RESOLVED that: ( i ) CBH be mandated to secure the best available deal from developers in respect of net construction cost for the three schemes. (ii) CBH can continue contractual negotiations such that early planning submissions can be made in respect of Cakebridge Place and Crabtree Place . (iii) CBH be mandated to act in respect of decanting tenants and securing the freeholds of privately owned properties, in full consultation with affected persons and subject to acceptance of appropriate terms and rehousing options. (iv) The decision with regard to ownership of the developments be delegated to Grahame Lewis, Executive Director, in consultation with the Cabinet Member Housing & Safety, Section 151 Officer and CBH following receipt of legal advice. This decision is to be made prior to any contractual commitment being entered into with any developer. (v) If the decision at (iv) is for CBH to own the completed properties the council will, subject to all necessary consents being received from the Secretary of State, agree to transfer land as required at nil cost (on the assumption ... view the full minutes text for item 8.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 16th October 2012 Cheltenham Borough Homes – Development Options Review
Accountable member Councillor Jeffries, Cabinet Member Housing and Safety
Accountable officer Grahame Lewis, Executive Director
Ward(s) affected St Pauls
Key Decision Yes
Executive summary In March of this year CBH were mandated by the Cabinet to review development options for Crabtree Place (24 properties), Cakebridge Place (20 properties) and four garage sites (14 properties). CBH were also requested to seek a development partner for these schemes following the completion of an appropriate competitive selection process.
Recommendations The above actions have now been satisfactorily completed and I would therefore make the following recommendations that:
(i) That CBH be mandated to secure the best available deal from developers in respect of net construction cost for the three schemes.
(ii) That CBH can continue contractual negotiations such that early planning submissions can be made in respect of Cakebridge Place and Crabtree Place.
(iii) That CBH be mandated to act in respect of decanting tenants and securing the freeholds of privately owned properties, in full consultation with affected persons and subject to acceptance of appropriate terms and rehousing options.
(iv) The decision with regard to ownership of the developments is delegated to Grahame Lewis, Executive Director, in consultation with the Cabinet Member Housing & Safety, Section 151 Officer and CBH following receipt of legal advice. This decision is to be made prior to any contractual commitment being entered into with any developer.
(v) If the decision at (iv) is for CBH to own the completed properties the council will, subject to all necessary consents being received from the Secretary of State, agree to transfer land as required at nil cost (on the assumption that the capital receipt from sales land values at St Pauls will be used to subsidise development costs) and provide financial support through the affordable housing reserve and provide access to PWLB borrowing.
Cabinet 16 10 12 Page 1 of 10 Last updated 05 October 2012 CBH – Development Options Review Version 2 Financial implications As outlined in sections 4 and 5 of this report.
Cabinet 16 10 12 Page 2 of 10 Last updated 05 October 2012 CBH – Development Options Review Version 2 Legal implications Disposing of land held for housing purposes under the Housing Act 1985 requires the consent of the Secretary of State. In the 13 March 2012 cabinet report I stated that CBC could rely on a general consent issued by the Secretary of State to sell land to CBH. However, as a result of revised general consents issued in May 2012 the council must now obtain a specific consent from the Secretary of State to transfer dwellings to CBH if it is to transfer more than 5 dwellings in any financial year. This is because the new general consents prohibit the transfer of more than 5 dwellings in any financial year to registered providers in which councils own an interest.
The council can rely on general consent A3.2 to dispose of the garage sites or any other land which does not comprise dwellings to CBH.
A number of the options mentioned in this report will involve the council transferring housing land at nil value and giving grants or granting loans to CBH. As Cheltenham Borough Homes has gained Registered Provider status under the Housing and Regeneration Act 2008, the Council is able give it financial support to enable it to develop land for housing accommodation by relying on a general consent issued by the Secretary of State, namely “The General Consent Under Section 25 of the Local Government Act 1988 for the disposal of land to registered providers of social housing”.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.