What was decided
The Head of Planning and Growth and the Head of Legal and Electoral Services may enter into a section 106 agreement. It must secure improvements, including the self build and off site habitat requirements, with terms finalised by the parties.
Planning permission was granted conditionally, subject to completion of the section 106 agreement. The conditions and reasons are those in the Head of Planning and Growth's report as amended by the Extras Report.
The Head of Planning and Growth was given delegated authority to determine the final detail of planning conditions. Amendments to the conditions and reasons are to be made in consultation with the Chair of the Plans Committee.
Why
The agreement is intended to secure improvements for the development.
The development must be constructed and initially occupied as a self build house.
The agreement must secure 0.08 units of off site habitat.
What happens next
Negotiate and enter into the section 106 agreement. Its terms are to be finalised by the parties.
Complete the section 106 agreement as a condition of planning permission.
The Head of Planning and Growth should determine the final planning condition details. Amendments to conditions and reasons should be made in consultation with the Chair of the Plans Committee.
Options considered
- Chosen: Grant planning permission conditionally with a section 106 agreement. The agreement must secure the self build and off site habitat requirements.
Implications
- Legal: Planning permission is conditional on completion of the section 106 agreement.
- Legal: The agreement is under section 106 of the Town and Country Planning Act 1990.
- Other: The development must be constructed and initially occupied as a self build house.
- Environment and climate: The agreement must secure 0.08 units of off site habitat.
- Legal: The agreement terms are to be finalised by the parties.
- Governance: The Head of Planning and Growth may determine final planning condition details in consultation with the Chair of the Plans Committee.
Who and where
- The applicant
- Initial occupants of 289 Forest Road
Timeline
- 2025-11-25: The Plans Committee authorised the section 106 agreement and granted conditional planning permission.
- Subject to the completion of the S106 agreement: Conditional planning permission applies to 289 Forest Road.
Plain English for the jargon
- Section 106 agreement: An agreement under section 106 of the Town and Country Planning Act 1990 to secure improvements for the development.
- Off site habitat units: Habitat provision required away from the development site, with 0.08 units to be secured.
- Delegated authority: Authority for the Head of Planning and Growth to determine final planning condition details, with the Chair of the Plans Committee consulted.