RESOLVED THAT 1.1 CBH be approved to pursue the options as set out below, with a view to identifying a viable option for each site based on costs, designs, ownership and risks for approval by Cabinet. i ) St. Pauls Phase 2 – options one, two, three and four ii) Cakebridge Place - options one, two, three and four iii) Garages – options one and two (with the addition of grant if reallocation by HCA secured). 1.2. CBH be assisted in identifying the most viable option for each site, CBH be authorised to undertake any necessary procurement exercises to identify a suitable developer partner who will provide a developer grant and/or capital as required, provided that no partner shall be selected until a report on the preferred developer partner(s) and the appropriate value for money tests is approved by Cabinet. 1.3 Authority be delegated to the S151 Officer in consultation with the Cabinet member Housing and Safety, Cabinet Member Finance and Community Development and Director Commissioning to approve any submission by CBH to be the registered provider for the development at North Place based on a nil subsidy approach which secures good value for money for the council and for CBH . 1.4 It be noted that CBH will ... view the full minutes text for item 6.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 13 March 2012 Cheltenham Borough Homes Development Options Review
Accountable member Councillor Klara Sudbury, Housing and Safety
Accountable officer Jane Griffiths, Director, Commissioning
Accountable scrutiny Social and Community committee
Ward(s) affected St Paul’s, Oakley
Key Decision No
Executive summary The Council, on 13th February, 2009, approved a capital strategy which confirmed that Cheltenham Borough Homes (CBH) is its preferred development partner, supported in principle on the basis of prudential borrowing, capital subsidy and transfer of land at nil value. Cabinet, on 21st April 2009, in response to the capital strategy, also agreed in principle to support of the submission of grant funding bids to the Homes and Communities Agency (HCA).
In April 2011 the cabinet approved a submission by CBH, through a consortium with Bromford Housing, for HCA affordable homes grant funding under the affordable rents programme to deliver a number of sites. Unfortunately the bid submitted by the consortium was unsuccessful.
Officers from CBH have been considering what alternative funding streams may be available to ensure that these sites can be delivered and working with CBC officers have considered a number of different options which are set out in this report. If CBH are able to access affordable homes grant through a third party (developer or RP) then this could reduce the need for CBC subsidy.
In addition to the schemes which were in the original consortium proposals, CBH have been approached along with other registered providers (RP) as to whether they would be interested in being the RP for the scheme on North Place. At the time of writing the report, the developers in response to the feedback from the RPs are reviewing the design layout and will be approaching providers for bids in the near future.
Any proposals finally endorsed would need to ensure that they provided value for money and a final decision would need to be made as to whether they are CBH or CBC properties.
The report also outlines a proposed change to the management agreement schedule which will enable a more efficient procedure for controlling and monitoring reactive repairs for council dwellings, by enabling all expenditure on reactive repairs to the stock to be consolidated through CBH. At present CBH manage certain reactive repairs contracts on our behalf, and with the implementation of the new finance and HR system there is an opportunity to consolidate the work so that it links better with the CBH repairs systems and
$c0clpdfk.doc Page 1 of 16 Last updated 02 March 2012 processes and enables more effective management of contracts and spend.
Recommendations 1.1 approve CBH pursuing the options as set out below, with a view to identifying a viable option for each site based on costs, designs, ownership and risks for approval by Cabinet.
i) St. Pauls Phase 2 – options one, two, three and four
ii) Cakebridge Place - options one, two, three and four
iii) Garages – options one and two (with the addition of grant if reallocation by HCA secured).
1.2.To assist CBH in identifying the most viable option for each site, authorise CBH to undertake any necessary procurement exercises to identify a suitable developer partner who will provide a developer grant and/or capital as required, provided that no partner shall be selected until a report on the preferred developer partner(s) and the appropriate value for money tests is approved by Cabinet
1.3Delegate authority to the S151 Officer in consultation with the cabinet member housing and safety, cabinet member finance and community development and director commissioning to approve any submission by CBH to be the registered provider for the development at North Place based on a nil subsidy approach which secures good value for money for the council and for CBH.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.