RESOLVED that it be recommended to Council that: 1. the revised HRA budget and capital programme for 2012/13 be noted. 2. the HRA budget for 2013/14 as shown at Appendix 2 including a proposed average rent increase of 3.43% (applied in accordance with national rent restructuring guidelines) and increases in other rents and charges as detailed at Appendix 5 be approved. 3. the 2013/14 HRA capital programme as shown at Appendices 3 and 4 be approved. the 2013/14 management fees and charges for Cheltenham Borough Homes as detailed in Section 4 be approved.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
1.1The draft revenue budgets approved by Cabinet on 21st December 2012 have been updated as follows:-
• Management costs have been increased by £30,000 to support the continuation of the Inspiring Families Project.
• Estimates of service charge income have been increased by £8,500 following the finalisation of charges for next year.
1.2The HRA budget proposals for 2013/14 reflect the impact of the new self financing regime for local authority housing. In February 2012 the Council approved a new 30 year HRA business plan which anticipated significant additional resources arising from the implementation of self financing. The Council also approved a strategy to use these resources to finance a programme of new build, further improvements to existing stock and additional support services for tenants. CBH was requested to bring forward delivery plans to meet these objectives and those plans are described in this report.
2. 2012/13 Revised Budget
2.1The revised budget at Appendix 2 shows an increase in surplus for the year of £61,400 compared to the original estimate. This additional surplus, together with an increase of £385,200 in the balance brought forward from 2011/12, will give revenue reserves of £3,113,000 at 31st March 2013.
2.2Significant variations have been identified in budget monitoring reports and are summarised below:-
Budget Heading Change in resources £’000 Reduction in interest payable - lower rate achieved on debt settlement 214 Supporting People – existing contract extended 75 Transfer from Major Repairs Reserve – confirmation of accounting practice 94 Revenue contributions to fund capital programme – additional expenditure -360
Page 2 of 10 Last updated 28 January 2013 on pv pilot scheme Other net 38 Net Increase in Surplus 61
3. 2013/14 Budget
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.