REDEVELOPMENT OF FRIARS PARK, CARMARTHEN

Approved Executive 1 paper

AI summaryCarmarthenshire Cabinet approves the redevelopment of Friars Park, Carmarthen, demolishing the former Wilko's building and rebuilding the car park, using £2.5m Welsh Government grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDemolish former Wilko's and rebuild car park
Money£2.5 million Welsh Government grantAdded to Council capital programme, no direct cost to Council
What happens nextNot stated
Who it affectsFriars Park site, CarmarthenTown centre businesses and nearby residents during works

What was decided

Cabinet approved the redevelopment of the Friars Park, Carmarthen site, covering demolition of the former Wilko's building and car park redevelopment. Report P3, P10

Cabinet approved inclusion of a £2.5 million Welsh Government Transforming Towns Grant into the Council's capital programme to fund the work, with no direct financial implication for the Council. Report P3, P19

The Council already owned the freehold and purchased the leasehold of the site in March 2024, giving it control to take the scheme forward. Report P19

Why

Officers reported that the former Wilko's building has reached the end of its usable life and that refurbishing the roof to relet it would cost about £1 million, which was not considered cost effective. Report P10, P20

The car park no longer meets modern parking standards or user expectations, and the report links the scheme to the Council's wider parking strategy and town centre vitality. Report P10, P21

The scheme supports the Corporate Strategy's Well-being Objective 3 on enabling healthy, safe and prosperous communities, and the Cabinet Vision Statement on the economy. Report P19

What happens next

Demolition of the former Wilko's store will be progressed via a Prior Notice of Proposed Demolition, and the car park redevelopment is to be treated as permitted development with a planning notice issued. Report P19

Works will be procured through the South West Wales Regional Construction framework, and new or varied Traffic Orders may be made to manage the car park. Report P19

The Council is in discussions with interested parties about the future use of the site, though no formal agreement has been reached yet; a biodiversity review under Schedule 6 of the Environment Act is required. Report P10, P22

The money

  • £2.5million Welsh Government Transforming Towns Grant to be added to the Council's capital programme for the Friars Park redevelopment Report P3, P19
  • £1.5m Minimum amount of the grant required to be spent in the 2026/27 financial year Report P20
  • in the region of £1million Estimated cost of roof works to make the former Wilko's building fit to relet, which the Council judged not cost effective Report P20

Options considered

  • Chosen: Proceed with demolition of the former Wilko's and redevelopment of the car park, funded by the Welsh Government Transforming Towns Grant. Building is past usable life, the car park fails modern standards, and full external funding is available Report P10, P12
  • Rejected: Do not proceed with the proposals. The building could not be relet without major investment and the car park would remain non-compliant Report P12

Implications

  • Financial: Fully funded by Welsh Government Transforming Towns Grant with no direct financial implication for the Council, subject to spending £1.5m of the grant in 2026/27 with the remainder to be spent in 2026/27. Report P3, P19, P20
  • Legal: Demolition to be progressed by Prior Notice of Proposed Demolition; car park works fall within permitted development, and new or varied Traffic Orders may be needed. Report P19
  • Risk: A risk register will be maintained; temporary impact expected on businesses in Merlin's Walk and adjoining residents while works are ongoing, with timely delivery flagged as key. Report P20
  • Equalities: Report marks equalities implications as YES, linking the scheme to active and healthy lives and to support for over 1,400 businesses. Report P18, P19
  • Climate: The prior notification application will consider biodiversity duties under Schedule 6 of the Environment Act, including a stepwise approach to existing trees and woodland. Report P22
  • Other: Scheme supports the Council's Cabinet Vision Statement on the economy and Well-being Objective 3 on prosperous communities. Report P19

Who and where

  • Town centre businesses in Carmarthen, including those in Merlin's Walk, during the works Report P20
  • Adjoining residents of the Friars Park site during demolition and car park works Report P20
  • Future users and tenants of the redeveloped site, subject to ongoing discussions Report P10, P22
  • Local members Cllr Alun Lenny, Cllr Emlyn Shiavone, Cllr Gareth John, Cllr Russell Sparks and Cllr Peter Hughes-Griffiths, who were consulted Report P27
  • Cabinet portfolio holder Cllr Hazel Evans, Deputy Leader and Cabinet Member for Regeneration, Leisure, Culture and Tourism Report P4

Timeline

  • March 2024: Council purchased the leasehold of the Friars Park site Report P19
  • 27 July 2026: Cabinet considered and approved the redevelopment and capital programme inclusion Report P1
  • 2026/27 financial year: At least £1.5m of the grant to be spent, with the remainder also scheduled in 2026/27 as stated in the report Report P20

Plain English for the jargon

  • Transforming Towns Grant: Welsh Government grant funding used to support town centre regeneration projects
  • Prior Notice of Proposed Demolition: A notification process under permitted development rights that allows a local planning authority to consider a demolition before it takes place
  • Permitted development: Development that does not require a full planning application, though the Council may still need to issue a planning notice
  • South West Wales Regional Construction framework: A procurement framework used by the Council to appoint contractors for construction works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED THAT : 8.1 the redevelopment of Friars Park, Carmarthen be approved; 8.2 the Welsh Government’s Transforming Towns Grant of £2.5million, be included into the Council’s capital programme.
Word for word from the decision Carmarthenshire published for this meeting. Source: democracy.carmarthenshire.gov.wales

Follow this further

Built from Carmarthenshire's papers

What the report saysPro

Report to Cabinet

Cabinet 27 July 2026

Subject: Redevelopment of Friars Park, Carmarthen.

Purpose: To seek approval from Cabinet to redevelop the Friars Park, Carmarthen site. Recommendations / key decisions required: Cabinet is asked to approve the following: • Redevelopment of the Friars Park, Carmarthen site. • Inclusion of the financial sum indicated below within the Council’s capital programme, to enable the redevelopment. This sum will be fully funded via Welsh Government’s Transforming Towns Grant, so there is no direct financial implication for the Council. Reasons: To allow the work to proceed to demolish the former Wilko’s building and redevelop the car park so the site is fit for purpose to be brought back into use for the benefit of the town. Cabinet Decision Required YES Council Decision Required NO

CABINET MEMBER PORTFOLIO HOLDER:- Cllr Hazel Evans, Deputy Leader and Cabinet Member for Regeneration, Leisure, Culture and Tourism Directorate: Designations: Tel: [phone removed] Corporate Services

Name of Head of Service: Head of Capital Email addresses: Alex Williams Projects [email protected]

Report Author: Head of Capital Alex Williams Projects

JAN 2024 EXECUTIVE SUMMARY

SUBJECT Friars Park Development Briefing Paper

1. BRIEF SUMMARY OF PURPOSE OF REPORT.

The report provides a summary of the proposal to redevelop the Friars Park, Carmarthen site which includes the demolition of the former Wilko’s building at Friar’s Park, Carmarthen and redevelopment of the surrounding car park. The former Wilko’s building has reached the end of its usable life and the car park no longer meets modern parking standards. It is therefore necessary to demolish the building and redevelop the car park to ensure that the site can be further developed to bring it back into use for the benefit of the town. The work itself is being fully funded by the Welsh Government Transforming Towns Grant and the Council is required to include this allocation within its Capital Programme to allow the work to proceed. The Council is in discussions with interested parties about the future use of the site, but at this stage no formalised agreement has been reached.

2. OTHER OPTIONS AVAILABLE AND THEIR PROS AND CONS

The Council would not proceed with the proposals. However, the current building on the site is past its usable life, and without considerable investment, the Council would not be able to relet the building to a suitable tenant. In addition, the current car park does not comply with modern parking standards and expectations.

DETAILED REPORT ATTACHED? NO

JAN 2024 IMPLICATIONS

I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:

Signed: Alex Williams Head of Capital Projects

Policy, Legal Finance ICT Risk Staffing Physical Bio- Crime & Manage- Implications Assets diversity & Disorder ment Issues Climate and Change Equalities

YES YES YES NONE YES NONE YES YES

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REDEVELOPMENT OF FRIARS PARK, CARMARTHENReport 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
CG
Cyng. Glynog DaviesCommittee Member, present, as expected, virtual
CH
Cyng. Hazel EvansCommittee Member, present
CL
Cyng. Linda EvansChairman, present
CP
Cyng Philip HughesCommittee Member, present
CC
Cyng. Carys JonesCommittee Member, apologies
CA
Cyng. Alun LennyCommittee Member, present
CE
Cyng. Emlyn SchiavoneCommittee Member, present
CE
Cyng. Edward ThomasCommittee Member, present
CJ
Cyng. Jane TremlettCommittee Member, present
CA
Cyng. Aled Vaughan OwenCommittee Member, present, as expected, virtual
SW
Stuart WaltersOfficer, in attendance
AW
Alex Williams (Head of Health Related Capital Projects)Officer, in attendance

All 17 on the meeting page

More from Carmarthenshire Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. Decided Open
21 Sep 2026 Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. Decided Open
21 Sep 2026 Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. Approved Open
21 Sep 2026 Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. Approved Open