD
Cyng. Deryk CundyNon-Committee Member (Observer), present, as expected, virtual
KE
Kelly EvansSecretary, in attendance

All 14 on the meeting page

On this subject at Carmarthenshire

Search all
  1. CAPITAL PROGRAMME 2025/26 UPDATEThis decision
  2. Capital programme 2026/27 updateAgreed
  3. Capital programme 2025/26 updateNoted
  4. Five year capital programme (council fund) 2026/27 to 2030/31Approved
  5. Five year capital programme (council fund) 2026/27 to 2030/31Decided
  6. Five year capital programme (council fund) 2026/27 to 2030/31Noted

More from Carmarthenshire Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. Decided Open
21 Sep 2026 Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. Decided Open
21 Sep 2026 Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. Approved Open
21 Sep 2026 Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. Approved Open
21 Sep 2026 Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. Decided Open