APPEALS REPORT

Noted Planning 2 papers

AI summaryCarmarthenshire Planning Committee noted a report listing 8 appeals lodged, 10 in progress and 9 decided between April and June 2026, with 7 dismissals and 2 allowed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlanning Committee noted the appeals summary
MoneyNot stated
What happens nextPEDW to progress appealsAppeals in progress continue through written, hearing or inquiry routes
Who it affectsAppellants and interested partiesApplicants and residents linked to the listed appeal sites

What was decided

The committee resolved that the appeals report be noted, taking no separate decision on individual appeals. Report P9

The report set out appeals lodged, in progress and determined, and explained the appeal stages and roles. Report P12, P13

Why

The report is the standard update on planning appeal activity, which is managed by Planning and Environment Decisions Wales (PEDW). Report P9, P10, P11

It records that the council's planning decisions were not made within 8 weeks or were refused, triggering the appeals listed. Report P11, P38, P39

What happens next

Appeals in progress will be determined by an inspector through written representations, hearing or public inquiry, with decisions published on the planning casework portal. Report P17, P19, P37, P38, P39

Lodged appeals are waiting a start date from PEDW, with no comments accepted until the appeal begins. Report P29, P30, P37

For householder appeals, interested parties can only withdraw previous comments; no new comments are accepted at appeal stage. Report P40

Implications

  • Other: A backlog at PEDW means new appeals are waiting validation, with householder, advert and minor commercial cases being prioritised at present. Report P29
  • Legal: Once an appeal is in progress, no new evidence is accepted; comments after the deadline are returned. Report P37
  • Other: Determined appeals are decided by a PEDW inspector rather than the council, with the council acting only as a party to the process. Report P10, P11, P19

Who and where

  • Appellants of the 8 lodged appeals awaiting a PEDW start date Report P30, P31, P32, P33, P34, P35, P36
  • Appellants of the 10 appeals currently in progress Report P38, P39
  • Owners and neighbours of sites subject to appeals, including in Llanelli, Carmarthen, Ammanford, Trimsaran, Kidwelly, Burry Port, Laugharne and Llanfynydd Report P30, P31, P32, P33, P34, P35, P36, P38, P39, P43
  • Anyone who commented on the original applications, who will have those comments forwarded to PEDW Report P26, P40

Timeline

  • as @ 30/03/2026: Snapshot date for appeals in progress (Table 2) Report P37, P38
  • about 14 weeks: Typical timescale for written representations appeals Report P28
  • about 21 weeks: Typical timescale for informal hearings Report P28
  • about 29 weeks: Typical timescale for public inquiries Report P28
  • 4 weeks after start date: Deadline for comments on an appeal Report P24
  • 01/04/2026 to 22/06/2026: Period covered by Table 3 (appeals determined) Report P13, P41
  • as @ 22/06/2026: Snapshot date for appeals lodged (Table 1) Report P13, P29

Plain English for the jargon

  • PEDW: Planning and Environment Decisions Wales, the body that manages planning appeals.
  • HMO: House in Multiple Occupation, a property let to three or more unrelated tenants.
  • Reserved Matters: Detailed aspects of an outline planning permission that are approved in a later application.
  • One Planet Development: A Welsh policy approach allowing a single dwelling where the holder meets ecological and sustainable living criteria.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

RESOLVED that the report be noted.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Planning Committee

Cyngor Sir Caerfyrddin Carmarthenshire County Council

PWYLLGOR CYNLLUNIO PLANNING COMMITTEE

Adroddiad Pennaeth Lle a Chynaliadwyedd Adran Lle, Seilwaith a Datblygiad Ecomonaidd

Report of the Head of Place and Sustainability Place, Infrastructure & Economic Development Department

02/07/2026

APELIADAU APPEALS COMMITTEE: PLANNING COMMITTEE

DATE: 02/07/2026

REPORT OF: HEAD OF PLACE AND SUSTAINABILITY

Planning Appeals Summary

Planning and Environment Decisions Wales (PEDW) manages casework relating to the development and use of land in the public interest, and deal with planning appeals. A Guide to Engaging with Planning & Environment Decisions Wales

The local planning authority makes decisions on planning applications, and the applicant can appeal a planning decision if either they disagree with it, or the decision was not made within 8 weeks.

This report provides the following information relating to planning appeals:-

• A description of the appeal stages • The role and responsibilities of the parties • How to comment on an appeal • The appeal timescales • Table 1 - Appeals Lodged as @ 22/06/2026 • Table 2 - Appeals in Progress as @ 22/06/2026 • Table 3 - Appeals Determined between 01/04/2026 and 22/06/2026

Planning Committee 02/07/2026 - Appeals Appeal Stages

Receipt to validation Appeal submitted (‘lodged’) to Planning and Environment Decisions Wales. On receipt, they check that it is a valid appeal. If all documentation is submitted with the initial appeal the validation stage will take 3 to 5 working days.

Validation to start Once the appeal has been validated, PEDW provide the timetable for the appeal. This includes deadlines for the submission of representations and support documents.

Appeals may be considered by a Planning Inspector in one of three ways: • written representations which involve the exchange of written statements by the appellant and the Council • informal hearing • public inquiry

Start to event PEDW will identify a suitable inspector to consider the appeal submissions. The inspector will hold a site visit, hearing, or an inquiry.

Event to decision The inspector will make a final decision on the appeal based on the evidence submitted. Decisions are published on the Planning Casework portal: https://planningcasework.service.gov.wales/

Roles and responsibilities

Further guidance on the roles and responsibilities of each party in the appeals or called-in application process can be viewed here: https://www.gov.wales/planning-appeals-guidance-procedural-guide

Comment on an appeal

Anyone can comment on a planning appeal.

The deadline for comments is 4 weeks after the start date of the appeal.

The local planning authority must tell anyone who has commented on the original application (interested parties) that there’s an appeal.

We must do this within a week of the appeal being started by Planning and Environment Decisions Wales. Read the detailed guidance about taking part in an appeal.

Timescales

Most appeals are handled in writing and take about 14 weeks to determine. Informal hearings are likely to take up to about 21 weeks and public inquiries up to about 29 weeks.

Planning Committee 02/07/2026 - Appeals TABLE 1 – Planning Appeals Lodged as @ 22/06/2026 There remains a backlog of new appeals waiting to be validated and started by PEDW. For several customer service, operational and resource reasons they have taken the decision to prioritise our Householder, Advert and Minor Commercial Appeal Services by starting these appeals ahead of other casework at this time. Except for a limited number of specialist cases that require bespoke procedural administration, all other casework will be dealt with in order of date of receipt.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APPEALS REPORTReport 238 KB DownloadRead as text
PDF
Appeal AddendumAddendum 85 KB Download

At this meeting

Whole meeting

Who was there

11 of 25 attended
CT
Cyng. Tyssul EvansChairman, present
CS
Cyng. Sue AllenCommittee Member, present, as expected, virtual
CM
Cyng. Mansel CharlesVice-Chair, present
CT
Cyng. Terry DaviesCommittee Member, present, as expected, virtual
CK
Cyng. Ken HowellCommittee Member, present
CJ
Cyng. John JamesCommittee Member, apologies
CJ
Cyng. Jean LewisCommittee Member, apologies
CD
Cyng. Dai NicholasCommittee Member, apologies
CD
Cyng. Denise OwenCommittee Member, apologies
CD
Cyng. Dorian PhillipsCommittee Member, present
CE
Cyng. Edward SkinnerCommittee Member, present
CR
Cyng. Russell SparksCommittee Member, present

All 25 on the meeting page

On this subject at Carmarthenshire

Search all
  1. APPEALS REPORTThis decision
  2. Appeals reportNoted
  3. Appeals reportNoted
  4. Nominations for appointment of chairs and vice chairs of 1) appointments and investigation committee and 2) disciplinary appeals committeeApproved
  5. Appeals reportNoted
  6. Appeals reportNoted

More from Carmarthenshire Planning Committee

All decisions
MeetingDecisionOutcome
27 Aug 2026 Determination of planning applicationsRESOLVED that the following planning applications be granted subject to the conditions detailed within the Report/Add... Approved Open
27 Aug 2026 Appeals reportRESOLVED that the report be noted. Noted Open
27 Aug 2026 Planning service performance - quarter 1RESOLVED that the report be received. Decided Open
27 Aug 2026 To sign as a correct record the minutes of the meeting held on the 30th july 2026RESOLVED that the minutes of the meeting of the Committee held on 30 th July 2026 be signed as a correct record. Decided Open
30 Jul 2026 Determination of planning applicationsRESOLVED that the following planning application be granted subject to the conditions detailed within the Report/Adde... Approved Open