COMMUNITY RENEWABLE ENERGY GRANT

Decided Committee 1 paper

AI summaryCarmarthenshire Council allocates £115,000 from Egni Sir Gâr to its Community Renewable Energy Grant, which already has £350,000 from the Local Growth Fund for 2026/2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved£115,000 from Egni Sir Gâr allocated to the grant
Money£115,000from Egni Sir Gâr to the Community Renewable Energy Grant
What happens nextRolling applicationscontinue until the budget is fully allocated
Who it affectsNot stated

What was decided

The £115,000 available within Egni Sir Gâr was allocated to the Community Renewable Energy Grant to support delivery of the programme.

The Cabinet Member for Climate Change, Decarbonisation and Sustainability, Cllr Aled Vaughan Evans, took the decision at the meeting on 30 June 2026. Report P2, P3

Why

Demand exceeded the available budget, with 33 expressions of interest received in the first two weeks after the grant launched on 11 May 2026. Report P30

The funding supports the Welsh Government commitment to become net zero by 2050 and the Authority's own net zero carbon goal by 2030. Report P9, P41, P43

Egni Sir Gâr Cyfyngedig, the Authority's Community Benefit Society, shares the grant's aim of reducing carbon emissions and supporting community based renewable energy. Report P31, P32

What happens next

The Bureau team, with support from the Authority's corporate energy team, will continue to administer the grant on a rolling basis until the budget is fully allocated. Report P29, P30

Approved third party applicants will be required to enter into a formal funding agreement with the Authority. Report P44

The money

  • £115, 000 available funding within Egni Sir Gâr allocated to the Community Renewable Energy Grant
  • £115,000 funding sought from Egni Sir Gâr Cyfyngedig to support grant applications Report P33, P45
  • £350,000 secured via the Local Growth Fund for the Community Renewable Energy Grant in 2026/2027 Report P29, P45
  • up to a maximum £25,000 maximum grant per project, covering up to 80% of total project costs Report P24

Options considered

  • Rejected: Reallocate the £115,000 funding elsewhere. Would not address current demand from Town and Community Councils and third sector organisations to reduce their carbon footprint Report P35

Implications

  • Legal: Successful applicants will need to enter a formal funding agreement with the Authority setting out the grant terms and conditions. Report P44
  • Climate: The grant supports Carmarthenshire's net zero carbon by 2030 aim and the Welsh Government net zero by 2050 target, and aligns with the Well-being Plan 2023 to 2028. Report P41, P42, P43
  • Other: Policy and Crime and Disorder, Finance, ICT, Risk Management, Organisational Development, Physical Assets, and Biodiversity and Climate Change implications were considered, with the latter two marked YES. Report P38, P39, P40, P46

Who and where

  • Third sector organisations across Carmarthenshire Report P5, P23, P49
  • Town and Community Councils in Carmarthenshire Report P5, P23, P49

Timeline

  • 11 May 2026: Community Renewable Energy Grant launched, with expressions of interest invited on a rolling basis Report P30
  • Within the first 2 weeks of opening: 33 expressions of interest received, exceeding the available budget Report P30
  • 09 June 2026: Report signed by Head of Place and Sustainability, Rhodri Griffiths Report P37
  • 30/06/2026: Cabinet Member Decisions Meeting for Climate Change, Decarbonisation and Sustainability Report P2, P19

Plain English for the jargon

  • Egni Sir Gâr Cyfyngedig: Carmarthenshire County Council's Community Benefit Society, set up to develop and operate renewable energy assets across the county and to fund local carbon reduction and fuel poverty initiatives.
  • Community Renewable Energy Grant (CREG): Capital grant offering up to 80% of project costs, capped at £25,000, for community venues installing renewable energy, heating, or energy efficiency measures.
  • Bureau team: The team administering the Community Renewable Energy Grant, supported by the Authority's corporate energy team.
  • Local Growth Fund: Welsh Government funding channel, via the UK Local Growth Fund in Wales, that has provided £350,000 for the grant in 2026/2027.
  • tCO2e: Tonnes of carbon equivalent, the unit applicants must estimate in carbon savings over five years as a grant output.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

RESOLVED that the £115, 000 available funding within Egni Sir Gar be allocated to the Community Renewable Energy Grant to support the delivery of that programme.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Climate Change, Decarbonisation and Sustainability

CABINET MEMBER DECISIONS MEETING

30/06/2026

Cabinet Member: Portfolio: Cllr. Aled Vaughan Evans Cabinet Member Decisions Meeting for Climate Change, Decarbonisation and Sustainability

Subject: Community Renewable Energy Grant

Purpose: To seek Cabinet Member approval to allocate funding via Egni Sir Gâr Cyfyngedi to support applications received under the Carmarthenshire Community Renewable Energy Grant.

Recommendations / key decisions required:

To authorise the allocation of funding from Egni Sir Gâr Cyfyngedig to support the Community Renewable Energy Grant, which is being managed by the Bureau team.

Reasons:

To provide the necessary support to enable third sector and town and community councils across the County to reduce their carbon footprint in line with Welsh Government’s commitment to become Net Zero by 2050.

Directorate: Designations: Place, Infrastructure & Economic Tel: 01267 234567 Development [email removed].u Rhodri Griffiths Head of Place & Sustainability k

Report Author: Economic Development Area Tel: 01269 590216 Rhian Phillips Manager [email removed].u k Declaration of Personal Interest (if any): None

Dispensation Granted to Make Decision (if any): N/A

DECISION MADE:

Signed: _____________________________________________ DATE: CABINET MEMBER

The following section will be completed by the Democratic Services Officer in attendance at the meeting

Recommendation of Officer YES / NO adopted Recommendation of the Officer was adopted subject to the amendment(s) and reason(s) specified:

Reason(s) why the Officer’s recommendation was not adopted: EXECUTIVE SUMMARY

CABINET MEMBER DECISIONS MEETING FOR CLIMATE CHANGE, DECARBONISATION AND SUSTAINABILITY

30/06/2026

SUBJECT: Community Renewable Energy Fund

SUMMARY OF PURPOSE OF REPORT

Purpose To seek Cabinet Member approval to allocate funding via Egni Sir Gâr Cyfyngedig to support applications received under the Carmarthenshire Community Renewable Energy Grant.

Background: Climate change is one of the most pressing challenges of our time, with far-reaching impacts on our environment, economy, and society. As part of the Local Growth Fund (26/27), funding has been secured to provide grant assistance to 3rd sector organisations and Town and Community Councils to decarbonise their assets via the Community Renewable Energy Grant.

The Community Renewable Energy Grant (CREG) has been established to support community venues as part of their net zero journey whilst significantly reducing their outgoings. The grant provides capital funding of up to 80% of total project costs up to a maximum £25,000 towards eligible projects. These include:

Power Systems • Small scale, single wind turbine • Solar photovoltaic panels (roof mounted/ ground mounted) • Battery linked to renewable energy systems • Grid linked battery storage system (where the tariff is with a renewable energy supplier) • Hydro-electric

Heating Systems • Air Source Heat Pump (Air to water and air to air) • Ground Source Heat Pump (vertical, horizontal, diagonal & radial) • Solar thermal panels (roof mounted/ ground mounted) Electric vehicle charging points

Energy Efficiency measures • LED lighting if replacing energy inefficient lighting. • Insulation (wall – cavity & solid, roofs/lofts, floors and pipes) As part of the application process, applicants are required to give an estimation of tonnes of carbon equivalent (tCO2e) saved over five years from installation of the system (based on pre- installation usage as compared to usage of the new system) as an output of the grant.

Programme Delivery and Funding Position:

The Community Renewable Energy Grant is being administered via the Bureau team with support from the Authority’s corporate energy team. A budget of £350,000 has been secured via the Local Growth Fund for 2026/2027.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COMMUNITY RENEWABLE ENERGY GRANTReport 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 8 attended
CA
Cyng. Aled Vaughan OwenCommittee Member, present
LJ
Llinos JenkinsOfficer Exempt Access, expected
NE
Neil EvansOfficer, in attendance, virtual
CF
Caroline FergusonOfficer, in attendance
KR
Kathryn ReesOfficer, in attendance
RP
Rhian PhillipsOfficer, in attendance, virtual
RG
Rhodri GriffithsOfficer, in attendance, virtual
JO
Julie OwensSecretary, in attendance

On this subject at Carmarthenshire

Search all
  1. COMMUNITY RENEWABLE ENERGY GRANTThis decision
  2. Carmarthenshire community renewable energy fund (creg)Approved

More from Carmarthenshire Climate Change, Decarbonisation and Sustainability

All decisions
MeetingDecisionOutcome
10 Aug 2026 To sign as a correct record the decision record of the meeting held on the 30th june 2026RESOLVED that the decision record of the meeting held on the 30 th June 202 6 be signed as a correct record. Decided Open
10 Aug 2026 Carmarthenshire community renewable energy fund (creg)RESOLVED that the following application for assistance be approved subject to the usual terms and conditions and thos... Approved Open
30 Jun 2026 To sign as a correct record the decision record of the meeting held on the 20th march 2026RESOLVED that the decision record of the meeting held on the 20 th March, 2026 be signed as a correct record. Decided Open
30 Jun 2026 Definitive map modification order (dmmo) investigation into claimed unrecorded public rights along parc pencae and maes piode, llandybieRESOLVED that the Definitive Map Modification Order (DMMO), as set out be approved and tested through due process. Approved Open
20 Mar 2026 To sign as a correct record the decision record of the meeting held on the 9 september, 2025RESOLVED that the decision record of the meeting held on the 9 th September, 2025 be signed as a correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies