RESOLVED THAT When undertaking service re-design, and commissioning the service, the Council requires the future service provider to identify and implement innovative services/schemes in an effort to combat the affects of welfare reform on the most vulnerable households. ( Para 4.1.6) Housing Options Management continue to pursue enhancements to the Homeseeker system and that the necessary training and changes to processes identified through systems thinking are progressed. ( Para 4.2.5) the conclusion that there are 2 potential commissioning options for Housing Options be endorsed, i.e. in-house and transfer the service to CBH and that a further report be brought back to Cabinet in May 2013 recommending the proposed commissioning option. ( Para 4.3.9)
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Accountable member Councillor Peter Jeffries, Cabinet Member Housing and Safety
Accountable officer Pat Pratley, Executive Director
Ward(s) affected All
Key Decision No
Executive summary Housing Options delivers the Council’s statutory duties towards households who are homeless or in housing need, as required under the Housing Act 1996. The service performs well and the staff work with and provide support to some of the most vulnerable people within the community of Cheltenham.
Earlier this year the Council adopted its new Housing and Homelessness Strategy in response to the impending welfare reforms announced by Government. The strategy outlines the outcomes the Council wishes to achieve to prevent homelessness in the Borough.
In anticipation of the welfare reforms, the Council had already committed to review its Housing Options service to make sure that it was fit for purpose and also to consider how the service may be commissioned in the future.
The commissioning review has reached the conclusion, at the end of the analysis phase, that there are 2 potential commissioning options available; in-house provision or, alternatively, to transfer the service to a registered provider, in this case the Council’s Arms Length Management Organisation (ALMO), Cheltenham Borough Homes (CBH).
CBH is a 3 star ALMO. During the autumn CBH will, together with its stakeholders, including the Council, be considering its future service priorities, seeking to build upon its excellent performance record as well as its community engagement and community development role. Commissioning Housing Options on behalf of CBC will be one of the service options that CBH will consider.
In the meantime, the in-house Housing Options team will consider how the service needs to adapt, or consider new service delivery methods to achieve the Council’s stated outcomes for homelessness prevention. This thinking and work is necessary regardless of who delivers the service in the future as it will form the basis of a service specification/service plan against which the provider will be judged against on delivery and performance.
\\mudata\mgdataroot\published\Intranet\C0000016 Page 1 of 12 Last updated 29 November 2012 6\M00001858\AI00004494\$eliuuuqo.doc Recommendations 1. When undertaking service re-design, and commissioning the service, the Council requires the future service provider to identify and implement innovative services/schemes in an effort to combat the affects of welfare reform on the most vulnerable households. (Para 4.1.6)
2. Housing Options Management continue to pursue enhancements to the Homeseeker system and that the necessary training and changes to processes identified through systems thinking are progressed. (Para 4.2.5)
3. Cabinet endorse the conclusion that there are 2 potential commissioning options for Housing Options, ie, in-house and transfer the service to CBH and that a further report be brought back to Cabinet in May 2013 recommending the proposed commissioning option. (Para 4.3.9) Financial implications A reduction of £30,000 in the cost of the existing service has been identified (paragraph 2.2). There are no direct financial implications arising from this report. The financial implications of potentially commissioning the service will be considered as part of the commissioning review and reported to Cabinet in May 2013.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.